645
|
10 Sep 2025, 10:31 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 10.09.2025 |
General Announcement:
- M. Doering announces on the LIMP-25:
1. XTD10 Scaffolding is installed for cabling work in October;
2. PLC updates: remaining work in tunnels to be done next week (discussed with VAC and XPD) as well as at SQS;
3. Update task list: M. Doering will send to the groups the Task list for that it is updated accordingly to the latest status (e.g. completed, cancelled, delayed...);
4. Recurring tasks for the Winter Maintenance will be planned for the end of the year. A list will be sent to the groups and please inform XO if you have new activities to be done before 2026.
CTRL:
- Karabo upgrade: start with MID next week to spot possible issues. MID topic will be accessible from the hutch only.
DA:
- Nothing to report.
EEE:
- PLC updates: see above.
VAC:
- Everything progressing well in XTD6 also with PLCs.
XPD:
- Nothing to report.
DET:
- Nothing to report; starting AGIPD at MID before Karabo is down in October.
ITDM:
- Nothing to report.
- Fast-X gateway upgrade last week is done.
XRO:
- Busy with SA1 activities.
LAS:
- Not present.
UNSYS:
- Delays with water and cable from Desy groups; but all ongoing.
SPB:
- Not present.
FXE:
- Nothing to report.
MID:
- MID control room is very warm: needs to check temperatures in control room; Gerd W. says technical infrastructure needs to be modified.
HED:
- Nothing to report.
SCS:
- Issue with installation of beam stop and AIBS position.
SQS:
- Not present.
SXP:
• Not present. |
644
|
08 Sep 2025, 09:42 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 08.09.2025 |
General Announcement:
- Regarding LIMP-25, there is nothing different apart of what was already mentioned on Wednesday for this week cw37.
CTRL:
- Nothing to report.
DA:
- Nothing to report.
EEE:
- Nothing to report.
VAC:
- Nothing to report.
XPD:
- Nothing to report.
DET:
- Nothing to report.
ITDM:
- Activity with electricity in Balcony room 30 was finished on Friday. DESY crates can be switched on again.
XRO:
- Not present.
LAS:
- Not present.
UNSYS:
- Everything is fine.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- All fine.
HED:
- Nothing to report.
SCS:
- Nothing to report.
SQS:
- Not present.
SXP:
- Nothing to report. |
643
|
03 Sep 2025, 10:29 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 03.09.2025 |
General Announcement:
- LIMP-25: next week cw37 sees the PLC updates starting in SPB/SFX and SQS; also the re-installation of AIBS will be completed.
CTRL:
- Nothing to report.
DA:
- Nothing to report.
EEE:
- Nothing to report.
VAC:
- Not present.
XPD:
- Not present.
DET:
- Nothing to report.
ITDM:
- Upgrade of Fast-X gateway: to be done this week. When finished, an e-mail will be sent to xo-info.
XRO:
- Not present.
LAS:
- Not present.
UNSYS:
- Nothing to report.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- All is fine.
HED:
- Nothing to report.
SCS:
- Nothing to report.
SQS:
- Nothing to report.
SXP:
- All fine. |
642
|
01 Sep 2025, 09:37 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 01.09.2025 |
General Announcement:
- There are no general updates regarding LIMP-25.
CTRL:
- No major updates from CTRL.
DA:
- Nothing to report.
EEE:
- PLC updates in tunnels: coordinating with VAC and XPD and updates are still ongoing this week.
VAC:
- Nothing to report.
XPD:
- Nothing to report.
DET:
- Nothing to report. All fine.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Nothing to report.
UNSYS:
- Nothing to report.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
- Construction of 2nd control hutch at FXE is ongoing accordingly to the plan.
MID:
- All fine at MID.
HED:
- Not present.
SCS:
- Nothing to report.
SQS:
- Not present.
