Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 253
Entry time: 23 Aug 2021, 10:03
|
Author: |
Frederik Wolff-Fabris |
Location: |
General |
Severity: |
Information |
Subject: |
Notes XO Integration Meeting 23.08.2021 |
|
|
General Announcement:
- There were two minor power glitches on Saturday morning but with negligible effects to machine.
CTRL:
- Nothing to report.
DA:
- Nothing to report.
EEE:
- Update of EPS-SA1 loop was done this morning in order to enable the FXE imagers modes.
VAC:
- Nothing to report.
XPD:
- Nothing to report.
DET:
- DSSC is installed back to SCS and put into operation last Friday.
ITDM:
- Nothing to report.
XRO:
- Not present.
LAS:
- All AMPHOS are ON and LAS is preparing PP-lasers for instruments today.
UNSYS:
- Issue with cell5/SA1 phase shifter: M. Yakopov confirms a power cycle was made to recover it.
SPB:
- Problem with Karabo (misread 2 of vacuum gauge values): the problem was a terminal of the crate was broken. After the terminal has changed, it works fine.
FXE:
- Nothing to report.
MID:
- All fine at MID.
HED:
- Nothing to report.
SCS:
- Nothing to report.
SQS:
- Nothing to report. |