Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther, Page 21 of 31  Not logged in ELOG logo
ID Date Author Location Severity Subject
  202   24 Feb 2021, 09:03 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 24.02.2021

General Announcement:

- Due to a failure alarm in the smoke extraction system in XTD6+8+9, Desy colleagues will need to reboot a crate and exchange one module. This will bring down the air conditioning for the tunnels during about two hours. The activity is scheduled for March 1st starting at 11:30AM and it appears in the EuXFEL infrastructure calendar.

- It has been found a situation with one of the elevators to the XHEXP1 Hall. Due to corona regulations a maximum of 3 people is allowed simultaneously in the elevator. This number is indicated by signs/papers fixed nearby. However, someone unauthorized has modified the number “3” to an “8”. We are investigating the situation. The shields have been corrected back to “3” but we would like to remind signs and warnings must not be modified by unauthorized persons.

- Gerd W. informs that SXP chicane modification foreseen to take place today and tomorrow is shifted to Monday or Tuesday due to delays in delivery of components. Affected people have been contacted by PMO via but in case of issues with the new plan, please contact Gerd W.

CTRL:

- Few requests for tickets on Karabo devices were received. CTRL reminds to please add device ID in the ticket.

- SA3 motors: a few changes were done due to migration of MC2 motors. If someone or a group needs more input, please directly contact Steffen Hauf.

- Regarding Data Operation Center (DOC): CTRL would like to have a functional account to the instrument e-logs to be able to access it and track problems when OCD gets called. If instruments have any concerns with this, please contact Steffen Hauf.

DA:

- Nothing today.

EEE:

- No main issue.

- EEE also asks that when submitting tickets, please include the instrument and component name, preferentiably in the header.

- PLC side: ZZ to check motors.

VAC:

- Nothing to report.

XPD:

- Continuing today with beam commissioning of XTD6 components (HIREX and MCP).

DET:

- Nothing special to report.

ITDM:

- Nothing special.

XRO:

- Issues will be addressed when tunnels are open.

LAS:

- SA1 and SA3 PP-lasers are making progress.

UNSYS:

- Nothing to report.

SPB:

- Issues with Interlock and DACHS are solved.

FXE:

- Interlock issues are solved.

MID:

- Nothing special.

HED:

- Thomas Preston asks if the Covid regulations in hutches can be sent by e-mail. Sandra Plett will send the link to the documents after the meeting.

- The mask occupancy for the hutch was changed (are the signs updated or not?). Thomas P. says it was 4-5 but someone wrote new numbers in the signs. Sandra P. says that if everybody is using FFP2 masks, then more people are allowed than the max. occupancy.

- Pouneh S. says if people use laser safety googles, one can use FFP2 with filters. Sandra P. says that rules also apply for this case.

- Issues with cameras: DAQ did not run (did not take data, probably due to lost configurations). HED will send ticket.

SCS:

- Nothing to report.

SQS:

- Yesterday a meeting to review digitizers took place.

  201   22 Feb 2021, 10:14 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 22.02.2021
General Announcement:
- In case someone has any remaining question on the use of masks in the hutches please feel free to ask in this meeting series or write XO an e-mail.
- Racks for the SXP will be delivered and moved around XHEXP1 in March. The calendar for such activities will appear in the EXFEL infrastructure calendar. 
The activity is coordinated by TS and in case of conflicts, please contact us or Ulf Brueggmann.

CTRL:
- Few configurations issues with motors are being taken care with EEE. 
- XPD found a bug in the middle layer device and it needs new deployment. CTRL will contact people involved.
- DOC will start going on next week. Further info will be sent around and contact to single points in the instruments will be made.

DA:
- Preparing the DA contribution to the DOC.

EEE:
- Nothing to report apart the work for the configuration of motors.

VAC:
- Vacuum interlocks triggered on Friday in SA3. VAC reminds that when someone opens the shutter, nothing behind must be left in the beam.

XPD:
- A. Koch says commissioning of SA3 components and Imagers take place. The Shimadzu camera was tested with beam in SA1 and signal was observed. 

DET:
- Preparing for regular support of Detectors.

ITDM: 
- A question arises if SASE3 also operating. A. Galler says there is an effort for commissioning beam transport on SASE3, but focus for operation still remains in SASE1.

XRO:
- XRO has commissioned beam transport in SA3 and in SA1. Overall beam was stable apart of few interruptions. Objectives for the weekend were successfully completed.
- Couple of issues need to be fixed; XRO will request ZZ access in XTD10 together with EEE. Tickets are sent.

LAS:
- No news from last week.

UNSYS:
- Nothing to report.

SPB:
- Issues with Laser interlock system and accessing hutches persists, as reported last Wednesday. SPB expects laser safety to be working on that. 
Romain Letrun confirms the problem is related to the DACHS access system.

FXE:
- It has faced similar problems with the interlock system as the ones observed by SPB/SFX.

MID:
- Hutch cleaning is planned this week.

HED:
- All fine.

SCS:
- Nothing to report.

SQS:
- Last Friday an interlock issue (no beam to hutch) was found but solved almost immediately.
  200   17 Feb 2021, 09:27 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 17.02.2021

General Announcement:

CTRL:

- update for GUI server this morning is finished.

-  CTRL advices people starting systems such as cameras, in case of connecting issues please try first to reboot the devices first.

DA:

- nothing special to report.