SXP:
- Nothing to report. |
641
|
27 Aug 2025, 09:30 |
Andreas Galler | General | Information | Notes XO Integration Meeting 27.08.2025 |
General Announcement:
- Martin shows the preview for cw36,
- Implementation of central gas management
- safety lights maintenance
CTRL:
DA:
EEE:
VAC:
XPD:
DET:
ITDM:
XRO:
LAS:
UNSYS:
SPB/SFX
FXE:
MID:
HED:
SCS:
- small leakage yesterday in th ooling water circuit for the Turbo Pumps in the experiment
SQS:
SXP:
DRC
PRC
AOB:
|
640
|
25 Aug 2025, 09:28 |
Andreas Galler | General | Information | Notes XO Integration Meeting 25.08.2025 |
General Announcement:
- Martin Doering
- XTD6 today maintenance of cooling water pumps --> fluctuations can occur
- Safety: a couple of EPDs have not been logged out
CTRL:
DA:
EEE:
- Tunnel PLCs
- issues are being addressed with VAC & CTRLs
- FXE&SPB?SFX Beckhoff CPUs to be replaced
VAC:
XPD:
DET:
ITDM:
XRO:
LAS:
UNSYS:
SPB/SFX
- AIBS work will happen this week
- 4M installation infrastructure going forward as planned
FXE:
MID:
HED:
SCS:
SQS:
SXP:
DRC
PRC
AOB:
|
639
|
20 Aug 2025, 09:43 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 20.08.2025 |
General Announcement:
- Martin Doering announces on the LIMP-25 (Main infrastructure works are ending in general):
1. Water related activities will be finished this week;
2. Air conditioning will work again next week;
3. Guest House also will be opening again next week;
4. Electricity: tasks are finishing next week and minor tasks in SA1 and SA3 instruments will be discussed to be scheduled in future;
5. PLC updates are still ongoing in tunnels over next week;
6. AIBS and Air Boxes will be reinstalled next week;
7. MKK2 cooling water pump replacement in XHEXP1 takes place (there is a redundant pump system so it is a task without impact).
- M. Prollius says the NDR TV crew will be at XFEL after lunch and will go to XTD1 by 13:00, maybe also at XHEXP1.
CTRL:
- Nothing to report.
DA:
- Nothing to report.
EEE:
- Nothing apart of the PLC updates (see above).
VAC:
- Not present.
XPD:
- Nothing to report.
DET:
- X-ray pulse source that suffered from the power cut: depends on experts return from holidays.
ITDM:
- Nothing to report.
XRO:
- Not present.
LAS:
- Nothing to report.
UNSYS:
- Not present.
SPB:
- Nothing to report.
FXE:
- Not present.
MID:
- Nothing to report.
HED:
- Not present.
SCS:
- Not present.
SQS:
- Nothing to report.
SXP:
- All good at SXP. |
638
|
18 Aug 2025, 09:36 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 18.08.2025 |
General Announcement:
- O. Bilani informs transport and crane activities are being made at truck bay today. Please be careful when walking around.
- M. Prollius informs on Wednesday afternoon the NDR is making footages at undulator tunnels, organized by COMS.
CTRL:
- Nothing major to report.
DA:
- Nothing new / to report.
EEE:
- Work on PLC updates this week in tunnels and then moving forward to instruments.
VAC:
- Nothing to report.
XPD:
- Nothing to report.
DET:
- Not present.
ITDM:
- Nothing to report.
- Maxwell upgrades went fine and hiccups were fixed successfully.
XRO:
- Not present.
LAS:
- Nothing to report.
UNSYS:
- Nothing to report.
- Alignment MEA started working with UNSYS tasks.
SPB:
- Nothing to report.
FXE:
- Not present.
MID:
- All fine at MID.
HED:
- Not present.
SCS:
- Nothing special to report.
SQS:
- Nothing to report.
SXP:
- Everything fine for SXP. |
637
|
13 Aug 2025, 09:50 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 13.08.2025 |
General Announcement:
- A. Galler informs on the LIMP-25 plans for next week:
1. TS tasks: last week with water, dehumidification activities;
2. Karabo PLC updates in tunnels ending next week;
3. Ramp up activities apart of FXE will be ending.
- Issue with SA1 PP-laser air conditioning on Tuesday 12.08: T. Clever says an incident in preparation works at D.14 SPB hutch result in valves not been properly closing so that water leaked.
