ID Date Author Location Severity Subject
  352   24 Aug 2022, 09:28 Andreas GallerGeneralInformationNotes XO Integration Meeting 24.08.2022

General Announcement:

  •  

CTRL:

  • nothing special

DA:

  • nothing

EEE:

  • actions from Monday (SA3 PLC master update,  PNACT testing) successful

VAC:

  • vacuum ok

XPD:

  • nothing

DET:

  • nothing major to report

ITDM:

  • nothing to report

XRO:

  • nothing to discuss

LAS:

  • nothing

UNSYS: 

  • nothing

SPB/SFX:

  • nothing

FXE:

  • all fine

MID:

  • all fine

HED:

  • undulator setting off by 100 eV --> HED had means to accurately measure the delivered photon energy and compensate for that.

SCS:

  • nothing

SQS:

  • nothing

DRC

  • nothing

PRC

  • nothing

 

  351   22 Aug 2022, 09:50 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 21.03.2022
General Announcement:
- Power glitch on Saturday morning took two cryo streets down and beam was recovered more than 24:00 later.
- Naresh K. as PRC reminds instruments to retract CRLs and place beamlines in safe state after ending the beamtime on Mondays.
- P. Schmidt as DRC reports that minor issues were addressed on Sunday after beam was back.

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- PLC team busy today for testing the tunnel PNACT remotely.
- SA3 PLC master upgrade also happening today from 10:00.

VAC:
- Saturday's power glitch did not affect any vacuum devices this time.

XPD:
- Nothing to report.
- Naresh K., as PRC, reports MID got 30mins more beam as agreed with operators.

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- Ask SCS for confirmation if it is needed to change PP-laser rep rate this week. SCS will confirm later.

UNSYS:
- Nothing to report.

SPB:
- Intervention last night was advertised 20 mins but took 1 hour.

FXE:
- Issue with digitizers for detector was solved.

MID:
- User experiment on THU/FRI went good.
- Second user experiment on SAT/SUN received about 12hs of beam delivery; no outcome.

HED:
- Nothing to report.

SCS:
- Suffered from downtime.

SQS:
- Nothing to report.
  350   17 Aug 2022, 11:19 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 17.08.2022
General Announcement:
-  Machine is currently set at 12 GeV to best accommodate the requests for the next 3 weeks.

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- SA1-PP laser update is done and no problems are seen now.

VAC:
- Nothing to report.

XPD:
- Jan G. informs as PRC the machine had difficulties to tune SA1 and SA2 yesterday. However overnight intensities improved by a factor 2 and are now higher or equal than 1 mJ (6keV at SA1 and 9keV in SA2).

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- Nothing to report.

UNSYS:
- Nothing to report.

SPB:
- Started using beam to pre-align mirrors last night.
- Intensity is lower than expected to start with. To be seen if user program will be affected.

FXE:
- FXE performed the work as planned last weekend. When changing undulator gap on Sunday beam jitter occurred.

MID:
- Still need 352 pulses for this week; Pre-tuning at 12keV was done during the night with 500uJ intensity.
- A stage has to be implemented for the user runs together with G. Giovanetti.

HED:
- Not present.

SCS:
- Nothing to report.

SQS:
- Maurizio V. asks on the last week’s photon energies (lower values) and would like to discuss with SQS the performance of the beamline transport concerning the C absorption (mirrors). SQS will look 
together with XRO.
  349   15 Aug 2022, 09:49 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 15.08.2022
General Announcement:
-  On Saturday 4AM there was a very short power glitch. Machine kept running and to our best knowledge only the SA3 GATT had to be reset afterwards. 
If any group find any other affected device, please inform XO or the PRC.

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- Updates for SA1 PP-laser are coordinated with LAS.
- OCD call yesterday to replace motor on site (HED?).

VAC:
- Issue with GATT on Saturday early morning. It was resolved by SQS and VAC-OCD. Under investigation; it may be related to a drop of cooling water flow.

XPD:
- Nothing to report regarding XPD and PRC duties.