EEE:

- will update PPL update mTCA SASE3 - affects only LAS group

VAC:

- nothing to report.

XPD:

- Recommissioning diagnostics in SA1.

- Pop-in YAG screen in FXE/SA1 was found broken. Any information on when was working last time please send to Andreas K. In this Pop-in is a second screen with diamond which is working. YAG exchange is for next maintenance period.

DET:

- The offline calibration service update is finished and is available again. Please contact DET in case of issues.

ITDM:

- nothing to report.

XRO:

- Working at BKR yesterday with commissioning SA1 alignment; SA1 is aligned until SPB and FXE.

- Today continuing with SA2 depending on beam stability.

- Idoia F. mentions that computers were not running at BKR. A check after shutdowns and prior operation is welcome.

LAS:

- The AMPHOS in SA3 needs a new power supply. Expected delivery and exchange on Friday.

- PLC update in SA3 and uTCA upgrade on Friday.

- Advancing with SA1-PPL commissioning.

- LAS will send e-mail to Zunaira A. for that MEA3 personal is contacted on the problems with sensor boxes.

UNSYS:

- Ambient field coil was fixed.

- New minimum gaps will be calculated and communicated to XO.

SPB:

- After interlock test last week there is an issue with the new DACHS terminal. The hutches can’t be accessed. Pouneh S. says DACHS is working but this particular new terminal might not be activated in the system. An special permission must be given. Tobias Haas will be informed to contact MEA3.

FXE:

- Martin K. will ask FXE colleagues on YAG screen information. Currently he is not aware when this happens (similar event back in 2019). 

MID:

- all fine.

HED:

- all fine.

SCS:

- in contact with Eric B. to get the beam shutter back on Friday for closing hutches during the weekend.

SQS:

- Early next week review with the digitizer engineers.

- Pouneh S. asks that laser interlock in laser hutch does not work. The new parts have been shipped and arrive soon. Together with TS electrician one has to exchange the relay. Daniel Rivas is informed.

  199   17 Feb 2021, 08:52 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 15.02.2021
General Announcement:
- It had been a cooling water issue with SA1 and SA3 PPLs on Saturday. Other groups are encouraged to check their components for eventual damage. Cooling water is back 
again.
- Change on definition of a critical work: everything that leads to operation is from now on considered a critical work (official communication will be send by e-mail).
- Tomasz J. says interlock tests in SA1 tripped the laser interlock due to the Seeder connection to the interlock. 
Andreas G. says there are care been taken to prevent this in future. More discussion will follow.

CTRL:
- Updates were done on the time servers and data loggers.
- GUI servers will be done this week as there was no access to GITLab. Current suggestion is next Wednesday morning before 08:00AM. 
Each topic will take a few minutes only. XPD is fine with the proposed day/time.

DA:
- Nothing to report.

EEE:
- Issue during weekend: signals to the absorber. EEE and PRC (Maurizio V.) will coordinate when it is the best time for applying the final fix. 
EEE needs to mask it for proceeding with the work.

VAC:
- VAC OCD was involved in the absorber EPS issue.
- Today around lunchtime the XTD6 and XTD9 will be closed.

XPD:
- EPS issues: any component driven to the beam was not protected by many bunches operation. The EPS was thinking the PNACT was closing but in reality, it was opened.
PRC/EEE/VAC/XPD OCDs solved by manually telling the system it is closed.
- Wrong bunch number sent to XGM: SA3 toroid was moved to a different position and the old name was not valid anymore. 
Info from this toroid was not received and the consequence XGM was receiving wrong bunch numbers. This makes impossible for the XGM to calculate correctly the number of 
bunches. 
Doocs servers were not updated (these programs would need to be informed of new naming). 
- Andreas K. says that XTD6 is clean. In XTD9 an intervention by EEE will take place. Bruno F. says that it is a simple task and we are accessing tunnels right now.
- Operation E-log 2021 is missing and must be created. 

DET:
- Offline calibration work is ongoing until tomorrow morning.

ITDM: 
- GPFS offline storage maintenance to be done today. 
- ITDM was notified by Desy that is necessary to reboot logins on Maxwell nodes (between 11:00-12:00).

XRO:
- Nothing to add to what was discussed on the EPS.

LAS:
- Affected by water cooling incident. SA1 came up without issues but in SA3 there is problem as AMPHOS did not restart.
- Trigger issue on last week are not the issue anymore. This was not repeated (but SA1 still on local mode).

UNSYS:
- BBA and photon BBA last week: new values to be implemented and minimum gaps will be updated accordingly.
- Frank Brinker tested the ambient field corrections. A ZZ is taking place this morning to fix SA2/cell12. 
Few other coils have different polarities and will be fixed today or in another ZZ.

SPB:
- Preparing for the first two weeks with beam in March.

FXE:
- Aligned the cameras in FXE mono.
- Crates to be installed in the rack room.

MID:
- Joerg H. raises the question on the FFP2 usage recommendation. Sandra Plett says the document containing guidelines will be prepared (hopefully today); 
It is mandatory to use FFP2 masks if you are not alone; it also depends on the room size and at the moment it is 3-5 people in the hutches with mandatory use. 
A. Galler says these are the current regulations and maybe this will change in future.

HED:
- Nothing to report.

SCS:
- Nothing to report.

SQS:
- Trying to get a new DAQ and will talk to ITDM.
  198   10 Feb 2021, 09:20 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 10.02.2021

General Announcement:

- Tunnel closure: it has been decided both XTD6 and XTD9 will be searched and closed on Monday 15.02.

