SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 377
Entry time: 28 Nov 2022, 09:58
|
Author: |
Frederik Wolff-Fabris |
Location: |
General |
Severity: |
Information |
Subject: |
Notes XO Integration Meeting 28.11.2022 |
|
|
General Announcement:
- The XO Integration Meetings will continue until the end of the year; For next year SXP will be included in the round of discussions.
- A. Galler reminds on the electrical and water supply maintenance on Saturday 3rd. Please read the latest e-mail from TS and contact xo-planning@xfel.eu in case of questions.
- SXP hutch is currently interlocked for the ramp down day. A. Scherz will ask G. Mercurio for closing also SCS experimental hutch.
CTRL:
- Nothing to report.
DA:
- All fine at DA.
EEE:
- Dates for switching OFF the PLCs for the Dec.3rd activity are available at the EuXFEL infrastructure calendar.
VAC:
- Nothing to report.
XPD:
- Working on the ramp-down activities today. Ongoing activities can be seen at Remote1 Zoom session from BKR.
DET:
- DSSC was tested in commissioned.
- SPB/SFX AGIPD modules were exchanged and detector is running again.
- No news from Jungfrau / Burst mode.
ITDM:
- Start tomorrow with online resources at balcony room updates (out of service during intervention).
- Over the weekend ITDM takes the chance to migrate InfluxDB: system not available.
- On Friday the network gateway will be updated.
XRO:
- Busy with ramp-down day.
LAS:
- Nothing to report.
UNSYS:
- Cell29/SA1 Phase shifter presents a problem and is to be fixed from tomorrow by exchanging motors.
SPB:
- Working with Agipd and ramping down for the weekend.
FXE:
- XRO is using FXE hutch for the ramp-down.
- Preparing for the power work on Saturday.
MID:
- All fine at MID; started with ramp down procedure.
HED:
- Not present.
SCS:
- Nothing to report.
SQS:
- Not present. |