Emergency solution was to shut down the 8C cooling water. Increased temperature in hutches of about 1-2C was measure. After fixing the system the temperatures were back to normal operation.
- A. Galler reminds that this XO integration meeting is the main platform to exchange and receive information between groups.
Please use this platform to share and have discussions between support groups and scientific instruments.
- M. Prollius says a team from NDR may visit tunnels next week for footage. A timetable will be communicated in coming days (likely on Wednesday afternoon). XO will discuss with Communications group.
CTRL:
- Nothing major to report.
DA:
- Nothing to report.
EEE:
- Working with VAC in tunnel deployments.
VAC:
- Nothing to report.
XPD:
- Nothing to report.
DET:
- Nothing to report.
ITDM:
- Not present.
XRO:
- Not present.
LAS:
- Not present.
UNSYS:
- Nothing to report; no news on the work of Desy alignment group - seems that today they may start working in SASE1 with drilling activities.
SPB:
- Nothing to report.
FXE:
- Not present.
MID:
- Not present.
HED:
- Not present.
SCS:
- Nothing to report.
SQS:
- Nothing to report.
SXP:
- Nothing to report. |
636
|
11 Aug 2025, 09:39 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 11.08.2025 |
General Announcement:
- A. Galler informs that regarding the LIMP-25 scheduling there is nothing new as compared to what was announced last Wednesday.
CTRL:
- Karabo 3 has been released. In case of any for assistance please do not hesitate in contacting CTRL groups.
DA:
- Nothing to report.
EEE:
- No issues; Loop updates in tunnels are ongoing.
VAC:
- Everything fine.
XPD:
- Nothing to report.
DET:
- AGIPD chiller has been recovered.
ITDM:
- Tomorrow in the morning there will be maintenance of Maxwell log in nodes, as announced per e-mail. Jobs that are running will not be affected.
XRO:
- Not present.
LAS:
- Nothing to report.
UNSYS:
- Nothing to report.
SPB:
- Nothing to report.
FXE:
- Not present.
MID:
- Nothing to report.
HED:
- Nothing to report.
SCS:
- Nothing to report.
SQS:
- Nothing to report.
SXP:
- Not present. |
635
|
06 Aug 2025, 09:40 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 06.08.2025 |
General Announcement:
- A. Galler informs on the LIMP-25 for next week:
1. Water: dirty traps maintenance ongoing in all tunnels but without interruptions, only changes in water pressure;
2. Limited AC and humidification control is expected;
3. Central hot water maintenance ongoing;
4. PLC updates ongoing in some areas (SA1/3 tunnels);
5. Last instrument racks ramping up next week;
6. No electricity interruptions are planned for next week.
- M. Prollius informs that constructions in the campus / roads near the shaft buildings will be taking place in order to investigate water leakage. Please be careful when using the back entrances or
biking in the campus.
- O. Bilani reminds groups to inform her when companies are planned to carry work at XHEXP1.
CTRL:
- Nothing to report.
DA:
- Nothing to report.
EEE:
- Nothing to report.
VAC:
- Nothing to report.
XPD:
- Nothing to report.
DET:
- Nothing new from DET.
ITDM:
- Not present.
XRO:
- Not present.
LAS:
- All quiet at LAS.
UNSYS:
- Nothing to report.
- MEA surveillance availability is limited for the next week, but shall not affect UNSYS.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- Nothing to report.
HED:
- Nothing to report.
SCS:
- Nothing to report.
SQS:
- Nothing to report.
SXP:
- Not present. |
634
|
04 Aug 2025, 09:43 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 04.08.2025 |
General Announcement:
- A. Galler informs on the LIMP-25: 1. TS task #7 takes place this week with firm upgrade of the building management system will affect infrastructure system for about a minute or so.