- Temporary tunnel access requests: for ZZ access please be aware of the new Redmine ticket for access requests. The link to it appears in the BKR E-log.

- Use of FFP2 masks in experiments control hutches:  Sandra Plett informs rules such as temporary stop of work after 75 minutes of mask use or a day off after two working days with masks are not mandatory - these are only a recommendation; If two people are <1.5m, one has to use masks. While Seated or alone you can remove the masks; However, if there are people running around, please use masks also if seated; The wearing time is just a recommendation - it is not mandatory to make the break.

CTRL:

- Graphical user interface update: there is a new version to install in the gateway and BKR.

- Update of data loggers and GUI servers to take place.

DA:

- all going well.

EEE:

- SA2 loop update (MOV) was done yesterday for Hirex and Shimadzu.

VAC:

- nothing to report

XPD:

- DACHS terminal in XTD9 did not allow access: database connection issue. Andreas K. has contacted M. Prollius.

DET:

- Deployment of offline calibration pipeline from today until Friday. It will be communicated when it’s finished.

ITDM:

- Two weeks ago, ITDM pre-announced an offline GPFS update. Preparations will be ready by Friday. Ideally ITDM will deploy on next Monday. Please let K. Wrona aware if this date is not suitable.

XRO:

- Not present.

LAS:

- Upgrade on uTCA crate in SA1 – ADC acquires data. A small problem with data acquisition was found and a Redmine ticket was created. In any case all is fine for switching PPL-SA1 on.

- Today between 2:00-08:00AM there was no trigger coming to PPL-SA1. It may be from Desy or from Balcony room. Bruno F. will investigate the balcony rooms.

UNSYS:

- Unsys will request access for next week to fix a SA2 ambient coil.

SPB:

- nothing

FXE:

- nothing

MID:

- All fine

HED:

- nothing

SCS:

- nothing

SQS:

- Issues with trigger are fixed.

- uTCA firmware updated; now fixed.

  197   08 Feb 2021, 08:30 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 08.02.2021

General Announcement:

- XTD10 tunnel was closed last Friday; XTD9 to be closed by end of this week; XTD6 is undefined – mostly likely by Monday. Any schedule deviation will be communicated.

CTRL:

- Deployment of offline services from 10.2 to 12.2. Services such as offline calibrations are not reliable in this time. An e-mail was sent and another reminder will be sent again.

DA:

- no news.

EEE:

- Update of PPL uTCA in SA1 today (laser);

- SASE2 PLC loop update to take place tomorrow at 13:00 (Hirex and Shimadzu camera).

VAC:

- Nothing to report

XPD:

- No issues to report.

- Andreas K. says in SA1 hardware activities are done; testing optical alignment.

- Hirex SA2 update is missing.

DET:

- nothing to report

ITDM:

- nothing to report

XRO:

- nothing to report

LAS:

- Switching on SA1 laser – after uTCA upgrade. Small issue relates to the missing trigger from Desy (dynamic triggers). Point of contact are Tim Wilksen and Lars Froelich.

UNSYS:

- Hick-ups with controls during the weekend. BKR opened gaps to 220mm and caused troubles (usually they open o 210mm).

- One ambient field coil needs ZZ for fixing (SA2/cell12); not urgent.

- Cleaning was done in XTD4.

SPB:

- setting up for the first set of commissioning

- Gotthard trigger seems to be solved.

FXE:

- nothing to add

MID:

- all fine

HED:

- nothing to add

SCS:

- not present.

SQS:

- uTCA digitizer issue: ongoing.

  196   03 Feb 2021, 09:26 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 03.02.2021

General Announcement:

- Automatic Power Switch Testing was done yesterday. The switches are working as expected and a protocol has been produced. Torsten Schoen informs this test is done every 4 years; from now on equipment can be connected again to the orange and green power outlets.

- Re-start of the accelerator takes place from last Monday. Currently the setup of the injector and LINAC is ongoing. There are no changes to the last plan for closing dates of the photon tunnels.

CTRL:

- CTRL works on the Doocs Undulator devices/panels that have to be changed.

DA:

- nothing to report.

EEE:

- EEE and LAS people are on-site checking the reported uTCA problems after the power switch (by LAS). Issue refers to no communication to the uTCA.

- SASE1 motion loop update yesterday was done.

VAC:

- Not present.

XPD:

- XTD6 and XTD9 Shimadzu cameras update continue.

- Next loop update for XTD6 will probably be next week together with Hirex changes.

DET:

- all fine

ITDM:

- everything is fine

XRO:

- VAC is busy in tunnel leaking check the XTD10 soft mono (pressure went down to 10-6mbar already) but it takes more time.

LAS:

- Yesterday the SA1 and SA3 PP-laser systems were lost. Tomasz J. and EEE are looking into it.

UNSYS:

- today ZZ in XTD4 for the cleaning at SASE3. PRC has informed the BKR.

SPB:

- Problems with trigger of Gotthard are reported by Marcin S. It may be also linked to a communication issue.

FXE:

- nothing to add

MID:

- all fine

HED:

- nothing to add

SCS:

- not present.

SQS:

- Wanted to run digitizer on uTCA but could not find/communicate to it. Under investigation this afternoon.

