92
|
31 Mar 2017, 16:02 |
NEREA JARDON | General | Information | SASE1 EPS | Dear all,
EPS loop is running with the latest
hardware updates. Today, when I was trying |
|
160
|
21 Apr 2017, 14:36 |
Tobias Freyermuth | XTD9 | Information | SASE EPS RACK 1.14 disconnect | We have to disconnect the EPS crate in
RACK 1.14 in order to check the interface
to the MPS. |
|
163
|
21 Apr 2017, 15:30 |
Tobias Freyermuth | XTD9 | Feedback | SASE EPS RACK 1.14 connected |
The
EPS-loop is now complete again. |
|
178
|
26 Apr 2017, 18:34 |
Jan Grünert | XTD9 | Problem | SA1-VAC loop down (only XTD9) and later restarted | Since around 17h30 all XTD9 VAC loop is
in error. It came back in karabo around 17h50.
XTD2 not affected. |
|
347
|
27 Jul 2017, 15:42 |
Eric Boyd | XHEXP | Information | Restricted areas Durring Radiation Measurements of SASE 1, Friday 28.07 | No radiation measurements have taken place
today (27.07) due to insufficent energy of
the machine. We think we can achive the desired |
|
225
|
12 May 2017, 08:21 |
Harald Sinn | General | Information | Restart vacuum loop now | We are in the BRK and corrected the
vacuum interlock condition.
We will restart the SA1 vacuum loop |
|
238
|
16 May 2017, 15:59 |
Andreas Koch | XTD2 | Feedback | Request for imager checks | Since tomorrow there is no beam I want
to use the time for some checks of the imagers
in XTD2. Please, let the motion loop up if |
|
592
|
16 Jan 2019, 10:20 |
Adriano Violante | General | Information | Report after dispatch meeting 09.30 | SPB/SFX
FXE
SQS |
|
594
|
21 Jan 2019, 10:43 |
Adriano Violante | General | Information | Report after dispatch meeting 09.30 | SPB/SFX
FXE
SQS |
|
595
|
23 Jan 2019, 10:47 |
Adriano Violante | General | Information | Report after dispatch meeting 09.30 | SPB/SFX
FXE
Fixing session of the sample |
|
597
|
28 Jan 2019, 14:33 |
Adriano Violante | General | Information | Report after dispatch meeting 09.30 | SPB/SFX
The vacuum section of the
burthrough monitor was vented for some intervention |
|
593
|
18 Jan 2019, 11:05 |
Adriano Violante | General | Information | Report after dispatch meeting 09.00 | SPB/SFX
The interlock definitions
in the tunnel were updated. They have to |
|
596
|
25 Jan 2019, 10:07 |
Adriano Violante | General | Information | Report after dispatch meeting 09.00 | SPB/SFX
Trigger for Jungfrau detector
is needed.
Commissioning |
|
15
|
02 Dec 2016, 11:47 |
Frederike Wittmaack | General | Information | Remote access to control network form | http://tinyurl.com/jskzj2h
|
|
55
|
28 Feb 2017, 11:38 |
Tobias Haas | General | Information | Reminder: Stable operation and development periods | One word of clarification:
The discussion last Friday left some
people uncertain over how to define stable |
|
261
|
24 May 2017, 09:06 |
Tobias Haas | General | Information | Reminder: SASE1 Readiness Dispatch @ 0930 today | see you there |
|
240
|
17 May 2017, 08:52 |
Tobias Haas | General | Information | Reminder S1R Dispatch at 09:30 today in front of MCR (Mockup Control Room) | |
|
437
|
08 Jan 2018, 09:50 |
Monica Aresté | General | Information | Reminder Readiness meeting today at 13:00 | Dear all,
This is a reminder to inform you
that Readiness meeting will resume today |
|
466
|
31 Jan 2018, 22:34 |
ITDM Admin | General | Information | Re: exflgateway migration | The migration has finished, to avoid temporary
problem with ssh you can use
ssh exflgateway -o StrictHostKeyChecking=no |
|
457
|
22 Jan 2018, 15:12 |
Bruno Fernandes | General | Information | Re: Status report after dispatch meeting 13:00 | Hi everyone,
there was some miscommunication
between us and DESY: only the Timing firmware |
|