Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther, Page 16 of 31  Not logged in ELOG logo
Entry   Notes XO Integration Meeting 02.03.2022, posted by Frederik Wolff-Fabris on 02 Mar 2022, 10:12 
General Announcement:
- There is a high probability that we will run out of Helium gas due to difficulties with stock. If an instrument needs He on next weeks please get in
touch with TS to verify its availability.
Entry   Notes XO Integration Meeting 28.02.2022, posted by Frederik Wolff-Fabris on 28 Feb 2022, 10:35 
General Announcement:
- This week a facility development week takes place without user operation. XO thanks the groups for posting at the Operations-2022 e-log.
Entry   Notes XO Integration Meeting 23.02.2022, posted by Frederik Wolff-Fabris on 23 Feb 2022, 10:30 
General Announcement:
-  A. Galler reminds instruments and support groups to feel welcome in making regular entries on the Operations-2022 e-log.
Entry   Notes XO Integration Meeting 21.02.2022, posted by Frederik Wolff-Fabris on 21 Feb 2022, 11:57 
General Announcement:
- Philipp S. says a downtime for the calibration / GPFS update is to be done today at 12:00.
- Raul V. says that the biggest issue of last PRC week was related to the FXE beam pointing. In general, was a quiet and productive week. Please, instrument
Entry   Notes XO Integration Meeting 16.02.2022, posted by Frederik Wolff-Fabris on 16 Feb 2022, 10:42 
General Announcement:
- XO launched a new XO Alfresco presence. Please check there for information related to operations and do not hesitate in giving suggestions or raising
questions. 
Entry   Notes XO Integration Meeting 14.02.2022, posted by Frederik Wolff-Fabris on 14 Feb 2022, 10:02 
General Announcement:
- Thanks to instruments that posted at the Operations-2022 e-log. Please make regular entries that allow PRCs to recognize eventual issues that have to
be tracked down.
Entry   Notes XO Integration Meeting 09.02.2022, posted by Frederik Wolff-Fabris on 09 Feb 2022, 10:09 
General Announcement:

CTRL:
Entry   Notes XO Integration Meeting 07.02.2022, posted by Frederik Wolff-Fabris on 07 Feb 2022, 10:56 
General Announcement:
-  Power glitch on Sunday morning at around 04:00AM seems to have no effect at machine or Schenefeld site.
Entry   Notes XO Integration Meeting 02.02.2022, posted by Andreas Galler on 02 Feb 2022, 08:39 


General Announcement:


 


CTRL:
Entry   Notes XO Integration Meeting 31.01.2022, posted by Frederik Wolff-Fabris on 31 Jan 2022, 10:03 
General Announcement:
-  On this current run, beam delivery to instruments will start on Tuesday at 07:00AM.
Entry   Notes XO Integration Meeting 26.01.2021, posted by Frederik Wolff-Fabris on 26 Jan 2022, 10:46 
General Announcement:
- The cold compressor failed this morning and beam operation is currently stopped. We expect the beam operation for the alignment of beam systems will
resume tomorrow morning (Thursday).
Entry   Notes XO Integration Meeting 24.01.2022, posted by Frederik Wolff-Fabris on 24 Jan 2022, 11:18 
General Announcement:
- Steffen H. states DOC starts in special operation mode 09:00-17:00 for the weekdays. Jour-fixe also starts today at 13:00. Instruments are welcome to
join.
Entry   Notes XO Integration Meeting 19.01.2022, posted by Frederik Wolff-Fabris on 19 Jan 2022, 11:00 
General Announcement:
- Machine status: SA2 is currently lasing @ 9keV and 2.5mJ. North Branch was closed yesterday and after a quick ZZ in XTD10 this morning the BBA and tuning
will resume today and tomorrow.
Entry   Notes XO Integration Meeting 17.01.2022, posted by Frederik Wolff-Fabris on 17 Jan 2022, 10:41 
General Announcement:
- SEPS interlock tests are scheduled for this Friday January 21st; Zunaira A. needs XTD6 closed by the SEPS interlock at 09:00. 
Martin D. will evaluate if it is possible to close XTD6 before Friday pending to finish the work (without closed vacuum we won't have beam in future).
Entry   Notes XO Integration Meeting 12.01.2022, posted by Frederik Wolff-Fabris on 12 Jan 2022, 10:06 
General Announcement:
- SEPS interlock tests are scheduled for January 21st: starting early morning from 08:00 to 16:00 across all the SASEs; 
In parallel D-3 tests the interlocks in all hutches including SXP. An e-mail to instruments was sent and a reply has to be directed to Zunaira A.
Entry   Notes XO Integration Meeting 10.01.2022, posted by Frederik Wolff-Fabris on 10 Jan 2022, 09:22 
General Announcement:
- The "Readiness" mailing list will be discontinued and substituted by the "xo-info@xfel.eu" list. This new list is owned by XO and please use it in future
for sharing information to a broad audience.
Entry   Notes XO Integration Meeting 05.01.2022, posted by Andreas Galler on 05 Jan 2022, 09:29 


General Announcement:


 


CTRL:
Entry   Notes XO integration meeting 20.12.2021, posted by Andreas Galler on 20 Dec 2021, 09:25 
General Announcement:


 


CTRL:


no update


DA:
Entry   Notes XO Integration Meeting 15.12.2021, posted by Frederik Wolff-Fabris on 15 Dec 2021, 10:26 
General Announcement:
- Severe power cut affected Schenefeld campus yesterday: it seems to be associated to human error but investigations are still ongoing. As soon as information
will be available, it will be distributed via 
Entry   Notes XO Integration Meeting 13.12.2021, posted by Frederik Wolff-Fabris on 13 Dec 2021, 10:51 
General Announcement:
- The cooling water various types shall be working/restored and it seems that temperatures are back to normal. In case of finding deviations in temperatures
let TS or XO know. Racks and racks rooms can in 