- Kristina Lorenzen reminds that
1. External companies shall not use visitor cards;
2. Please let room managers know if external companies are accessing or working these rooms;
3. Please keep paths and storage places free.
- Patrick Gessler amends that external companies were letting doors open which should remain closed.
A. Galler says it is a responsibility of the inviting person to let room managers and other affected groups to know an external company is having work here.
CTRL:
- Fast ADC issue was fixed at all places.
DA:
- Everything quiet.
EEE:
- Work in SPB AGIPD 4M ongoing from today;
- Also work at SCS parts to be done this week.
VAC:
- Everything fine.
XPD:
- Everything fine.
DET:
- Everything fine apart of the affected detector and X-ray power due to the power cut on 25.07.
ITDM:
- Issues at IT with Desy was fixed on Friday (cooling pipe leaked affecting building). The affected computer center is primarily not used by XFEL.
XRO:
- Nothing to report.
LAS:
- Nothing to report.
UNSYS:
- Nothing to be reported.
- No news on MEA2 availability; A. Galler says the MEA2 was busy at Flash and could not start work at XFEL. To be enquired at RC meeting today.
SPB:
- Nothing apart of the cabling for AGIPD 4M.
FXE:
- Nothing to report.
MID:
- All PLCs are running.
HED:
- All PLCs are running.
SCS:
- DPVA3 tests ongoing.
- PLC loop 1 crashed by was fixed by Nerea J. / EEE. It runs normally over the weekend.
SQS:
- Nothing to report.
SXP:
- Not present. |
633
|
30 Jul 2025, 09:22 |
Andreas Galler | General | Information | Notes XO Integration Meeting 30.07.2025 |
General Announcement:
- electrical meintenance on July 30th XHQ green marked area
- electrical maintenance on July 31st - Aug 1st XHQ blue marked area
CTRL:
- issue with fastADC device, investigation going on together with EEE
DA:
EEE:
- Bruno clarifies that the fast ADC issue is with a specific class of the PPL fast ADCs
VAC:
- nothing
- Daniele reports that the SA3 ODL chamber had been m XTD4 ODL
XPD:
- question to SCS and EEE, is the PLC loop 1 up? Nerea comments, yes it is.
DET:
- still investigating the damages on the reference detector and the pulsed x-ray source
ITDM:
XRO:
- tunnel temperature being monitored
- XTD9 lower than the other tunnels, but tolearable for tunnel works
LAS:
- SA2 & SA2 PPLs restarted. SA1 coming later this week
- support from EEE, CTRL is greatly appreciated
UNSYS:
- SA2 Undulators shifted to make toom for the chicances
SPB/SFX
- work ongoing, prep for AGIPD4M (possible installation by end of October)
FXE:
MID:
HED:
SCS:
- XGM restart today afternoon
SQS:
SXP:
DRC
PRC
AOB:
- Michael Prollius reminds to take self rescuers along when leaving the tunnels.
|
632
|
28 Jul 2025, 09:20 |
Andreas Galler | General | Information | Notes XO Integration Meeting 28.07.2025 |
General Announcement:
- electrical maintenance on July 28th
- electrical sockets in the IT-Rack rooms E1.010 & E1.092 & E1.174; Meeting room equipment in E1.173; Reception
- electrical meintenance on July 29th - 30th
- electrical maintenance on July 31st - Aug 1st
CTRL:
- aftetr cooling water invention karabo was restarted
DA:
EEE:
- ramp up of EEE systems, bringing up inbstruments step by step
VAC:
XPD:
DET:
- reference detector damaged during electrical maintenance power cut on Friday
- pulsed X-Ray source may be affected too
ITDM:
- tomorrow, memory upgrade of online storage
- should not affect storage availablity
- few servers across different instruments need forwmare upgrade for network cars wich is problematic
- correct procedure for the upgrade is now available and will be applied
XRO:
- all as planned
- power cut did not damage any systems in the labs
LAS:
UNSYS:
- some activties postponed, since MEA2 is currently not available.
- some rescheduling necessary, as this woul otherwise be a blocking issue.