DET:
- Nothing to report.

ITDM: 
- Small issue related to Graphana but fixed on Saturday.

XRO:
- Nothing to report.

LAS:
- Nothing to report.

UNSYS:
- Small issue with PS cell33/SA2: fixed and working by now.

SPB:
- Nothing to report.

FXE:
- No info on the beam usage over the weekend.

MID:
- All fine.

HED:
- Used beam from Friday until Sunday 23:00.

SCS:
- Using TOPAS for laser: some instability was found and shall be checked today together with LAS.

SQS:
- No news from the user program.
  348   10 Aug 2022, 09:56 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 10.08.2022
General Announcement:
- Machine has restarted after the cryo failure: SA3 is receiving photons and tuning in SA1 and SA2 tunings are still ongoing.
- The SA3 beam pointing position (by the crosshair) was fixed on Monday. 

CTRL:
- Request on background effects on XTD2/SA1 Imager is ready to be deployed. SPB/SFX agreed to install now as there is no beam. A. Parenti will get in touch with SPB/SFX.

DA:
- Calibration constant (low) performance issue on the GPFS cache is solved. If issues still appear please contact Philipp S.

EEE:
- Nothing to report.

VAC:
- GATT SA3 is set with Ar operation. VAC needs to make tests (30 mins) regarding the injection issue that appears eventually and it will get in touch with SQS for defining a suitable time.

XPD:
- Nothing to report.

DET:
- Nothing major to report.

ITDM: 
- Nothing to report.

XRO:
- Not present.

LAS:
- Nothing to report.
- Lasermet was contacted and no news by now.

UNSYS:
- Issue with cell33/SA2 not moving yesterday night was fixed by now.

SPB:
- Reports a misunderstanding with BKR on the requested 6keV photon energy.

FXE:
- Nothing to report.

MID:
- Nothing to report.

HED:
- Nothing to report.

SCS:
- Not present.

SQS:
- Nothing to report. SQS will contact Martin D. for the tests on the GATT.
  347   08 Aug 2022, 09:54 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 08.08.2022
General Announcement:
- The accelerator is down since Sunday morning. An oil pump of the warm compressor failed at around 7;00AM. In the afternoon a temperature of a cold compressor bearing raised and had to be exchanged. 
Cryo OK is expected today at 22:00. The operation for the current week will be updated by XO as soon as news are shared. 
- Harald Sinn as PRC informs the SA3 pointing is not so perfect (issues with crosshairs). Center of aperture is currently being used by SCS. 
SQS still has to find if actual position is good. When A. Koch is back this shall be revisited.

CTRL:
- Nothing to report.

DA:
- Nothing to report.
- Update of GPFS online analysis issues: mitigations put in place are working. 

EEE:
- One issue with a motor was solved by the DOC on Saturday.

VAC:
- Nothing to report.

XPD:
- Nothing to report.

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.
- M2 mirror in SQS (new feature reported last week): no news.

LAS:
- FXE reported PP-laser to have long pulse duration and small beam profile at hutch. LAS is discussing and investigating with FXE. An update will be done by end of the day.
- SA3 PP-laser: SCS reported not been able to open instrument hutch. A restart /re-cycling of laser interlock was done and worked properly, consequently shall not be the issue's origin. 
SCS shall contact SRP and Lasermet. A proposition is to use dummy connector but needs to be discussed with SRP.

UNSYS:
- Nothing to report.

SPB:
- Nothing to report; Program of last week could be carried out.

FXE:
- Nothing to report.

MID:
- All fine at MID.

HED:
- Nothing to report.

SCS:
- Not present.