  195   01 Feb 2021, 09:06 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 01.02.2021

General Announcement:

- The test of the emergency automatic switch of power bridge is scheduled for Tuesday, 2nd of February 2021, 09:00. This will affect orange outlets in XHQ and green and orange outlets in XHEXP1. A short interruption in the power supply lines will happen. We expect all groups have taken appropriate measures to place devices in safe mode or connected to white power outlets.

CTRL:

- not much to report, things are running

- Read the docs is operational again. A given feedback to CTRL is welcome.

DA:

- Nothing special to report.

EEE:

- Tomorrow update sase1 motion loop at 13:00: an email will be sent to readiness mailing list.

VAC:

- Nothing to report.

XPD:

-  Maintenance work ongoing: Imagers in XTD6; Work with EEE in XTD6 and XTD9.

DET:

- AGIPD: new control with new gain is tested. DAQ issue with data is fixed (K. Wrona informs it was related to a wrong hidden parameter setting).

ITDM:

- Downtime on Offline calibration system / GPFS: update to be made in about two weeks from now. K. Wrona says that ITDM would like to have one day of GPFS maintenance; it is important to switch to the new scratch files before we start operation. Data taking shall not be affected by this.

- Jan G. asks when would be required by the earliest. K. Wrona says they need to copy a lot of data before the update and it is estimated in two weeks (+-2 days), to take place in the second half of February. As photon activities take place in the last two weeks of February, one needs coordination to find a suitable date.

XRO:

- everything fine.

- Today closing of soft mono chamber in XTD10.

LAS:

- Upgrade in SA1 uTCA: information will be given to LAS this afternoon.

- Two Desy colleagues needs access in SA1 hutches. Use of FFP2 masks is mandatory.

UNSYS:

- ZZ in XTD4 is planned for Wednesday (for cleaning undulator area).

- Suren K. asks if the balcony rooms are effected by test emergency power switch. This will be discussed offline.

SPB:

- Nothing special to report.

FXE:

- Nothing special to report.

MID:

- all fine

HED:

- Nothing special to report.

SCS:

- Nothing special to report.

SQS:

- Nothing to report.

  194   27 Jan 2021, 09:08 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 27.01.2021

General Announcement:

- FFP2-Masks needs to be used in the experiment control hutches from now on regardless the number of people working in this areas. Regulations concerning the maximum number of staff in this areas remain the same.

- SASE1 Laser interlock upgrade originally scheduled for this week was postponed to next week. As soon as we receive the information on the new date, this will be communicated.

CTRL:

-   Intervention for the new scenes for the size of the labels was originally scheduled for yesterday. This was postponed as additional tests will be conducted in CTRL lab. A new date will be announced. 

- Panel topics: some old types doocs undulator devices were replaced for a single device. CTRL would like to remove the old ones in 2-3 weeks and kindly ask groups to inform if they are still in use. CTRL will send an e-mail on this subject.

DA:

- Nothing special to report.

EEE:

- Nothing special to report.

VAC:

- Still working in XTD10 and XTD6.

XPD:

- Tunnel works ongoing in XTD6 and XTD9, e.g. Shimadzu cameras / Imagers.

- EEE will need to have access at the end of the Imager intervention of XTD6.

DET:

- SPB Agipd: issues with new data acquisition system. It has been under work.

- This week DET plans to test the new Control fix medium gain to be used in user experiments.

ITDM:

- Nothing special to report.

XRO:

- Not present.

LAS:

- After SASE2 AMPHOS update: there are issues with the interlock

UNSYS:

- Unfortunately neither Desy or EuXFEL could grant access to the external company for the XTD4 tunnel cleaning. UNSYS is trying to organize themselves. PKG shall not be switched on before the clean is done.

SPB:

- Tests with DAQ of the AGIPD: new version has issues with data assignment of aggregated version. Currently AGIPD is back in the old version.

- Work of EEE with some crates of rack room.

FXE:

- Nothing special to report.

MID:

- all fine

HED:

- Nothing special to report.

SCS:

- Nothing special to report.

SQS:

- nothing to say

  193   25 Jan 2021, 09:28 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 25.01.2021

General Announcement:

- Test of automatic switch of power bridge is shifted to Feb.2: this affects all devices connected to orange or green power sockets (no power for few seconds/minute). General e-mail will be sent. Instruments will need to care for equipment which is connected to these sockets. This also affects the E0 level as well as office space in XHQ. Pease plug devices out or re-plug in other sockets.

  • The Covid-19 regulations continue valid. Only critical work in the XHEXP1 or tunnel activities shall take place.

- Work on the Soft Mono in XTD10 (SA3) takes place this week. XRO and ME asks everybody to do not move any motors in this device during the whole week.

CTRL:

- New Script to fix label issues in Karabo is ready and will be run today. An e-mail will be sent.

- ITDM and CTRL managed to get updated the “Read the docs”. It runs properly.

DA:

- Not present due to Satellite Workshop.

EEE:

- nothing to report

VAC:

- continuing with tunnel works

XPD:

- Ongoning with few tasks in the tunnel

DET:

- Not present

ITDM:

- nothing to report. Offline GPFS under work today: no Maxwell access during this time.

XRO:

- Not present. Please see general announcements on the Soft Mono.

LAS:

- Error with remote operation on mirrors for SA3/SQS PP-laser is found. A discussion after the meeting will take place between LAS and XO.

