Dear all,
EPS loop is running with the latest hardware updates. Today, when I was trying to update the loop, I have found that someone has powered off the EPS crate in XTD2 Rack 1.5. Please, if you have to do some work in any part of SASE 1, let us know about it.
Thank you! |
160
|
21 Apr 2017, 14:36 |
Tobias Freyermuth | XTD9 | Information | SASE EPS RACK 1.14 disconnect |
We have to disconnect the EPS crate in RACK 1.14 in order to check the interface to the MPS.
I will keep you updated |
163
|
21 Apr 2017, 15:30 |
Tobias Freyermuth | XTD9 | Feedback | SASE EPS RACK 1.14 connected |
The EPS-loop is now complete again.
The interface from EPS to MPS is working now. One broken wire in the cable between EPS and MPS was found. We are using now other pairs for the signals "SA1_SYS_EPS2MPS/DCTRL/MODE1", "SA1_SYS_EPS2MPS/DCTRL/MODES" and "SA1_SYS_EPS2MPS/DCTRL/MODEM".
Cheers,
Tobias |
178
|
26 Apr 2017, 18:34 |
Jan Grünert | XTD9 | Problem | SA1-VAC loop down (only XTD9) and later restarted |
Since around 17h30 all XTD9 VAC loop is in error. It came back in karabo around 17h50. XTD2 not affected.
At that point, we had to reset every single karabo device of the XGM, then restart pumps etc.
Did the same also for the DPS upstream and downstream of XGM@XTD9.
XGM vatterfly valves will be opened by me only when I see that no further errors occur.
Currently, all but one pumps were restarted, also in Rauls DPS, only one of these not |
347
|
27 Jul 2017, 15:42 |
Eric Boyd | XHEXP | Information | Restricted areas Durring Radiation Measurements of SASE 1, Friday 28.07 |
No radiation measurements have taken place today (27.07) due to insufficent energy of the machine. We think we can achive the desired energy by tomorrow morning at which time the SRP group will attemtp to commission both the SPB OPT and SPB EXP hutch. The attached presentation shows the new expected time schedule.
A log book entry will be made when area restriction goes into affect and when it is lifted. |
Attachment 1: Restricted_areas_for_measurments.pptx
|
225
|
12 May 2017, 08:21 |
Harald Sinn | General | Information | Restart vacuum loop now |
We are in the BRK and corrected the vacuum interlock condition.
We will restart the SA1 vacuum loop in a few minutes
|
238
|
16 May 2017, 15:59 |
Andreas Koch | XTD2 | Feedback | Request for imager checks |
Since tomorrow there is no beam I want to use the time for some checks of the imagers in XTD2. Please, let the motion loop up if possible until 10 am, otherwise let me know. |
592
|
16 Jan 2019, 10:20 |
Adriano Violante | General | Information | Report after dispatch meeting 09.30 |
SPB/SFX
FXE
SQS
- Power cut of the primary power line in the rackroom will occur to allow fixing of the emergency power off system (as agreed between TS ans MM last week). Happening today. After completion CAS and AE support is needed to switch the systems back on.
- AQS chamber is being removed
- New interlock definitions have to be tested and implemented asap. AE will discuss a date to SQS, although Friday might me a good time.
- SQS is eager to get the new trigger system from desy and AE and help testing it. It was noted that the trigger is linked to a specific SASE.
SCS
MID
HED
OPT Lasers
XRO
XPD
VAC
- M2 mirror has been installed, the chamber closed. MCP is being mounted back.
AE
- VAC loops updates in the tunnels are ongoing and being coordinated with affected groups
- Motion 2 in SASE2 loop needs to be updated. Being coordinated with AKoch.
- SASE3+2 implementation of changes and commissioning ongoing.
EET
ITDM
DET
- During some AGIPD test with cold detector Karabo lost connection with the PLCs. This was due to the installation of new CPUs for the SFX components. For 10 minutes was not clear whether the vacuum was OK and for safety purposes the detector has been warmed up. These works have to be properly communicated next time.
CAS
AoB
- 22/23 January Fa. LIEN will fix the sliding doors in the SASE3 hutches.
|
594
|
21 Jan 2019, 10:43 |
Adriano Violante | General | Information | Report after dispatch meeting 09.30 |
SPB/SFX
FXE
SQS
- AQS chamber has been removed. The reaction microscope is now being installed. (Currently sitting next to the beamline)
- New interlock definitions have to be tested and implemented. Some tests were performed and bugs fixed. New tests are needed and planned for Wednesday. ==> Master loop will be updated until tomorrow. Tests still planned for Wednesday.