SPB/SFX:
FXE:
MID:
HED:
SCS:
- question to EEE:
- SCS PLCs are being brought up today? --> yes --> please bring up PLC loop 1 first
SQS:
SXP:
DRC
PRC
AOB:
|
631
|
23 Jul 2025, 09:25 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 23.07.2025 |
General Announcement:
- Martin Doering informs on the LIMP-25:
1. Today it happen crane activities in the XHEXP1 and please take the appropriated safety measurements when craning takes place.
Also the elevator close to the main entrance is being maintained today so please use alternative ways to get into the XHEXP1;
2. For next week: Karabo and PLCs will be ramped up;
3. Activities taking place at some instruments like MID, SCS and SPB starting next week;
4. Electricity interruption at XHQ level 2 taking place next week, as communicated in e-mail;
5. IT rooms in XHQ level 1, reception and E1.173 meeting room are affected on July 28th due to electrical works;
6. On Friday 01.Aug the XTD6 access at XHEXP1 will be interrupted for 2-6hs due to the relocation of the dosimetry cabinet for HXS project (exiting from XTD6 is still possible).
- Air conditioning at XHPEXP1: conditions seems to work well even with limited hardware controlling temperature and humidity.
- Temperature and humidity in tunnels are being monitored and look stable. In XTD9 temperature is 3 C lower than other tunnels. It is not critical for components as of today. Normal operation will resume
by August 22nd.
- Pouhneh S. says the main work in laser interlock at SA3 is finished and it can be operated again.
CTRL:
- To ramp up Karabo: they shall be back by the 25.07.
DA:
- Nothing to report.
EEE:
- PLC systems will be bring back starting today.
- uTCA: started yesterday to bring back lab crates. Communication issues with digitizer was encountered. In contact with company to find solution.
If digitizer are needed in coming days, please get in touch with Bruno Fernandes.
VAC:
- Everything fine.
XPD:
- All fine.
DET:
- Question on cooling water supply for lab areas: systems that are fed by XHPSC has currently no redundancy and in case of failure it could warm for few minutes.
In general, the cooling water systems is running again.
ITDM:
- Starting up racks in tunnels and balcony rooms; DAQ servers to be restarted today.
XRO:
- Nothing to report.
LAS:
- Nothing to report.
UNSYS:
- Not present.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- Nothing to report.
HED:
- Nothing to report.
SCS:
- Nothing to update.
SQS:
- Not present.
SXP:
- Not present. |
630
|
21 Jul 2025, 09:54 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 21.07.2025 |
General Announcement:
- M. Doering informs on the Limp-25 / current week:
1. Cooling water maintenance in XHPSC: replacement of valves taking place and the filling back is ongoing; expected that cooling water will be back today.
2. Temperature in XHEXP1 showed 23.8C and 64% humidity as of Friday 18.07. When cooling water is back today please wait as humidity is too high and condensation may happen;
dehumidifying system is still limited due to maintenance but precision air conditions will return and help with dehumidification in Hall and labs.
3. Due to construction for HXS please avoid entering or leaving XDT7 to XHEXP1.
- Janusz Szuba asks on the cooling water redundant pumps: until the end of the current week the redundant system will not work and there is a risk that primary pumps go OFF in case of a power outage.
Unclear how long it takes to recover the system in case of this failure (depends if happens during day or night). As consequence the rack rooms may be affected due to heat. To be further discussed.
- O. Bilani reminds on the safety measures around the FXE hutch constructions and please be respecting safety rules; On Wednesday morning craning activities will take place between truck bay and Hall.
CTRL:
- Nothing major to report.
DA:
- All fine at DA.
EEE:
- Nothing to report.
VAC:
- Nothing to report.
XPD:
- Racks in XTD10 were closed after Thursday - rack 3.13 especially. Back doors were opened.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- No particular problems to report.
LAS:
- Air conditioning did not start at the lab E0.504 on Friday; Martin Doering will discuss with LAS - it likely to be a misunderstanding.
UNSYS:
- Nothing to report.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- Nothing to report.
HED:
- Nothing to report.
SCS:
- Nothing to report; emergency test was successful.