UNSYS:

- Nothing to report

SPB:

- Nothing to report

FXE:

- Nothing to add

MID:

- all fine

HED:

- Nothing to report

SCS:

- Nothing to report

SQS:

- Nothing to report

  192   20 Jan 2021, 10:32 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 20.01.2021
General Announcement:
- A. Galler encourages attendants to pose questions on the authorities decision of lockdown prolongation:  
Zunaira A. asks on travel restrictions between different cities: The commuting continues to be allowed, but not business travels; 
Adriano V. asks on business/meetings that were postponed (MID/AGIPD intervention) to February in order to plan work that will happen during the summer shutdown: Andreas 
G. says that if meeting can't be decided by Zoom, please send an e-mail to the task force with this enquire;
P. Gessler asks if EuXFEL considers to prepare documents (passport) again as in the first lockdown: A. Galler answers that this is in discussion but currently it will not 
to be implemented once no curfew is ongoing.

CTRL:
- Working with ITDM to get the Docs system running again.
- Working with EEE to have systems running by Friday.

DA:
- Nothing to report.

EEE:
- EEE reminds the update of SA1 motion loop (to allow work for Hirex) will take place today.

VAC:
- Not present.

XPD:
- Progressing with tunnel works, e.g. installation of viewports.
- A. Koch asks on the tunnel closure plans for XTD6 and XTD9. 
A. Galler says XTD9 will close around February 5th and for XTD6 one has to discuss with MXL-DESY on the possibility to keep it open for one week longer (until 12.02).

DET:
- Nothing to report on detector operation.

ITDM: 
- ITDM needs to finalize GPFS work which requires one day maintenance. The proposed date is next Monday 25.01. It means no access to data from Maxwell during the all day.
Instruments shall contact ITDM until tomorrow 21.01 in case of restrictions. 
- Tickets on e-mail lists (e.g. not authorized sending e-mails to some lists): ITDM is investigating.

XRO:
- XTD6 will have photon beam for recommissioning during the third week of February.

LAS:
- LAS asks instruments on their plans for when to use lasers (mid-February?). HED and MID confirm plans to have it by middle February. SQS, FXE and SCS will consult 
internally and let LAS known.

UNSYS:
- Two quad movers in SA2 are working again.
- Afterburner (winter shutdown tasks): Fire extinguishing system to be build; Cleaning the tunnel has to be made prior switching on the PKG.

SPB:
- Nothing to report.

FXE:
- Upgrade of Jungfrau and related work is postponed to Friday.

MID:
- All fine at MID.

HED:
- Nothing to report.

SCS:
- Nothing to report.

SQS:
- Nothing to report.
  191   18 Jan 2021, 09:44 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 18.01.2021
General Announcement:
- Clarification on the definition of a critical work will be made this afternoon during a discussion with group leaders and will be communicated to the staff. 
It includes also tasks carried out by two different groups.
- On Thursday there is going to be a switch of MPS components in the balcony room. 
This affects the timing signal distributed to XFEL, e.g. Lasers will not be able to follow timing. 
- Test of automatic switch of power bridge is shifted to Feb.2: this affects all devices connected to orange or green power sockets (no power for few seconds/minute).
General e-mail will be sent. Instruments will need to care for equipment which is connected to these sockets. 
This also affects the E0 level as well as office space in XHQ. Pease plug devices out or re-plug in other sockets.

CTRL:
- CTRL enquires ITDM on the issue with DOC (disk space full error). ITDM will take a look into it. 

DA:
- Getting prepared for involvements such as the data operation center.

EEE:
- Update of SA1 loop motion to take place by Wednesday. Affected staff is already informed.
- Firma Wille work on cabling is ongoing.

VAC:
- Continuing with works in the tunnels.

XPD:
- Tunnels works in XTD6 and XTD9 are ongoing. No incidents to report.

DET:
- Working on data analysis calibrations and installing the DOC.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- Regarding the Timing signal interruption mentioned in general announcements: it is not a problem as usually LAS keep the laser systems in the local timing during 
shutdown periods.
- Upgrading hardware that should be updated accordingly to the plans for the shutdown.

UNSYS:
- Works in tunnel are proceeding.
- Issues with SA2 cell 26 and cell27 were found and experts are going to the tunnel to solve it.

SPB:
- Working on making experimental plans for the Covid-19 beamtime.

FXE:
- Detectors: software upgrade taking place from today.

MID:
- All fine.

HED:
- Nothing to report.

SCS:
- Nothing to report.

SQS:
- Nothing to report.
  190   13 Jan 2021, 10:04 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 13.01.2021
General Announcement:
- Test of power grid switching affecting green and orange power sockets: this was planned for tomorrow 14.01 but it is not shifted to 02.02. 
For a second or so it may trigger power OFF in equipment. Groups have to identify devices that are connected to these sockets, for example at the instrument hutches. 
Devices shall be made safe. On the instruments rack room, equipment have two power supplies and therefore they shall be transparent to this intervention. 

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- Today EEE connects the new PLC for the AIBS project in SASE1 balcony room. One needs to restart momentarily EPS, SPB and FXE loops in SASE1 Tunnel after lunch. 
An e-mail was sent yesterday and clarified with instruments.

VAC:
- Tunnels are closed today for the interlock tests. XO thanks HED and FXE for making their hutches available.

XPD:
- Tomorrow XPD restarts with tunnel works, e.g., alignment of PES/XTD10 together with MEA.

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- Not present.