- Mpots control and integration is still being debugged by CYoungman. Additional tests planned for tomorrow.
SCS
- All the PLC hardware is now fixed, with the exception of some high voltage interlock controls, which is waiting for the E-plan to be finalized.
- Firnware update needed and planned for the next days.
- Updated interlock definition will be given to AE by SCS
- Electronics and cabling for the laser hutch is coming next. MTeichmann will talk to EET to agree on priority concerning the cables production and pulling. It may be necessary for SCS to pull a few cables as soon as possible (by themselves?). Anyway, cables route will be needed.
- This morning the PLCs in the SCS raclroom went off. The information from TS is that the emergency power off button was pushed in the SCS experiment hutch.
MID
- Has to be clarified when the chiller is going to be back
- Homing test motors in XTD1. Small issues found. Update needed.
- MC2 Motors are working properly
- Workin out commissioning priorities with AE and CAS based on the cables availability
HED
OPT Lasers
XRO
- Tomorrow the M2 in XTD will be ready for commissioning
- On Wednesday the MOV2 loop in SASE2 tunnels will be updated. CAS is saving the motor parameters right now.
XPD
- Screens have been exchanged
- XTD2 photonic science camera is back and working
- XTD10 SQS2 pop in monitor back and working
- All tasks foreseen for the Winter shutdown have been completed.
VAC
AE
- AE was asked to update MOV1 MOV2 and EPS loops for SASE3 tunnels. This is due to the implementation of a new B4C to be mounted and controlled. ==> MOV 1 will be updated. Also CAS will be asked to save the motor parameters. NO EPS and MOV 2 loops update necessary for now.
ITDM
DET
CAS
- Data logger schould be working for every component right now.
- On Wednesday the MOV2 loop in SASE2 tunnels will be updated. CAS is saving the motor parameters right now.
AoB |
595
|
23 Jan 2019, 10:47 |
Adriano Violante | General | Information | Report after dispatch meeting 09.30 |
SPB/SFX
FXE
- Fixing session of the sample stage. No controls modification involved. Done by today.
- Shutter controls from the hutch. Some works were supposed to be done by MPS. What is the status?
SQS
- New interlock definitions have to be tested and implemented. Some tests were performed and bugs fixed. New tests are needed and planned for Wednesday. ==> Master loop will be updated until tomorrow. Tests still planned for Wednesday. ==> Test successful. Now SQS has to decide whether to use the interlocks during next runs.
- VAC interlock test will be done during next days after update of the loop.
SCS
- Updated interlock definition will be given to AE by SCS==> Done.
- Electronics and cabling for the laser hutch is coming next. MTeichmann will talk to EET to agree on priority concerning the cables production and pulling. It may be necessary for SCS to pull a few cables as soon as possible (by themselves?). Anyway, cables route will be needed. ==> EET is waiting.
MID
- Loop commissioning priorities being discussed with AE. (as well as checking whether all the important PLCs are there)
- Next Tuesday the cabling shoud be completely done.
HED
OPT Lasers
- in SASE1 the seeder was swapped. This affects the timing. Will be discussed with AE.
- PP laser should also get the train id. Change request to be prepared soon.
XRO
XPD
VAC
- Leak test for HED mono has to be performed
- AE reports they got feedback that also SASE1 vacuum needs to be tested. MD checks.
AE
- AE was asked to update MOV1 MOV2 and EPS loops for SASE3 tunnels. This is due to the implementation of a new B4C to be mounted and controlled. ==> MOV 1 will be updated. Also CAS will be asked to save the motor parameters. NO EPS and MOV 2 loops update necessary for now. ==> SASE3 MOV 1 will be updated today.
ITDM
- DAQ installations for SASE2 and 3 will be physically migrated in the balconies to separate them from SASE1. Will be completed in the next days. Will be finished before DAQ has to be operative.
- DAQ SASE1 running for detectors test.
- MID will also get DAQ working soon for AGIPD test.
DET
CAS
- Data logger schould be working for every component now. ==> More info to come.
