  14  
 | 
01 Mar 2019, 14:18 | 
Adriano Violante | General | Information | Report after dispatch meeting 09.00 | SPB/SFX
 
 
 
	Today Loop 8 could be ready 
(AE)
 
	Agipd - visualization of | 
   | 
| 
  13  
 | 
27 Feb 2019, 11:27 | 
Adriano Violante | General | Information | Minutes of the Technical integration meeting 27.02.19  | SPB/SFX
 
 
 
	CSS component commissioning. 
Concept and implementation finalized. EPLAN | 
   | 
| 
  12  
 | 
25 Feb 2019, 09:52 | 
Adriano Violante | General | Information | Minutes of the dispatch meeting 09.30 | SPB/SFX
 
 
 
	Change to the triggers 
for  cameras is being discussed/implemented | 
   | 
| 
  11  
 | 
22 Feb 2019, 12:36 | 
Adriano Violante | General | Information | MInutes of the dispatch meeting 09.00 | SPB/SFX
 
 
 
	Pulse picker commissiong 
- Issues concerning motors position and triggers | 
   | 
| 
  10  
 | 
20 Feb 2019, 11:16 | 
Adriano Violante | General | Information | Minutes of the Technical integration meeting 20.02.19  | SPB/SFX
 
 
 
	CSS component commissioning. 
Concept and implementation being finalized.==> | 
   | 
| 
  9  
 | 
18 Feb 2019, 10:09 | 
Adriano Violante | General | Information | Minutes of the dispatch meeting 09.30 | SPB/SFX
 
 
 
	Data aggregators were often 
crashing during the WE and needed to be re | 
   | 
| 
  8  
 | 
15 Feb 2019, 12:14 | 
Adriano Violante | General | Information | Report after dispatch meeting 09.00 | SPB/SFX
 
 
 
	SPB requires the new trigger 
solution to be implemented for AGIPD. This | 
   | 
| 
  7  
 | 
13 Feb 2019, 10:59 | 
Adriano Violante | General | Information | Minutes of the Technical integration meeting 13.02.19  | SPB/SFX
 
 
 
	CSS component commissioning. 
RBean is discussing with AE. Concept and | 
   | 
| 
  6  
 | 
11 Feb 2019, 09:59 | 
Adriano Violante | General | Information | MInutes of the dispatch meeting 09.30 | SPB/SFX
 
 
 
	Beam is back on Wed. night.
 
	IT 
cables in D.23 were re-measured on friday. | 
   | 
| 
  5  
 | 
08 Feb 2019, 10:42 | 
Adriano Violante | General | Information | Report after dispatch meeting 09.00 | SPB/SFX
 
 
 
	IT cables in D.23 were 
re-measured yesterday. Waiting for the measurements. | 
   | 
| 
  4  
 | 
06 Feb 2019, 11:13 | 
Adriano Violante | General | Information | Minutes of the Technical integration meeting 06.02.19  | SPB/SFX
 
 
 
	AGIPD commissioning and 
tests. ==> intervention on the wings is | 
   | 
| 
  3  
 | 
04 Feb 2019, 10:17 | 
Adriano Violante | General | Information | Report after dispatch meeting 09.30 | SPB/SFX
 
 
 
	Waiting for the loop 12 
to be running to start the commissioning | 
   | 
| 
  2  
 | 
01 Feb 2019, 12:49 | 
Adriano Violante | General | Information | Report after dispatch meeting 09.00 | SPB/SFX
 
 
 
	Open AGIPD wing. Next 3 
days are needed for fixing purposes.
 
 
 
FXE | 
   | 
| 
  1  
 | 
30 Jan 2019, 11:26 | 
Adriano Violante | General | Information | Minutes of the Technical integration meeting 30.01.19  | SPB/SFX
 
 
 
	Planned for the next 2 
weeks
 
	
 
		AGIPD commissioning and | 
   |