LAS:
- Proceeding with small steps but lasers are OFF.
- LAS waits for feedback from SRP and MB on the safety issue. Thomas Tschentscher will bring the safety issue to be discussed offline with MB, LAS and SRP.  
Zunaira A. questions if there were problems to re-start the Seeder Lock-in. Tomasz Z. says it is currently locked but after much additional work (no guarantee it can be 
locked again if Seeder is once more OFF). 

UNSYS:
- Working in the completion of SA3 undulator system.

SPB:
- Drilling ongoing: please keep in mind access to hutch may be affected.

FXE:
- Nothing to add.

MID:
- Wille Firma is working on cabling installation from today afternoon.

HED:
- Expecting Wille will be working from today but shall not interfere with Interlock tests. Zunaira A. says that interlock activities take around 20 minutes during this 
afternoon.

SCS:
- An external company is currently working onsite.

SQS:
- Nothing to report.
  189   11 Jan 2021, 10:54 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 11.01.2021
General Announcement:
- The Interlock test light in the hutches take place on January 13th. From tomorrow is starts in the tunnels. 
We understand no support from instruments are needed and we thank HED and FXE for making their hutches available for these tests.
- A Functional interlock test was planned for the end of January. This will be shifted to later point in time.
- XO states that planned maintenance tasks that are critical for operation can of course be performed onsite at the XFEL campus. 

CTRL:
- Updated the microTCA crates was done.
- CTRL is testing many other systems.

DA:
- Nothing general to report.

EEE:
- Critical task to do related to the AIBS CPU: one power bridge is missing. EEE has to check and may need to switch one PLC off to replace the power bridge.

VAC:
- Continuing with tunnel installation works: urgent tasks.

XPD:
- No incidents to report. Tunnel works are ongoing together with VAC.
- Jan G. informed that not all channels are working in fast-ADC devices. XPD has informed CTRL and Steffen H. says that CTRL and EEE will take a look together.

DET:
- LPD calibration pipeline work is ongoing.

ITDM: 
- Nothing to report.

XRO:
- Ion pumps in SA1/3 photon beam transport are running. Pressure is in the order of 10^-8mbar.
- SA3 mc2 library update: continuing with checks some small items will need to be commissioned with beam.

LAS:
- Nothing to report.

UNSYS:
- Finishing small tasks at SA3 tunnel.

SPB:
- Start planning the revised schedule.
- XO informs that the emergency power OFF test takes place today in SA1 instruments. 

FXE:
- Nothing to add.
- XO informs that the emergency power OFF test takes place today in SA1 instruments.

MID:
- All fine at MID.

HED:
- Nothing to report.

SCS:
- Not present.

SQS:
- Nothing to report.
  188   06 Jan 2021, 09:05 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 06.01.2021

General Announcement:

  • Due to work restrictions, some of shutdown activities will not end as planned in time. This leads to a prolongation of the start-up phase starting next week. It means re-start of Accelerator and South branch will be delayed by 2-4 days while the North branch by about 1 week.
  • The first 2 weeks of X-Ray delivery (2.2-15.2) will most likely be affected and photon delivery cannot be guaranteed into all beam-lines at all days. Some flexibility in planning for the commissioning tasks is expected. A detailed schedule for an upcoming week will be available on the week before, latest on Friday.
  • Sara C. asks if tunnel access is allowed during this week. F. Wolff-Fabris understands tunnels still can be accessed this week apart of Covid regulations (in the context of tunnel maintenance tasks that have to be performed while tunnels are open). T. Tschentscher says the understanding is from Robert F. guidelines e-mail are still valid for this week and really important tasks may be conducted – an e-mail to Robert and Nicole pointing the task with the need of access could be sent. Steve A. reported from today’s Covid taskforce meeting that the regulations of last corona email are still valid - if there are any question send an email to health@xfel.eu.

CTRL:

- Due to incompatibility discovered after last update on Dec. 23rd, CTRL would like to update files on all microTCAs before user operation (Karabo devices) mostly likely next Friday.

- A network maintenance was performed by Desy. Please inform CTRL if issues are encountered.

DA:

- nothing to report

EEE:

- Preparing to finish the cabling in HED and MID.

- Nothing to report from PLC side.

VAC:

- nothing to report - tunnel update tomorrow

XPD:

- XPD OCD put in place during Christmas break had no emergencies calls.

- XPD expect earliest work to take place on next week.

DET:

- nothing to report

ITDM:

- Desy network team would like to do a update of the control network routers tomorrow at 1300 -> email comes to readiness

XRO:

- Proceeding with activities from last days of last year.

- No major updates. Testing the SA3 MC2 library update.

LAS:

- Lasers are down.

- SA2 seeder that took longer than expected time to be back in December after the OFF request by LSO. Probably on next OFF mode LAS has to exchange it.

UNSYS:

- Minimum gaps for SASE3 Undulator system is 10mm. Other SASEs shall be defined after the middle plan scans.

- Apple-X major work from Unsys is done.  

- Quad movers are working remotely.

- Remaining task: connecting fire extinguisher system in one rack.

SPB:

- nothing to report

FXE:

- nothing to add

MID:

- nothing to report

HED:

- nothing to report

SCS:

- not present

SQS:

- A High voltage power supply with double-polarity was installed. It is the first time this is installed at SQS.