SQS:
- Nothing to report.
  346   03 Aug 2022, 10:10 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 03.08.2022
General Announcement:
- Regarding the cw32 photon energies: it is expected for 8 GeV to have up to 6keV for the Hard X-ray beamlines. A third harmonic attempt at SA2 will be made. Expected photon intensities are in the order of 
500uJ.
- DOC shall run OK for operation regarding the number of available staff members. It includes people working remotely.
- SEPS interlock was approved last Monday and Tuesday. For questions please get in touch with Zunaira A.
- Harald Sinn as PRC reports: 
1. that yesterday there was a malfunction at SA1 and SA2 hutch search; together with Eric Boyd and Desy colleagues a fast replacement of devices was done; 
2. A confusion between change from SQS and SCS: not clear what time the change would have to be made and it was finally decided to do this morning; it requires Theo involvement.

CTRL:
- Follow-up of SA2 VAC loop: EEE changed the timing for the triggering updates and it seems to have improved; no slowness was seen since them. A fine tuning of the parameter will be made.

DA:
- Nothing to report.

EEE:
- Finishing the handover activities;
- PLC team working with CTRL to mitigate VAC loop issues;
- Fast electronics working with updates;
- Timing configurations were updated yesterday.

VAC:
- Apart of the VAC loop, nothing to report.

XPD:
- SXP Imager had a long exposure time but it is now fixed.

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- Recommissioned devices after the summer maintenance period. Feedback from instruments would be highly appreciated.
- SQS and SCS found features on M2 mirror in SA3 that needs more investigation (a fresh area of the mirror to be used was found).

LAS:
- SA2 PP-laser is working.
- PP-laser beam for FXE shall be ready for today; For SPB on next Monday.
- SA3 PP-laser for SCS is handled; for SQS will be ready on Monday.

UNSYS:
- Nothing to report.

SPB:
- Yesterday XGM was not instantiated but it may be solved by EEE.

FXE:
- Not present.

MID:
- EPS system triggered limit of 300 pulses; It seems to be related to a foil / diamond detector system. MID was not informed of this change in EPS. 
Nerea J. informs that the new entry at EPS was a request from XPD. Harald S. says an option is to the machine to increase the EPS to 360 pulses.  
- RF window was allowing only 272 pulses and not the requested 352 pulses.

HED:
- Nothing to report.

SCS:
- Not present.

SQS:
- Alberto Defanis says that the new mirror region found is not fully understood by SQS staff.
- Problem with the digitizer: shows an artefact and a discussion with the manufacturer is ongoing and may require its intervention. EEE is on the loop.
  345   01 Aug 2022, 10:02 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 01.08.2022
General Announcement:
- Today the SEPS interlock tests take place at all SASEs. This happens usually after maintenance periods and shall use the full day.
- For cw32: above 6.5keV only intensities of 500uJ shall be expected. An e-mail will be distributed by XO.

CTRL:
- SASE2 and SASE3 vacuum loops were not responding; both VAC loops were restarted.

DA:
- Nothing to report.

EEE:
- PLC team is doing a ZZ in XTD6 and handover to the instruments.
- This morning timing servers to be restarted (5 sec intervention) - no control on triggers during this time; the signals for triggering continue to be generated.

VAC:
- Issues with SA2 and SA3 loops already reported.

XPD:
- All fine with XPD.
- Gas changes for XGM are organized with Theo.

DET:
- Nothing major to report.

ITDM: 
- Nothing new to report.
- GPFS problem reported last week: meeting with Desy experts is to take place.

XRO:
- XRO worked with SA3 on Saturday: M6 new mirror commissioned (found new position for this mirror); optical path for SCS and SQS is established.
- Vertical slit checked and not damaged; Device is working; Interlock was tested and an e-mail will be sent.
- Prepared for SEPS interlock tests of today (many modifications).
- Still to be done: beam illuminating SXP tunnel (maybe POP-IN imager is not working, but not sure); Still to check the soft-mono and the beam path.
- Question from Michael Meyer referring to hutch access today: as Interlock tests take place at 16:00, hutch access when closing the shutter has to be discussed with Safety / RPOs. 
- SA1 and SA2 beam recommissioning are done; except of the SEPS interlock tests.

LAS:
- SA2 PP-laser shall be ready to go;
- SA1 and SA3 PP-laser will be available at latest Tuesday next week. The 282kHz mode is now available for SA1. 

