Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 341
Entry time: 13 Jul 2022, 09:59
|
Author: |
Frederik Wolff-Fabris |
Location: |
General |
Severity: |
Information |
Subject: |
Notes XO Integration Meeting 13.07.2022 |
|
|
General Announcement:
- Today and tomorrow the TUV / Interlock tests are taking place. Emergency OFF are bridged and work in the area is possible only with an EQP present.
CTRL:
- Nothing to report.
DA:
- Nothing to report.
EEE:
- Planned the Run over of the shutdown with instruments: starting with SPB today but an issue with SPB Elmo controller has to be fixed first. Handover tests will start today or tomorrow.
- EEE was informed by M. Petrich that an ion pump in tunnel shows problems and is under investigation.
- A PLC update for the gas attenuator will take place today.
VAC:
- Nothing to report.
XPD:
- Nothing to report.
DET:
- Progressing with tests for the cooling pipes at DSSC detector.
ITDM:
- Nothing to report.
XRO:
- Not present.
LAS:
- Timing system issues: ongoing with uTCA investigation; Lars F. from Desy is a contact point.
UNSYS:
- Issues with feedback of ambient field correction SA1/cell14: ZZ is scheduled for today.
SPB:
- Test of CTRL and EEE - some small issues to solve.
FXE:
- Nothing to report.
MID:
- Not present.
HED:
- Not present.
SCS:
- Testing devices: some devices issues in tunnels updates are solved.
SQS:
- Not present. |