  187   16 Dec 2020, 09:11 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 16.12.2020

General Announcement:

- Today is the last xo-integration meeting for this year. Xo wants to thank everyone for the participating in this meeting series while sharing information and giving updates.

- The next XO Int. Meeting will happen on 04 January.

CTRL:

- Beckhoff MC2 motor upgrades at SA3 is ongoing.

DA:

- no updates

EEE:

- all SA2 fast ADC tasks have been concluded.

- Cabling in HED is ongoing; On MID will happen next year.

- AIBS control at SA1 balcony room installation starts today.

- Testing Mc2 motor configurations in tunnel devices.

VAC:

- Trying to finish main shutdown tasks: GATT, new mirror chamber in SA3/SXP, SA2 M3 mirror chamber.

- M3 chamber InGa is clean and ready to be pumped down.

- XGM/SA1: broken gate will be replaced this week or next.

- Some members of VAC group are working on site next week.

XPD:

- XGM SA2/XTD6 was moved 4mm and is still in alignment (no damage found) -> Jan G and Harald S. will have a look today onsite. M. Dommach says the differential pump could not move that far away due to bellows. 

- Installing of switches for HRIX will be most likely finished this month and some maybe in January.

DET:

- nothing to report.

ITDM:

- nothing today.

XRO:

- Not present.

LAS:

- Laser Hutches are locked (no access allowed) by Safety and LAS members can not continue the work in laser rooms. LAS maintenance tasks can not be finished and may be delayed over the end of shutdown.

- Emission of SASE2 Seeder laser was put in OFF yesterday due to inspection by SLSO. This means laser was OFF and there is no guarantee the PP-laser will be available in February, as they will not start mode-locking again after an Emission OFF. 

- Typically the Seeder lifetime is 3-4 years. Each time it is switched OFF it shortens the lifetime by half. If Seeder is included in the Interlock system, and taking into account the interlock trips 1 time per week or month (case of SASE3), the availability of PP-lasers is in risk and consequently the whole operation for instruments.

- Alignment lasers will be no longer provided. This also relates to the safety decision - such lasers are not allowed to be operated.

UNSYS:

- not present.

SPB:

- nothing to report: quiet days.

FXE:

- Craning activities over the hutches due to SXP construction still ongoing: not always a notice from construction workers.

MID:

- all fine.

HED:

- nothing to report.

SCS:

- not present.

SQS:

- nothing to report

  186   14 Dec 2020, 09:00 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 14.12.2020

General Announcement:

- Please write to xo.planning, if something comes up with intteruption of the maintenance due to new COVID-19 regulations.

CTRL:

- Migration of Beckhoff MC2 motors at SA3.

- Checking operation (e.g. soft mono at SA3).

- Final checks together with EEE.

DA:

- nothing to report

EEE:

- Migration at SA3 MC2 PLC´s.

- Fast ADC: SA2 maintenance starts.

- Cabling to be done in SQS today and tomorrow at HED.

- Crate was sent to Poland and shall arrive this week.

VAC:

- not present.

XPD:

- problem / alarm XGM at SASE1 / XTD2  - Needs to re-cable and install new gauges; requires VAC group.

- PES was re-installed in XTD10 and has been pumped down.

- DAQ test on friday - things are fine.

- XTD6 XGM alignment starts today - used to be confirmed with VAC.

DET:

- AGIPD intervention: need some internal coordination also with DASY groups - it will let XO know, if support needed

ITDM:

- XFEL gateway next Monday

- pre-anouncement: 90% of maxwell cluster update to be done on January 4/5. Communication to be send to Readiness mailing list.

XRO:

- Testing Controls in tunnel devices - needs to fix SA3 expected bugs.

- XTD10 close the vaccuum for M6 mirror chamber this week.

- XTD6 some problems with M3 mirror: to be pumped down this week and checked start of January.

LAS:

- Small delay on works at SA3, but no risk for users.

- Question from LAS: is the SA1 laser interlock update takes place?

- SA2 AMPHOS: external company is coming today

UNSYS:

- not present

SPB:

- nothing to report

FXE:

- nothing to report

MID:

- all fine

HED:

- don´t have anything

SCS:

- nothing to report

SQS:

- nothing to report

  185   09 Dec 2020, 10:24 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 09.12.2020
General Announcement:
- Regarding the e-mail related to the general radiation training and procedure to deliver a signed certificate, one can also send it by conventional post to Zunaira A.

CTRL:
- BKR machines has been updated to the new Karabo release.
- The Notification service update will follow form today.
- CTRL reminds on getting configuration from the timing feature on the GUI: right click on the device and then "get configuration". 
An e-mail with detailed instructions will be sent today.

DA:
- Nothing to report.

EEE:
- Fast electronics: SASE3 maintenance is finished; SA2 will follow.
- PLC side: SQS has some loops running but not all of them due to the cooling issue. SCS will get their loops soon running.
- Cabling works at FXE is completed; at HED is ongoing.

VAC:
- Not present due to tunnel activities.

XPD:
- XPD has completed PES beamtime at Petra. Would like to thank ITDM for the smooth work. XPD has collected data for over 300 runs.
- Today XPD brings back other PES to SA3 tunnel. There is an appointment with MEA and the plan is to connect to the beamline tomorrow together with VAC.
- A. Koch asks EEE at CTRL if DAQ tests on XPD tunnel devices can happen on Friday. 
Nerea J. points SA3 is not yet commissioned (has to check motors) but SA1 and SA2 can be done on Friday as it has only pending vacuum update. 
Steffen H. says that cameras can be tested in all 3 SASEs; connections shall be fine; requests a list of all cameras. 
Jan G. adds the idea is to verify the components can be operated and acquire data, following a test with XPD/ITDM. 
Steffen H. reminds that for testing the digitizers one has to re-start (faster ADC) the device server. 