UNSYS:
- Air coils in SA3 cell 14 and cell20 had a problem and now it shall be solved after communicated between M. Yakopov and BKR.

SPB:
- Laser interlock issue was observed and solved.

FXE:
- Worked with D3 last week to recalibrate spare BTMs. Currently D3 had no spare parts and if the SA3 BTM would be triggered again it could stop North branch operation until a spare part would be available.
- There is an object in the beam path that can be seen: likely a cable belonging to the mono.

MID:
- All fine at MID.

HED:
- Nothing to add. HED is part of the ZZ in XTD6 together with EEE.

SCS:
- Nothing to report.

SQS:
- Nothing to report.
  344   25 Jul 2022, 09:14 Andreas GallerGeneralInformationNotes XO Integration Meeting 25.07.2022

General Announcement:

  •  

CTRL:

  • Today "bring up" works at FXE

DA:

  • Nothing special to report

EEE:

  • PLC team is trying to find solutions for slowness in big loops

VAC:

  • nothing to report

XPD:

  • nothing special

DET:

  • nothing major to report

ITDM:

  • SA2 GPFS updates today

XRO:

  • not present

LAS:

  • SA1 AMPHOS back as

UNSYS: 

  • K- Mono Scan last week
    • S. Arbeghyan assisted but new undultaor offsets will only be implemented after Aug 5th

SPB/SFX:

  • nothing special to report
  • bring up days are very successful

FXE:

  •  

MID:

  • ITDM please keep MID in the loop with SA2 GPFS updates, as MID plans to save data today
  • opening of the beam shutter is an issue
    • over the weekend MID was forced to open

HED:

  • shutter issue as MID

SCS:

  • nothing to report

SQS:

  • nothing to add

DRC

  •  

PRC

  • s

SH

  • VAC loops SA1 SA2, don't panic because of slowness

 

  343   20 Jul 2022, 09:30 Andreas GallerGeneralInformationNotes XO Integration Meeting 20.07.2022

General Announcement:

  • none

CTRL:

  • everzthing as planned
  •  

DA:

  • currently there is a gpfs issue affecting the online cluster
    • delays in online analysis have to be expected
    • delays in obtaining new constants, can take much longer than normally -->

EEE:

  • nothing to report
  • a couple of boards are not reachable, maybe connected to the power glitch we've had

VAC:

  • ongoing activities
    • XTD 6&9
      • HED Mono works closing
      • SXP beamline ready for beam
    • operation at very low photon energies at SA3:
      • GATT will use Ar --> System had been tested
  • power glitch yesterday was seen in water distribution

XPD:

  • ZZ on Tuesday for XTD1 SR imager camera
    • successful

DET:

  • nothing major to report

ITDM:

  • nothing

XRO:

  • nothing major to report
    •  

LAS:

  • nothing major to report

UNSYS: 

  • nothing to report

SPB/SFX:

  • issue with Elmo motors had been mitigated
  • DA and Detector recovery

FXE:

  • acces to air comperssor and support for moving LPD required for July 22nd for BTM tests.

MID:

  • after loop update wrong parameters had been put to LDM motors
    •  

HED:

  • not present

SCS:

  • nothing to report

SQS:

  • nothing to report

DRC

  •  

PRC

  •  

  342   18 Jul 2022, 09:31 Andreas GallerGeneralInformationNotes XO integration meeting 18.07.2022

General Announcement:

  • none

CTRL:

  • fastADC karabo Version updated
    • everything looks fine
  •  

DA:

  • nothing

EEE:

  • PLC and cabling as scheduled
  • fastADC update
    • MID and SPB issues being solved by lunch time

VAC:

  • HED Mono
  • SXP tunnel interface

XPD:

  • ZZ on Tuesday for XTD1 SR imager camera reset

DET:

  • DSSC update
    • test not yet conclusive on whether operation is safe or not.
    • current suggestion: postpone experiments until repair is done
  • AGIPD firmware update went well

ITDM:

  • nothing

XRO:

