Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 185
Entry time: 09 Dec 2020, 10:24
|
Author: |
Frederik Wolff-Fabris |
Location: |
General |
Severity: |
Information |
Subject: |
Notes XO Integration Meeting 09.12.2020 |
|
|
General Announcement:
- Regarding the e-mail related to the general radiation training and procedure to deliver a signed certificate, one can also send it by conventional post to Zunaira A.
CTRL:
- BKR machines has been updated to the new Karabo release.
- The Notification service update will follow form today.
- CTRL reminds on getting configuration from the timing feature on the GUI: right click on the device and then "get configuration".
An e-mail with detailed instructions will be sent today.
DA:
- Nothing to report.
EEE:
- Fast electronics: SASE3 maintenance is finished; SA2 will follow.
- PLC side: SQS has some loops running but not all of them due to the cooling issue. SCS will get their loops soon running.
- Cabling works at FXE is completed; at HED is ongoing.
VAC:
- Not present due to tunnel activities.
XPD:
- XPD has completed PES beamtime at Petra. Would like to thank ITDM for the smooth work. XPD has collected data for over 300 runs.
- Today XPD brings back other PES to SA3 tunnel. There is an appointment with MEA and the plan is to connect to the beamline tomorrow together with VAC.
- A. Koch asks EEE at CTRL if DAQ tests on XPD tunnel devices can happen on Friday.
Nerea J. points SA3 is not yet commissioned (has to check motors) but SA1 and SA2 can be done on Friday as it has only pending vacuum update.
Steffen H. says that cameras can be tested in all 3 SASEs; connections shall be fine; requests a list of all cameras.
Jan G. adds the idea is to verify the components can be operated and acquire data, following a test with XPD/ITDM.
Steffen H. reminds that for testing the digitizers one has to re-start (faster ADC) the device server.
DET:
- Not present.
ITDM:
- Nothing to report.
XRO:
- Nothing present.
LAS:
- Lasers are on good track.
- Interlock tests: there was miscommunication. The SA2 AMPHOS is disassembled for maintenance and therefore the PP-laser test in SA2 is postponed to next week.
UNSYS:
- Not present.
SPB:
- Nearly done with putting together the AGIPD. The Final test for DQA begin next week.
- Problem with timing but currently it has been running on local mode.
FXE:
- Not present.
MID:
- All fine at MID.
HED:
- Nothing to report.
SCS:
- Not present.
SQS:
- Nothing to report.
- SQS has ongoing work on Beckhoff crates. |