Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 18 of 30  Not logged in ELOG logo
ID Date Author Location Severity Subjectdown
  132   11 Apr 2017, 13:48 Alessandro SilenziGeneralInformationScript to install the latest karabo

Please find in attachment the dowload bash script for the latest Karabo.

if your system has a "karabo" directory, this script will not overwrite it, but the update will fail.
In this case, remove or rename the karabo directory.

To use it:
1. download the script in a directory of your choice.

2. open a terminal and execute it with
   $ bash PATH_TO/download.sh

Where PATH_TO is the path where the download script was saved.

Attachment 1: download.sh
#!/bin/bash

if [ -z ${outfilename} ]
then
    outfilename=.karabo.sh
fi
echo $outfilename
git clone https://xfel.redmine:K9Sss5CmWtQ_nbx3gyt2@git.xfel.eu/gitlab/Karabo/commissioning-guidelines .temp-commissioning --depth=1
cp -f .temp-commissioning/project_generation/install.sh .install.sh
rm -fr .temp-commissioning
. .install.sh
rm ${outfilename}
rm .install.sh
  298   22 Jun 2017, 15:15 Tobias HaasXTD2InformationSchedule for first beam SASE1 hutches

It was just decided to put a very low intensity beam into the SASE1 hutches starting tomorrow morning at 8 AM. Both instruments declared that they are ready to accept it. Due to the very low intensity no special measures need to be taken outside the hutches. SRP and D3 shall be in the experiment hall. Harald Sinn shall coordinate beam activities from the BKR. Please note that the TC and S1R meetings take place as announced.

  87   24 Mar 2017, 13:21 Tobias HaasGeneralInformationSchedule for PLC and Karabo Week 13

 

Day Motion Loop Vacuum Loop EPS Loop SPB Tunnel Loop Karabo
Monday Loop up.  Loop up.  Loop up  Loop inactive Version update by CAS 12:00 - 18:00
Tuesday Loop up.  Loop up.  Loop up  Loop inactive Running and no change
Wednesday Loop up.  Loop up  Loop up  AE brings up loop Running and no change
Thursday Loop up Loop up  Loop up  AE brings up loop Running and no change
Friday Loop up  Loop up  Loop up  Loop up Running and no change

 

 
  93   03 Apr 2017, 10:03 Tobias HaasGeneralInformationSchedule for PLC and Karabo 3 April after 09:30 Meeting

Tunnels closed today and tomorrow

- AE updates Vacuum and motion loop in the morning

- V. Bondar, J. Eidam and H. Sinn test vacuum in the afternoon (emphasis on understanding interlock conditions)

- A. Koch tests XTD2 imagers in the afternoon

See also  https://in.xfel.eu/redmine/projects/sase1/agile_board

 

Problems solved on Friday last week:

- Arms 2 & 4 of SRA are now moving. Apparently spindles had mechanical resistance that resulted in error condition. After moving a few times, this appears to be gone

- One of the problematic ion pumps had the serial line disabled. However, other lines 

 

 

 

  94   04 Apr 2017, 11:21 Tobias HaasGeneralInformationSchedule after 09:30 Meeting

 Tunnel closed today. Might re-open around 14:00

Note that that we re-convene briefly at 17:00 today in MCR (Mock-up Control Room)

Vacuum Loop:

Status:

  • Large number of ion pumps not responding properly (2 in XTD2, 63 in XTD9). There is the suspicion that the parameters on some ion pump controllers might be set incorrectly, such as baud rate or the bus address. The generated error code indicates a bad address.
  • Test in the lab requires Ion pump controller and PCL. No setup currently readily available. Check in the tunnel required. Could take place between 1200 and 1300 in XTD2 with a ZZ. (Update: B. Racky thinks she will be done around 1400 and would prefer access after this time)
  • Preparations needed to include XGM 

EPS Loop:

Status:

  • Temperature sensors return null value. Suspected firmware bug has been fixed and EPS loop updated by TF
  • EPS to MPS interface requires testing. Should be done tomorrow

Motion Loop:

Status:

  • Fixes have been applied to the MC2 lib. Tested for TECHNOSOFT driver. Should now work also for PBLMs . Tests do be done starting Wednesday

Imagers

Status:

  • Camera driver for SR imager not working
  • Camera driver for FEL driver working for imager in XTD2 but not for XTD9

Tasks for today:

  • E. Eidam, V. Bondor, , J. Tolkiehn H. Sinn go through all ion pumps in the Silenzi list
  • E. Eidam, T. Freyermuth check pump controller settings in the tunnel
  • A. Koch and W. Ehsan work on Photonics Camera driver for FEL imager

 

Tasks for tomorrow:

  • M. Planas, T. Maltezopoulos, N. Jardon, J. Eidam test XGM vacuum integration in XTD2 (not XTD9)
  • N. Gerasimova, N. Gerasimova and 1 firmware expert test PBLMs in the tunnel
  • T. Freyermuth tests EPS -> MPS interface

 

Other topics

  • The two signals from MCP to EPS shall be called MCP-upstream and MCP-downstream

 

 

 

 

 

 

 

  123   10 Apr 2017, 10:47 Tobias HaasGeneralInformationSchedule after 09:30 Meeting

Tunnel Open.

Mirrors:

Status:

  • Both mirrors M1 & M2 installed
  • Vacuum being closed in M2 today should be ready for ion pumps tomorrow
  • Surveying work going on (see email by M. Schlösser below)

Vacuum Loop:

Status:

  • Needs reconfig for XGM in XTD9
  • Interlock tests on XGM in XTD2 should go on. 
  • 2 Turbopumps still have a communication problem (J. Tolkiehn is working on this)
  • 6 Ion pumps in XTD9 still have communication problems (list was given by AS to JE)
  • Systematic testing according to the list by J. Eidam with V. Bondar starting this afternoon

EPS Loop:

Status:

  • One terminal needs to be exchanged for FEL Imager 
  • Description of EPS interlock still missing. It is planned to start with just one imager in for first beam commissioning
  • One fiber connection from Balcony room to DESY still to be done by DESY. AFter this testing of communication should start

Motion Loop:

Status:

  • Quick fix for motors not stopping was deployed on Friday. Now TF is working on a better fix to be deployed this evening

Imagers

Status:

  • EPS switch on FEL imager should be checked after exchange of terminal
  • Photonics camera driver still not working but not critical for tunnel closure
  • Work should now concentrate on SR imager

Karabo:

Status:

  • New version with TCP fix needs to be deployed. This should also be done to the local software run by users.

 

Tasks for today:

 

Note: Loop reconfiguration and updates of Karabo to be done in the morning. Testing can resume after lunch. Status updates should please be recorded in the log

  • Reconfigure vacuum and motion loops (updates for XGM interlock, motors not stopping)
  • Replace broken terminal in EPS loop for FEL imager 
  • Continue test XGM interlocks (N. Jardon, M. Planas, T. Matsopoulos)
  • Go through systematic test of the vacuum components (J. Eidam, V. Bondar)
  • Continue tests with PBLM in the tunnels (M. Jidda)
  • Test motion system of the imagers in the tunnels (A. Koch and W. Ehsan)
  • Monitor stability and responsiveness of GUI Server and Log Servers (A. Silenzi)
  • Set up monitoring of temperatures and pressures overnight (A. Silenzi)
  • Test communication between XFEL and DESY MPS once fiber connection from Balcony rooms to MPS is available (B. Fernandes)

Tasks for tomorrow:

  • Put XGM into the vacuum interlock
  • Continues testing of all interlock conditions for the vacuum

Other topics

  • Surveying is going on for mirror chambers M1 and M2 in XTD2
  • We need a well defined startup configuration of PLC, Karabo, Parameters, List of devices (A. Silenzi)

Email by M. Schlösser re alignment

Hi Tobias, hi Markus, Hi Winni,

Tobias, we discussed briefly the schedule for the T9 and T10 beamlines for the next few days, when we met in the tunnel yesterday.

From what i understand it is impossible to finish T10 until April 11th from the alignment and vacuum side. And probably more important, this also holds true for T9. There is at least one major problem with the alignment of the mirror chambers of T9 in XTD2, which will need some additional days to solve.
From my understanding at least the T9 beamline should be closed and aligned before putting SASE1 in operation. While it will of course be possible to send electrons down to the XSDU2 dump, it will not be possible to send photons to the experimental hall with the current state of the beamline.

Since it is not possible to work in XTD10 while the SASE1 electron beamline is in operation, i would propose to also finish this beamline before SASE1 electron startup. Since there is major work to do in XTD10 to finish the beamline, there is no hope to  do the remaining work during maintenance days. Finishing the beamline would require a major shutdown of the SASE1 branch later.