  • not present

LAS:

  • Timing issues solved, solved by Lars Froehlich
  • LAS may suffer from limited available resources

UNSYS: 

  • all fine

SPB/SFX:

  • issue with Elmo motors

FXE:

  • nothing

MID:

  • nothing
    •  

HED:

  • nothing

SCS:

  • mobile compressor will be used this week

SQS:

  • nothing

DRC

  •  

PRC

  •  

  341   13 Jul 2022, 09:59 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 13.07.2022
General Announcement:
-  Today and tomorrow the TUV / Interlock tests are taking place. Emergency OFF are bridged and work in the area is possible only with an EQP present.

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- Planned the Run over of the shutdown with instruments: starting with SPB today but an issue with SPB Elmo controller has to be fixed first. Handover tests will start today or tomorrow.
- EEE was informed by M. Petrich that an ion pump in tunnel shows problems and is under investigation.
- A PLC update for the gas attenuator will take place today.

VAC:
- Nothing to report.

XPD:
- Nothing to report.

DET:
- Progressing with tests for the cooling pipes at DSSC detector.

ITDM: 
- Nothing to report.

XRO:
- Not present.

LAS:
- Timing system issues: ongoing with uTCA investigation; Lars F. from Desy is a contact point.

UNSYS:
- Issues with feedback of ambient field correction SA1/cell14: ZZ is scheduled for today.

SPB:
- Test of CTRL and EEE - some small issues to solve.

FXE:
- Nothing to report.

MID:
- Not present.

HED:
- Not present.

SCS:
- Testing devices: some devices issues in tunnels updates are solved.

SQS:
- Not present.
  340   11 Jul 2022, 09:52 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 11.07.2022
General Announcement:
-  User Operation Meeting will re-start on cw30 (Friday 29.07).

CTRL:
- Nothing major to report.

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
- Tunnels were searched and closed last Thursday and photon tunnels XTD6 and XTD9 can be opened again when Interlock tests are done.

XPD:
- Nothing to report.

DET:
- Problem with in-vacuum cooling pipes at DSSC detector: reason is not yet known and is under investigation.

ITDM: 
- Nothing to report.

XRO:
- Not present.

LAS:
- Issues with timing system; issues with Doocs also. LAS needs to discuss with EEE and Desy groups. Patrick G. points that there is ticket with Tim Wilksen ongoing. Investigation will take place today.

UNSYS:
- Nothing to report.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- All fine at MID.
- It requests to get an information when TUEV tests are done on THU or FRI, if available.

HED:
- HED thanks EEE for solving last week's issues.

SCS:
- Nothing to report.

SQS:
- Not present.
  339   06 Jul 2022, 10:22 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 06.07.2022
General Announcement:
- Interlock tests in tunnels start today so there is no tunnel access today. Tests are finishing tomorrow and then tunnel search is taking place.

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- Deployment of new version of new ADC is taking place. Tutorials for new features are offered for interested groups. Please contact Bruno Fernandes for information.
- SA3 work is done (Nerea J. / Maurizio V.)

VAC:
- Not present.

XPD:
- Everything is fine.

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- Maurizio V. reports that vacuum level in M6 chamber in XTD10 is not progressing well and it is under investigation; some measures and discussions may take place in 1-2 weeks if things do not go well;
Apart of this, tests were successfully done together with EEE and CTRL. 

LAS:
- Back on track and PP-lasers are going up.

UNSYS:
- All good.

SPB:
- Preparing for tests and configurations for the start of next user run.

FXE:
- Today there will be Mono heater tests in XTD9 MONO.

MID:
- All fine at MID.

HED:
- Nothing to report.

SCS:
- Shutdown activities are ongoing; it will discuss with EEE and CTRL on updates.