DET:
- Not present.

ITDM: 
- Nothing to report.

XRO:
- Nothing present.

LAS:
- Lasers are on good track.
- Interlock tests: there was miscommunication. The SA2 AMPHOS is disassembled for maintenance and therefore the PP-laser test in SA2 is postponed to next week. 

UNSYS:
- Not present.

SPB:
- Nearly done with putting together the AGIPD. The Final test for DQA begin next week.
- Problem with timing but currently it has been running on local mode.

FXE:
- Not present.

MID:
- All fine at MID.

HED:
- Nothing to report.

SCS:
- Not present.

SQS:
- Nothing to report.
- SQS has ongoing work on Beckhoff crates.
  184   07 Dec 2020, 11:08 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 07.12.2020
General Announcement:
-	 

CTRL:
- Deployment updates: control network topics are through - SPB to be done in January.
- BKR and notification service updates to be deployed tomorrow or Wednesday.

DA:
- Nothing to report.

EEE:
- Cabling: finishing FXE and starting HED in the course of this week.
- Fast ADC: uTCA in SCS will be restarted for updated. SCS will contact Bruno F.
- SCS racks: cooling water is disconnected. Thomas Baumann informs TS needs to order cooling water lines and only in January will be connected. 
It is suggested to run with open doors in the meantime; Nerea J. says if one needs 1-2 loops then this is fine; Thomas B., Ulf B. and Nerea J. will discuss the details. 

VAC:
- Nothing to report.

XPD:
- PES installation will happen next Wednesday/Thursday. J. Laksman will contact VAC.
- Alarms in various XGM seem last week were due to updates. It is not a real problem.

DET:
- Nothing to report.

ITDM: 
- Lennart B. coordinates with instruments.
- Due to tomorrow timing update, the upgrade of DAQ on tunnels devices to start on Friday. Others will be contacted individually.
- Jan G. asks on issues of recording DAQ of PES during Petra ongoing beamtime. K. Wrona says it would be better to be informed in advance on the beamtime. 
The issue happens due to overload with a buggy script. If this script is not running, then the issue should not repeat again. 
At Petra it is used a standard control network which is different from the one at EuXFEL.

XRO:
- Not present.

LAS:
- All lasers are in local timing mode.
- LAS requests Bruno F. to have a crate update today as they have ongoing work in SA3. Bruno F. says the updates are agreed to be done today.
- Laser interlock upgrades: there is no news or known progress.

UNSYS:
- Not present.

SPB:
- Detector intervention ongoing and nearly finished. Test with DAQ and final test by end of this week. It is expected to be ready for Monday.

FXE:
- Elektro Wille firma working in the hutch.

MID:
- All fine at MID.

HED:
- Nothing to report.

SCS:
- Water leak last week was the only major event.

SQS:
- Nothing to add.
  183   02 Dec 2020, 10:21 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 02.12.2020
General Announcement:
- Laser interlocks activities in SA2 are delayed by two days. Therefore, activity in SA1 will start later.
- Gerd W. reports the cooling water in SA3 was refilled; air conditionings are running and maintenance on them are ongoing; 
next week temperature and humidity stability in other SASEs will be working; water leakage in SCS (yesterday) has been taken care by TS (crates are not damaged).

CTRL:
- Currently working in SASE2 deployment. SASE1 deployment happened yesterday and went relatively smooth. 
- Fast ADC cards in lasers stop working. CTRL will need to look with EEE.

DA:
- Works on updates are progressing/done.

EEE:
- MicroTCA SA1 update is done. Next week continues with SASE3 update.
- Cabling installation ongoing in FXE. It will be followed by SQS, SCS and MID.
- SA2 and SA1 motion loops updates to be done this week.
- Fast ADC issue with Lasers: Bruno F. says the installed update is the last version and Karabo has also to be updated to its last version also. CTRL and EEE will discuss 
together.

VAC:
- Maintenance activities are going as expected, some tasks are ahead of schedule.

XPD:
- SA3 PES is in the lab and being replaced parts. Plan is to test it today. XPD will discuss with VAC to install back this week or next week.
- XPD received a beamtime shift in PetraIII for the PES. This influences XPD schedule as many people are involved. Beamtime starts this Friday until next Wednesday.
- DAQ tests on Tuesday morning are scheduled. XPD will talk to ITDM to postpone to after the mentioned beamtime shift. 

DET:
- Nothing major to report. AGIPD Intervention: so far, so good.

ITDM: 
- Updates ongoing.

XRO:
- Not present.

LAS:
- ADC cards problems are communicated to CTRL. 
- Observed issues with trigger delay signal and it points to issues with recent update. Currently the lasers use local timing. CTRL will investigate if this can be the 
cause.

UNSYS:
- Not present.

SPB:
- Doing OK with AGIPD intervention: expected to be ready with final tests at start of the next week.

FXE:
- Cabling installation ongoing; Today there is the crane activity for SXP.

MID:
- All fine at MID.

HED:
- Everything is fine.

SCS:
- Not present.

SQS:
- Nothing to report.