Status report after dispatch meeting 09.30, posted by Adriano Violante on 13 Jun 2018, 10:48
|
SCS
Tests continue - List of issues sent to AE.(4/5 in total). Some of thema are related to cabling. EET will be notified.
SQS
Loop 1 - 2 issues with cables found. EET to act on that. Motors test continue
Loop 3 - Motors test continue
Loop |
Re: Status report after dispatch meeting 09.30, posted by Hugo Silva Santos on 13 Jun 2018, 11:07
|
Hi All,
Just adding more info:
CAS |
Status report after dispatch meeting 09.30, posted by Adriano Violante on 11 Jun 2018, 10:27
|
SPB
Beam delivery issues.
After several days of usage the Karabo GUI slows down. Servers are reported to have crashed a couple
of times in the last shift.
Same situation with data aggregators. Once per shift they have to be restarted. This in known to ITDM.
Interlock |
Status report after dispatch meeting 09.30, posted by Adriano Violante on 06 Jun 2018, 09:46
|
SPB
Ready for the Users run. No big issues.
The first 2 weeks of the shutdown will be used for cleaning and rearrangement of the
hutch by SPB, in preparation of the mirrors instalaltion. PLCs update and Technical interventions by TS or external companies have to be carried out |
Status report after dispatch meeting 09.30, posted by Adriano Violante on 04 Jun 2018, 10:46
|
SCS
List with the problems encountered so far during the end to end test was sent to AE. Bernard will get the info and eventually inform
EET if problems with cables are found.
SQS |
Status report after dispatch meeting 09.30, posted by Adriano Violante on 30 May 2018, 10:55
|
AE
CRLs in XTD1 being implemented
GATT and EPS loop in SASE3 being updated
SCS
Tests continue - No issues so far
SQS |
Status report after dispatch meeting 09.30, posted by Adriano Violante on 28 May 2018, 10:28
|
General
For the upcoming emergency off test in SASE1 SPB and FXE should propose a possible date in the next shutdown to be then discussed
with AE.
The machine is down due to the failure of a cryocompressor. Beam will be probably coming back tomorrow morning. Tomorrow morning will |
Status report after dispatch meeting 09.30, posted by Adriano Violante on 23 May 2018, 12:44
|
General
Please remember to send the list of the tasks you planned for the next shutdown to Monica Areste by the end of the week.
Please
remember to send the list of the alignment works needed until July to Gerd Wellenreuther.
AE |
MPS update Info from AE , posted by Adriano Violante on 16 May 2018, 13:52
|
The MPS comm for SASE 2 and FXE were tested and the only remaining part is to test the SPB to MPS changes. Tomorrow morning a timeslot will be
agreed between AE and SPB. |
Summary of the dispatch meeting 09.30, posted by Adriano Violante on 16 May 2018, 11:37
|
AE
SASE3:
-Request from Andreas Koch about interlocks for MCP and LED Power in SQS/SCS (this installation is unique in SASE3). |
Summary of the dispatch meeting 09.30, posted by Adriano Violante on 14 May 2018, 10:17
|
SQS
Loop1 still being worked by AE. Not yet up and running.
Loop 3 is needed to be up and running in 2 weeks since the mirror motors
ar eincluded in this loop and they are needed for the final check with FMB.
SCS |
Summary of the dispatch meeting 09.30, posted by Adriano Violante on 09 May 2018, 10:09
|
SPB
Test on the mirrors peltier showed some issues due to the fact that the test boxes were different from the actual stuff. R.Bean will
clarify it with FMB.
Loops 12,13 update to be done.
Magnetic turbos control: the serial communication has some issues. Being checked |
Status report after dispatch meeting 09.30, posted by Adriano Violante on 07 May 2018, 10:36
|
SPB
Loops 5,7,11, update and Karabo deployed.
Loops 12,13,8 update ongoing.
SQS
Loop1 cabled up. Today the formware will be uploaded.
Loop 2 will probably be ready on Wednesday
SCS |
Status report after dispatch meeting 09.30, posted by Adriano Violante on 02 May 2018, 11:17
|
SPB
After re-compiling the relative karabo device, the configuration procedure of the AGIPD is now smoothand reliable.
PLCs update
ongoing. AGIPD is in a safe state to allow the PLC update.
SQS |
Status report after dispatch meeting 09.30, posted by Adriano Violante on 30 Apr 2018, 09:51
|
CAS (C. Youngman)
Following the Technical commissioning phase for the SASE2 tunnel components, the need of a technical coordination activity is strongly pointed
out. This is in particular important to make sure that the proper final tests are performed by the components owner before e.g. first lasing attempts. |
Lasing SASE3, posted by Adriano Violante on 27 Apr 2018, 10:21
|
INFO
As reported by the PRC (J. Gruenert) during the operation meeting this morning, due to the first lasing attempt in SASE2 no lasing of SASE3
is to be expected until the middle of next week. |
Status report after dispatch meeting 13:00, posted by Adriano Violante on 25 Apr 2018, 13:28
|
SPB
Loops update: 1-4+8 this week. 5-7 Wed. next week. 11-13 end next week.
Smaract motors for PAM are needed and Nerea is on
it.
It is not clear whether the AGIPD firmware has to be updated. To clarify with Jola when she is back. The info is important foe ITDM to plan |
Re: Status report after dispatch meeting 13:00, posted by Alessandro Silenzi on 25 Apr 2018, 18:10
|
Regarding CAS Support for SASE2 Lasing:
CAS is happy to support in the frame of the On Call Duty system as it has been provided in the past.
Adriano |
SASE3 MOV1 loop update, posted by Marijan Stupar on 25 Apr 2018, 11:42
|
I will update the SASE3 MOV1 loop in 30 minutes. Please let me know if you would like me to postpone the update.
Best regards,
Marijan |
Status report after dispatch meeting 13:00, posted by Adriano Violante on 23 Apr 2018, 15:35
|
SPB
Timing tool for optical laser installed
Sample chamber's PLC will be updated next week due to ongoing tests until monday.
Pending.
It is not clear whether the AGIPD firmware has to be updated. To clarify with Jola when she is back. The info is important foe ITDM |
Tunnel closing after shutdown, posted by Gerd Wellenreuther on 18 Apr 2018, 15:06
|
Dear all,
below please find the hottest and most up-to-date times for the closing of the tunnels after the shutdown:
XTD1: 23.04.
XTD2: 23.04.
XTD6: not before 02.07.
XTD9: 27.04. after lunch
XTD10: |
Status report after dispatch meeting 13:00, posted by Adriano Violante on 18 Apr 2018, 13:43
|
SPB
Karabo has been deployed without major problems!
Now PLCs update follows. Sample chamber's PLC will
be updated next week due to ongoing tests until monday.
It is not clear whether the AGIPD firmware has to be updated. To clarify with Jola when |