SQS:
- Not present.
  338   04 Jul 2022, 09:30 Andreas GallerGeneralInformationNotes XO Integration Meeting 04.07.2022

General Announcement:

  • M. Döring:
    • almost all of the activities that should have been done until last Friday had been done

CTRL:

  • last week karabo topic updates had finishedexcept for LAS
  •  

DA:

  • nothing

EEE:

  • SA3 exit slit

VAC:

  • leak search on M6 (SA3) chamber
  • leak search in XTD9
  • all in all well

XPD:

  • almost all tasks have been completed
  • XTD1 new crate connected on Friday,

DET:

  • nothing

ITDM:

  • all updates are finsihed
  • some activities continuing on the offsite --> should be comüpletely transparent
  • after the prox change there are some PCs which are using the old host names --> relavant people will be contacted by Janusz Szuba

XRO:

  • M6 mirror installation beign finished
    • end switch checks shoudl be finished by today
    • ramp up procedure being written down
      • instruments are asked to submit any additional requests for ramp up

LAS:

  • fastADCs should be finished by Wed this wek

UNSYS: 

  • control system has to be adjusted after removal of APPLE X, i.e. the control system looks for motors and

SPB/SFX:

  • checks

FXE:

  • motor commissioning ongoing

MID:

  • nothing
    •  

HED:

  • when modifying cables downstairs, make sure modules upstairs are switched off

SCS:

  • PLC updates

SQS:

  • not present

DRC

  •  

PRC

  • SCS incident on Monday, photon energy scanning script was left running --> had to be stopped manually

  337   29 Jun 2022, 09:44 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 29.06.2022
General Announcement:
- Today tasks are going on: general infrastructure as per XO infra schedule: maintenance on electrical distribution; maintenance on Climatization; cranes tests; TUV tests on elevators and dirt trap 
replacement on cooling waters. 

CTRL:
- Done with Kababo update in SA1 and SA2. Today it continues with SA3.

DA:
- Nothing to report.

EEE:
- EEE is finishing updates in tunnels (today with SA2). It is going well.

VAC:
- All going accordingly to the plan.

XPD:
- All going as planned.

DET:
- Nothing to report.

ITDM: 
- Proceeding together with CTRL on tasks.
- Tomorrow there is in the morning euxfel gateway work and sessions have to be restarted afterwards.

XRO:
- Not present.

LAS:
- Everything going on the plan.

UNSYS:
- Apple-X undulators are moved out. 

SPB:
- Maintenance tasks are ongoing.

FXE:
- Problem with CRL in XTD2 was solved.

MID:
- All fine at MID.

HED:
- Not present.

SCS:
- Not present.

SQS:
- Not present.
  336   27 Jun 2022, 10:03 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 27.06.2022
General Announcement:
- Tobias Clever confirms that elevator maintenance will take place as planned.

CTRL:
- Deployment follow-up ongoing from today on.

DA:
- Nothing of significance to report.

EEE:
- Nothing major to report. Maintenance tasks are ongoing as expected.

VAC:
- Tasks going well.

XPD:
- Not present.

DET:
- Working on tasks as expected.

ITDM: 
- Maintenance tasks are following the schedule.

XRO:
- XRO started to document at the E-log the actions that were done.

LAS:
- Everything going well so far.

UNSYS:
- The 4 Apple-X should have been removed last week; problem with transport car occurred and only one was removed; it was fixed and the remaining shall be removed today or tomorrow.

SPB:
- Not present.

FXE:
- Try to fix XTD2 CRL last Friday. Needs further assistance from EEE (already communicated).

MID:
- All fine at MID.

HED:
- Not present.

SCS:
- Nothing to report.

SQS:
- Not present.
  335   22 Jun 2022, 10:20 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 22.06.2022
General Announcement:
- An e-mail with DOC and DRC status during the maintenance period will be sent. There is no DOC but DRC will receive the calls. Also ticketing system is a way to contact. 

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- Fuse modification in tunnels and PLC updates: progressing well. 

VAC:
- No issues to report and busy inside the tunnels

XPD:
- Not present.

DET:
- AGIPD 1M at SPB: maintenance is over. Put back the faulty module online. It is working now.

ITDM: 
- Started the updates.

XRO:
- Not present.

