Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther, Page 29 of 29  Not logged in ELOG logo
ID Date Author Location Severity Subject Text Attachments
  8   15 Feb 2019, 12:14 Adriano ViolanteGeneralInformationReport after dispatch meeting 09.00SPB/SFX


SPB requires the new trigger
solution to be implemented for AGIPD. This
  
  7   13 Feb 2019, 10:59 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 13.02.19 SPB/SFX


CSS component commissioning.
RBean is discussing with AE. Concept and
  
  6   11 Feb 2019, 09:59 Adriano ViolanteGeneralInformationMInutes of the dispatch meeting 09.30SPB/SFX


Beam is back on Wed. night.
IT
cables in D.23 were re-measured on friday.
  
  5   08 Feb 2019, 10:42 Adriano ViolanteGeneralInformationReport after dispatch meeting 09.00SPB/SFX


IT cables in D.23 were
re-measured yesterday. Waiting for the measurements.
  
  4   06 Feb 2019, 11:13 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 06.02.19 SPB/SFX


AGIPD commissioning and
tests. ==> intervention on the wings is
  
  3   04 Feb 2019, 10:17 Adriano ViolanteGeneralInformationReport after dispatch meeting 09.30SPB/SFX


Waiting for the loop 12
to be running to start the commissioning
  
  2   01 Feb 2019, 12:49 Adriano ViolanteGeneralInformationReport after dispatch meeting 09.00SPB/SFX


Open AGIPD wing. Next 3
days are needed for fixing purposes.


FXE
  
  1   30 Jan 2019, 11:26 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 30.01.19 SPB/SFX


Planned for the next 2
weeks

AGIPD commissioning and
  
ELOG V3.1.4-7c3fd00