SQS:
- Nothing to report.
SXP:
- Not present. |
629
|
16 Jul 2025, 09:51 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 16.07.2025 |
General Announcement:
- Martin Doering informs on the LIMP-25 on cw30:
1. On PLCs only the GATT will have an update next week;
2. Ramp-up phase will start next week with tunnel racks, balcony rooms and Lasers;
3. XHQ rack room doors will remain open next week - please do not enter rooms;
4. SA2 HXS electrical work will finish this week;
5. XHEXP1 UPS extension work is postponed and will not happen on 22-23.07. Once new date is available it will be communicated;
6. Electrical work in XHQ: lab areas (level 0) being affected until 21.07;
7. Electrical work on the XHQ offices of level 1 starts on 22.07 until 25.07;
8. XHQ level 2 office areas are affected with electrical work from 29.07 to 01.08.
- Martin Doering updates on the cw29 (current week):
1. Today from 10AM to 11:30 craning activities are planned for HXS area; Electrical maintenance in E0/lab area are also affected on Thursday in the same way as today.
- Michael Prollius informs on the fire safety for SA2 experimental area: the smoke detection system is currently OFF due to the electrical work being done.
CTRL:
- Nothing to report; Karabo to be ramped up next week from 22.07 to 25.07.
DA:
- Nothing to report.
EEE:
- Nothing major; temperatures of SA1 balcony rooms raised more than other areas - to be monitored to see if PLCs shall also be switched off.
VAC:
- Not present.
XPD:
- Nothing to report.
DET:
- Nothing to report.
ITDM:
- Balcony rooms being monitoring temperatures.
- Doors to the rooms are opened and there is a trend of slow raise of temperature ongoing and flow of air from the Hall to be improved with fans.
XRO:
- Nothing to report; activities are progressing as planned;
LAS:
- Progressing with tasks.
UNSYS:
- Nothing to be reported.
SPB:
- Nothing to report, all good.
FXE:
- Nothing to report.
MID:
- Nothing to report.
HED:
- Ongoing work depends on the return of electricity.
SCS:
- Emergency OFF tests were delayed and Tobias C. informed it will happen today.
SQS:
- Nothing to report.
SXP:
- Not present. |
628
|
14 Jul 2025, 09:59 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 14.07.2025 |
General Announcement:
- On Crane activities:
1. Next craning activity from truck bay to HXS area will take place on Wednesday 16.07 from early morning. During the time helmets will be provided in case you need to cross the area to access XTD6 or
XTD7 or work around this area;
2. Craning for FXE hutch construction will also take place and please watch out if crane activities take place around e.g. XTD8 entrance.
- Martin Doering informs on the LIMP-25:
1. Air conditioning this week is switched OFF at XHEXP1 but as temperatures outside are expected to be mild during the week we thus expect working conditions to be good at the Hall;
2. Cooling water activities start tomorrow from 7AM but will be already switched OFF today;
3. Elevator maintenance takes place at XHEXP1 on 17.07;
4. AV power will be switched to a different transformer on Friday 18.07 (potential risk of glitch).
- Torsten Schoen says work at lab floor E0 is done (electricity); connection to orange outlets shall be moved to white ones already by Tuesday afternoon. One can use the orange sockets again by the end of
this week.
- Alessandro Silenzi says DOC phone (98089) is still available and coverage will be provided.
CTRL:
- Nothing special to report and tasks going accordingly to the plan (stopping Karabo).
DA:
- Nothing to report; all calm at DA.
EEE:
- Switched off everything apart of tunnels.
- After discussing with instruments: OCD PLC will be discontinued and returned in November.
VAC:
- Nothing to report.
XPD:
- Nothing to report.
DET:
- Nothing to report.
ITDM:
- Remind couple of proposals to be closed: reminder to be sent by e-mail.
XRO:
- Nothing to report.
LAS:
- Nothing to report.
UNSYS:
- Nothing to report. All fine.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- Nothing to report.
HED:
- Nothing to report.
SCS:
- Nothing to report.