AoB
- LIEN fixed the sliding doors in SASE3 experiments. Drag chains have been installed. Only 1 cable has to be ordered and exchanged. Will be done during the next shutdown.
|
597
|
28 Jan 2019, 14:33 |
Adriano Violante | General | Information | Report after dispatch meeting 09.30 |
SPB/SFX
- The vacuum section of the burthrough monitor was vented for some intervention and is now being pumped again.
- CSS component has issues with limit switches implementation. Will be discussed with AE and EET.
- Jungfrau loop can be brough up once AE gets the fuse boxes formt he company.
FXE
SQS
SCS
- Waiting for loops updates
- DSSC can be switched on since no more works on the power lines are foreseen.
MID
- ATT XTD6 being re commisisoned.
- Mono in XTD6 being commissioned.
- Optics hutch commissioning ongoing.
HED
- Loop 2 needed for commissioning. AE checks the status.
- Modules for the attenuator also needed. AE checks the status.
OPT Lasers
XRO
- Encoders for the mirrors in XTD6 are being checked.
- Commissioning of benders in SASE3 planned for 8,9,10. Feb. SQS hutch will be interlocked and shutter opened.
XPD
VAC
- Tunnel access schedule was updated: https://ttfinfo.desy.de/elog/XMLlist?file=/XFELelog/data/doc/Schedule/2018-12-12T08:13:57-02.xml&xsl=/elogbook/xsl/elog.xsl&picture=true
AE
- The timing software needs to be updated. Today at 14:00.
ITDM
DAQ in the tunnels has been updated.
A mail will be circulated with the new proposals for users.
SA1 will be switched to the new storage. Corrdinated with CAS. This will allow the users to access data on the online cluster without first migrating the data to the Maxwell cluster. System will be tested on Wed afternoon and Thu. In this time frame interruption of the storage systems can happen.
EET
CAS
AoB |
593
|
18 Jan 2019, 11:05 |
Adriano Violante | General | Information | Report after dispatch meeting 09.00 |
SPB/SFX
- The interlock definitions in the tunnel were updated. They have to be tested.
FXE
SQS
- Power cut of the primary power line in the rackroom will occur to allow fixing of the emergency power off system (as agreed between TS ans MM last week). Happening today. After completion CAS and AE support is needed to switch the systems back on. ==> Completed. No issues.
- AQS chamber has been removed. The reaction microscope is now being installed.
- New interlock definitions have to be tested and implemented. Some tests were performed and bugs fixed. New tests are needed and planned for Wednesday.
SCS
MID
HED
OPT Lasers
XRO
XPD
VAC
- Mono loop in SASE 3 has to bee updated (22nd). Agreed with involved parties.
- MOV2 Loop SASE2 also needs to be updated. Agreed with involved parties.
AE
- AE was asked to update MOV1 MOV2 and EPS loops for SASE3 tunnels. This is due to the implementation of a new B4C to be mounted and controlled. This task was not included in the shutdown list and therefore has not been planned. The issue needs to be reported in the operation meeting since a reshuffle of priorities and relative decisions are eventually needed.
- CRLs for SPB will be controllable at the end of March/ beg. April as agreed with the instrument people.
EET
ITDM
DET
CAS
- It is pointed out that the CAS policy is not to implement changes in the software on Friday in order to guarantee the smooth operation of components during the week end. This should be also reported in the Operation meeting.
AoB
- 22/23 January Fa. LIEN will fix the sliding doors in the SASE3 hutches.
|
596
|
25 Jan 2019, 10:07 |
Adriano Violante | General | Information | Report after dispatch meeting 09.00 |
SPB/SFX
- Trigger for Jungfrau detector is needed.
- Commissioning of the instrument should start next week
- Loop priorities for the donwstream components have been set with AE.
FXE
SQS
- VAC interlock test will be done during next days after update of the loop.
- Loop 4 has to be updated following some HW changes. Should run by next week since is needed for the preparation of the users run.
- Digitizers crate is being tested by AE and CAS and will be installed/usable by the middle of next week.
- Burst trigger - status and requirements will be discussed with BFernandes after this meeting.
- MPOT test CY/TB Today at 13:30
SCS
MID
HED
- Preparation of Hi res mono has been completed last week
- OPT hutch CRL commissioning ongoing. ATT will follow (needed missing crate will be installed next week)
- Chamber motion for the monochromator has to be checked
OPT Lasers
XRO
- Loops update in thetunnels have been completed. the MOV1 in SASE3 included also some PBLMs ==> XRD should check whether everything is fine afte the update.
