General Announcement:
- Interlock tests in tunnels start today so there is no tunnel access today. Tests are finishing tomorrow and then tunnel search is taking place.

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- Deployment of new version of new ADC is taking place. Tutorials for new features are offered for interested groups. Please contact Bruno Fernandes for information.
- SA3 work is done (Nerea J. / Maurizio V.)

VAC:
- Not present.

XPD:
- Everything is fine.

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- Maurizio V. reports that vacuum level in M6 chamber in XTD10 is not progressing well and it is under investigation; some measures and discussions may take place in 1-2 weeks if things do not go well;
Apart of this, tests were successfully done together with EEE and CTRL. 

LAS:
- Back on track and PP-lasers are going up.

UNSYS:
- All good.

SPB:
- Preparing for tests and configurations for the start of next user run.

FXE:
- Today there will be Mono heater tests in XTD9 MONO.

MID:
- All fine at MID.

HED:
- Nothing to report.

SCS:
- Shutdown activities are ongoing; it will discuss with EEE and CTRL on updates.

SQS:
- Not present.