LAS:
- Nothing to report.

UNSYS:
- Test for the Apple-X radiation: only 2 bunches were used; no signal in the Radfets and Pandora data has to be analyzed
- Yesterday started removing the cables of Apple-X.

SPB:
- Good news from detector side.

FXE:
- Nothing to report.

MID:
- All fine.

HED:
- All fine at HED; shutdown ongoing.
- Stability measurements: cooling / ventilation off between 14:00-15:00 on Monday. HED took data from HED POP-IN (two devices) and FEL imagers. 
It went well and it was seen 10-15% jitter reduction. Tunnel ventilation is not main source of jitter. 

SCS:
- Nothing to report.

SQS:
- Not present.
  334   20 Jun 2022, 10:33 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 20.06.2022
General Announcement:
- Summer maintenance period starts tomorrow; today the ramp down activities is taking place and two studies: beam stability at SA1/SA2 correlated to the air conditioning; radiation studies in SA3 
Afterburner. 
From tomorrow the tunnels are open at 07:00AM. Interlock tests at XHEPXP1 takes place between 13-15 July. In case of questions please contact Martin Doering at xo-planning@xfel.eu

CTRL:
- Starting to prepare the Karabo update that takes place from next week.

DA:
- Last week was quiet.

EEE:
- On the weekend an issue with digitizer for SQS: timing system card was misbehaving. This is a new issue, never seen before. The outputs of the timing card were generating wrong values. 
Fixed during the weekend by rewiring the digitizers/crates. Reason is not yet fully understood and may relate to config files at DOOCS.

VAC:
- Nothing to report.

XPD:
- Beam stability study this afternoon: influence of tunnel ventilation on the beam for SA1 and SA2. It takes place from 14:00-16:00.
- Participating on ramp down activities today.

DET:
- AGIPD 1M module at SPB: to be tested today.

ITDM: 
- Nothing to report.

XRO:
- Busy with ramp down activities.

LAS:
- Shutdown activities.

UNSYS:
- Nothing to report; preparing for the summer maintenance.

SPB:
- Starting with AGIPD intervention today.
- Successful last week night shifts.

FXE:
- Pulse numbering issue between Karabo / DOOCS: 1 and 0 pulses. To contact CTRL for investigation.
- Damage Si filter in XTD2 attenuator.
- Problems with beam stability during the weekend (lost 8 hours).
- FXE had data saving blocked. Origin was a not clear communication that first user should remain open until Monday 20.06. It was re-opened by ITDM after XO clearance on Friday 20:00.

MID:
- User run was cancelled on Friday evening as HXRSS was dominated by background. 
- Busy with maintenance period.
- Mirror chamber issue: it needs EEE to solve.

HED:
- Busy with tests today on the stability task. Parasitic alignment of monochromator with XRO.
- Starting shutdown activities.

SCS:
- Nothing to report.

SQS:
- Start the shutdown activities. Successful beamtime last week.
  333   15 Jun 2022, 10:40 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 15.06.2022
General Announcement:
- Currently beam delivery is suffering with gun trips at every 1 hour or so. The RCs and PRC are discussing measures to improve the situation. 
Last Monday gun conditioning did not had the desirable effect in the number of daily gun trips.

CTRL:
- Nothing to report.

DA:
- All fine.

EEE:
- Preparing for the shutdown.

VAC:
- Issue with vacuum signal at SA1 yesterday morning 04:00AM in SPB branch (controller was having faulty settings). The BKR did not call the VAC OCD or the PRC. After a ZZ this mal-function of ion pump was 
fixed.

XPD:
- Nothing to report.

DET:
- Maintenance of AGIPD 1M at SPB: modules were exchanged this week. Unfortunately, one new module is not yet working and needs further investigation.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- Nothing to report.

UNSYS:
- Not present.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- All fine at MID; under HXRSS tuning and have observed frequent gun trips.

HED:
- Nothing to report.

SCS:
- Nothing to report.

SQS:
- Nothing to report.
ELOG V3.1.4-7c3fd00