SQS:
- Nothing to report.
SXP:
- Not present. |
627
|
09 Jul 2025, 08:32 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 09.07.2025 |
General Announcement:
- LIMP-25 update for this week: elevators were to be maintained this week but it is now shifted to 16-19.July.
- A. Galler announces on the LIMP-25 regarding next week:
1. Karabo updates take place from next week and thus are not available;
2. Next week last racks (UNSYS) will be placed down;
3. Cooling water is available next week impacting racks and air conditioning in XHEXP1 - please switch OFF electrical devices in the Hall to spare heating;
4. Humidity controlled in the Hall will not be available next week, thus temperature will change in the experimental Hall;
5. Electricity: SA2 area in XHEXP1 do not have available electricity next week; Also XHQ will be affected;
6. Waste water affecting some areas in XHQ;
7. DACHS in some doors will also be affected.
- Tobias Clever reminds that UPS in XHQ will happen this weekend from 12.July.
- Suren K. says the undulator control cabinets do not use cooling water and therefore it is preferable to keep them UP and running.
- Radu S. asks on the PKGs of the XHEXP1: Tobias C. says they are to be maintained accordingly to their scheduled dates.
- Ivan A. will discuss with TS about task#2 which brings down the UPS in the lab areas to find a solution to switch OFF a spectrometer.
- A. Galler says on Monday 14.07 craning will be done in XHEXP1 and access to the HED is not possible in the morning.
CTRL:
- Karabo SA1 instruments are already down; SA3 follows tomorrow.
DA:
- Nothing to report.
EEE:
- uTCA system being updated and prepared.
VAC:
- Following LIMP plans with activities in tunnels.
XPD:
- Ongoing with activities. All fine.
DET:
- Nothing to report.
ITDM:
- Activities are ongoing as planned. Servers in rack rooms are shut down; Next will be balcony rooms.
XRO:
- Not present.
LAS:
- Going well so far.
UNSYS:
- Everything goes as planned; spare undulators are out of XTD8.
SPB:
- Finished ramp down yesterday.
FXE:
- Nothing to report; everything downstairs are OFF and construction works start next week.
- FXE rack room has difficult access due to the construction.
MID:
- Nothing to report.
HED:
- Not present.
SCS:
- Nothing to report.
SQS:
- Everything accordingly to the plan.
SXP:
- Not present. |
626
|
07 Jul 2025, 09:44 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 07.07.2025 |
General Announcement:
- Martin Doering announces:
1. Karabo will be stopped this week accordingly to a distributed e-mail;
2. HXS hutch craning will take place today;
3. Photon tunnels starts by opening rack doors in preparation for cooling water activities - they must stay open;
4. Companies working at XHEXP1 starts this week;
5. Toilettes and kitchen are closed in the XHEXP1 for this week (no waste water to be produced);
6. Elevator maintenance takes place on the 10.07 affecting XHEXP1.
- A. Galler reminds that info distributed at this meeting is disseminated by the present people to colleagues inside their respective groups.
CTRL:
- Plan of Karabo shutdown was sent to xo-info mailing address; topics will be brought up again starting from July 22nd.
DA:
- Nothing to report.
EEE:
- Remind the ramping down was done and will be ramped up after Karabo is back.
VAC:
- Nothing to report.
XPD:
- Regular maintenance ongoing as planned.
DET:
- No news from DET.
ITDM:
- Supporting opening racks in tunnels.
- Migration of data/proposals: please move them this week as they will be discarded from next week.
XRO:
- Everything fine and progressing with M1 at XTD2 and with the optical delay line.
LAS:
- All are going accordingly to the plan.
UNSYS:
- Everything going well: SA1 undulator cell#17 moved to cell#1; relocation of SA2 cabinets ongoing; area of SCU is free.
SPB:
- Nothing to report.
FXE:
- Not present.
MID:
- All fine.
HED:
- Nothing to report; switching OFF last devices today and tomorrow.
SCS:
- Nothing to report.
SQS:
- Starting to rip-out cables; all fine.
SXP:
- Not present. |