General Announcement:
- M. Doering announces on the LIMP-25:
1. XTD10 Scaffolding is installed for cabling work in October;
2. PLC updates: remaining work in tunnels to be done next week (discussed with VAC and XPD) as well as at SQS;
3. Update task list: M. Doering will send to the groups the Task list for that it is updated accordingly to the latest status (e.g. completed, cancelled, delayed...);
4. Recurring tasks for the Winter Maintenance will be planned for the end of the year. A list will be sent to the groups and please inform XO if you have new activities to be done before 2026.
CTRL:
- Karabo upgrade: start with MID next week to spot possible issues. MID topic will be accessible from the hutch only.
DA:
- Nothing to report.
EEE:
- PLC updates: see above.
VAC:
- Everything progressing well in XTD6 also with PLCs.
XPD:
- Nothing to report.
DET:
- Nothing to report; starting AGIPD at MID before Karabo is down in October.
ITDM:
- Nothing to report.
- Fast-X gateway upgrade last week is done.
XRO:
- Busy with SA1 activities.
LAS:
- Not present.
UNSYS:
- Delays with water and cable from Desy groups; but all ongoing.
SPB:
- Not present.
FXE:
- Nothing to report.
MID:
- MID control room is very warm: needs to check temperatures in control room; Gerd W. says technical infrastructure needs to be modified.
HED:
- Nothing to report.
SCS:
- Issue with installation of beam stop and AIBS position.
SQS:
- Not present.
SXP:
• Not present. |