XPD
VAC
- Tunnels are ready for beam.
AE
- EXAPOD in SPB can be tested.
- HED need PPU in XTD6. To be re-checked.
- The timing software needs to be updated. BFernandes circulated a mail with proposed date: Next monday at 14:00. In case of different suggestion, please contact Bruno. CAS suggests to keep the proposed date.
ITDM
ET
CAS
- Data logger schould be working for every component now. ==> Meeting later with VAC and Laser group to define the use case and start a new optimization project.
- VAC of HED Opt tests are ongoing (CY) before pumping down.
- For the debug of gauges control is possible that a ZZ access will be requested. (CY)
AoB
- Tunnel access schedule will be updated by HSinn after the Operation meeting with the latest information.
|
15
|
02 Dec 2016, 11:47 |
Frederike Wittmaack | General | Information | Remote access to control network form |
http://tinyurl.com/jskzj2h
|
55
|
28 Feb 2017, 11:38 |
Tobias Haas | General | Information | Reminder: Stable operation and development periods |
One word of clarification:
The discussion last Friday left some people uncertain over how to define stable operation and development periods. Hence I had a discussion with Nerea and Alessandro and agreed on the following:
PLC development: Tuesday - Thursday
Stable operation with Karabo: Friday - Monday
Handover period is Thursday afternoon between AE and CAS
|
261
|
24 May 2017, 09:06 |
Tobias Haas | General | Information | Reminder: SASE1 Readiness Dispatch @ 0930 today |
see you there |
240
|
17 May 2017, 08:52 |
Tobias Haas | General | Information | Reminder S1R Dispatch at 09:30 today in front of MCR (Mockup Control Room) |
|
437
|
08 Jan 2018, 09:50 |
Monica Aresté | General | Information | Reminder Readiness meeting today at 13:00 |
Dear all,
This is a reminder to inform you that Readiness meeting will resume today at 13:00.
Best regards and Happy New Year !!
|
466
|
31 Jan 2018, 22:34 |
ITDM Admin | General | Information | Re: exflgateway migration |
The migration has finished, to avoid temporary problem with ssh you can use
ssh exflgateway -o StrictHostKeyChecking=no
until it will be resolved in the morning ( the usual update of all hosts ssh keys).
Home folder has been changed to /data/<user_name> and it is slightly bigger then before...
Let me know if there is still anything missing.
best, Janusz
ITDM Admin wrote: |
Today late in the evening (~22:00), the exflgateway will be migrated to a new hardware. All users will be logged out before migration and home folders will be copied.
After migration is finished, you may experience ssh warning about ssh host key. For all centrally managed Linux this should be fixed the following morning. For all other, like Windows, or yellow desktops, you need to remove the old key and/or accept a changed one.
Best
Janusz
|
|
457
|
22 Jan 2018, 15:12 |
Bruno Fernandes | General | Information | Re: Status report after dispatch meeting 13:00 |
Hi everyone,
there was some miscommunication between us and DESY: only the Timing firmware and doocs server need to be updated, the RTM was already been replaced. This require update is similar to the one perform two weeks ago (see entry #449).
The time slot for this update is next Wednesday, 23rd January, between 16h and 17h. The update will affect all Timing Devices in SASE1. This operation should not take more than 10 minutes; during this time no timing signals will be generate (clocks/triggers/bunch patterns/etc.). Naturally, problems may occur during this update which will lead to increase down time.
If somebody sees a problem with the current schedule, please contact me.
Adriano Violante wrote: |
General remarks:
- Stable beam only to be expected starting from 1.03. for SASE1 instruments commissioning
- There is no guarantee for parasitic beam delivery to the experiments. If it happens at all it will most probably be during the last week of Feb. This has to be agreed on the fly with the BKR and H.S/ T.T.
SPB/SFX:
- Preparing D.02 for mirrors installation (next week)
- Karabo being updated
Advanced Electronics:
- Trigger delivered by DESY should be back and stable at 10Hz.
- ATM for timing has to be replaced in the balcony rooms. Bruno Fernandes is trying to find a way to reduce the downtime down to 30 minutes. Will be scheduled in the next days.
ITDM:
- 1 line card has to be replaced. Probably happens on Wednesday this week during the DAQ tests.
- Tuesday afternoon the online storage units will me remounted with the same path of the offline ones.
- This week a proposal for the in-house commissioning is going to be circulated.
|
|