Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 338
Entry time: 04 Jul 2022, 09:30
|
Author: |
Andreas Galler |
Location: |
General |
Severity: |
Information |
Subject: |
Notes XO Integration Meeting 04.07.2022 |
|
|
General Announcement:
- M. Döring:
- almost all of the activities that should have been done until last Friday had been done
CTRL:
- last week karabo topic updates had finishedexcept for LAS
-
DA:
EEE:
VAC:
- leak search on M6 (SA3) chamber
- leak search in XTD9
- all in all well
XPD:
- almost all tasks have been completed
- XTD1 new crate connected on Friday,
DET:
ITDM:
- all updates are finsihed
- some activities continuing on the offsite --> should be comüpletely transparent
- after the prox change there are some PCs which are using the old host names --> relavant people will be contacted by Janusz Szuba
XRO:
- M6 mirror installation beign finished
- end switch checks shoudl be finished by today
- ramp up procedure being written down
- instruments are asked to submit any additional requests for ramp up
LAS:
- fastADCs should be finished by Wed this wek
UNSYS:
- control system has to be adjusted after removal of APPLE X, i.e. the control system looks for motors and
SPB/SFX:
FXE:
- motor commissioning ongoing
MID:
HED:
- when modifying cables downstairs, make sure modules upstairs are switched off
SCS:
SQS:
DRC
PRC
- SCS incident on Monday, photon energy scanning script was left running --> had to be stopped manually
|