Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 343
Entry time: 20 Jul 2022, 09:30
|
Author: |
Andreas Galler |
Location: |
General |
Severity: |
Information |
Subject: |
Notes XO Integration Meeting 20.07.2022 |
|
|
General Announcement:
CTRL:
DA:
- currently there is a gpfs issue affecting the online cluster
- delays in online analysis have to be expected
- delays in obtaining new constants, can take much longer than normally -->
EEE:
- nothing to report
- a couple of boards are not reachable, maybe connected to the power glitch we've had
VAC:
- ongoing activities
- XTD 6&9
- HED Mono works closing
- SXP beamline ready for beam
- operation at very low photon energies at SA3:
- GATT will use Ar --> System had been tested
- power glitch yesterday was seen in water distribution
XPD:
- ZZ on Tuesday for XTD1 SR imager camera
DET:
ITDM:
XRO:
LAS:
UNSYS:
SPB/SFX:
- issue with Elmo motors had been mitigated
- DA and Detector recovery
FXE:
- acces to air comperssor and support for moving LPD required for July 22nd for BTM tests.
MID:
- after loop update wrong parameters had been put to LDM motors
HED:
SCS:
SQS:
DRC
PRC
|