Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 256     Entry time: 01 Sep 2021, 10:36
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 01.09.2021 
General Announcement:
- A change of meeting room occupancy will happen soon (increase by some %) and will be posted at each meeting room door. 

CTRL:
- Together with EEE, CTRL updated the pnCCD system and is working again. Hardware train-IDs acquisition was used by SQS yesterday afternoon and was successful.

DA:
- Nothing to report.

EEE:
- Nothing special to report.

VAC:
- Nothing to report.

XPD:
- Nothing to report.

DET:
- Follow up for the pnCCD today (offline calibration fixed). Detector is being cooled down and then data will be collected. DET supports CTRL that one had to make better plan earlier.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- Nothing to report.

UNSYS:
- Nothing to report; Cell#16 in SA3 got repaired on Monday.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- All fine at MID.

HED:
- Yesterday the beam was available for delivery later than 15:00 due to issues with machine tuning.

SCS:
- Not present.

SQS:
- Not present.