Since there will be no alternative to send the beam to (e.g. SASE2) for the next year (?), it does not make sense to stop work in XTD10 now, just to continue later then, without any overall benefit for the machine.

Of course i don't have a complete overview of all the machine schedule, but from my point of view it would make more sense to finish work in the northern branch, at least to align all components and to close the vacuum system, even if that means some more weeks before the SASE1 startup.

cu
Markus

  103   05 Apr 2017, 10:15 Tobias HaasGeneralInformationSchedule after 0930 Meeting

Tunnel Open.

Vacuum Loop:

Status:

  • Communication problem with Ion pump controllers is fixed after adjusting controller settings
  • Loop is now down to allow inclusion of XGM

EPS Loop:

Status:

  • Temperature sensors return reasonable values after EPS loop fix
  • EPS to MPS interface is working but fiber to central desy interface still lacking

Motion Loop:

Status:

  • Should be up for testing PBLMs and Imagers

Imagers

Status:

  • Test of FEL imager ok, but hampered by occasional slow response of the system
  • SR Imager needs work on the driver

Tasks for today:

  • Include XGM in Vacuum loop (N. Jardon, M. Planas, T. Matsopoulos, V. Bondar)
  • Test updated MC2 lib with PBLM in the tunnels (N. Gerasimova, M. Jidda)
  • Work on camera driver for SR imager (A. Koch and W. Ehsan)
  • Test motion system of the imagers in the tunnels (A. Koch and W. Ehsan)
  • Monitor stability and responsiveness of GUI Server and Log Servers
  • Set up monitoring of temperatures and pressures overnight
  • Push DESY to get fiber connection to MPS (P. Gessler)

Tasks for tomorrow:

  • Terminals need to be added and firmware adjustments made in motion loop (take loop down as early as possible for one hour)
  • Test EPS inputs to MPS system with DESY people
  • Power down crate 1.15 for grounding. Could take longer than one day

Other topics

  • N. Jardon needs complete info of motor names in rack 1.18
  22   24 Jan 2017, 08:17 Tobias HaasXTD2InformationSTATUS UPDATE: XTD2 Differential Pumping Modules running under interlock control

 Post on behalf of Raul Villanueva:

As we just finished the exhaustive testing and final adjustments of local
test and the interlock program for each of the turbopumps at each
Differential Pumping Sections in XTD2 Tunnel, we are happy to announce
that the system has been released and is up and running smoothly and under
control.  That means that the isolation gate valves in front of each
turbopump is open and therefore the latter is pumping already the beamline
as expected during the upcoming operation phase of the facility. That also
means that WP74, after having already received the wiring documentation
from the Vacuum Group can proceed with the same protocol to keep the whole
gas section in XTD2 in a consistent fail-safe status.

With this positive news, we wish you to have a nice evening,

Regards,

Raúl, Tobias and Nerea,

 

  32   02 Feb 2017, 14:29 Richard BeanXTD9InformationSPB/SFX updates to component table

Table updated with status of SPB/SFX devices at end of XTD9 in preparation for SASE1 readiness meeting on 03.02.17

Attachment 1: Components-XTD2-9.xlsx
  512   17 Apr 2018, 14:23 Torsten SchoenXHEXPInformationSPB emergency power off tests

Dear all,

 the emergency power off test has been successfully performed in SPB.

Nobody can instantly cut the power to non hazardous racks (see racklist.xlsx managed by Ulf Brueggmann) by pushing the emergency off button anymore. The outlets in the experiment hutch do not go off. This is due to some missing cables. These will be installed in the next weeks and a new test will be planned for next shutdown.

Furthermore three racks for D.02 (SPB optics) and two racks for D.13 (SPB laser) cannot be powered off anymore by pushing the emergency off in D.09. The missing two emergency power off switching devices will be mounted in UV-XHEXP1-01-13-AV in the next shutdown. Until then the power to those five racks (D03-UH1 - D03-UH3, D13-UH1, D13-UH2) cannot be cut by emergency off buttons in D.02 or D.13.

  345   26 Jul 2017, 14:10 Bernard BaranasicXHEXPInformationSPB - Loop 5 is back online

SPB Loop 5 is back online:

- but without crate BKF00095-SPB_IRU_CHL (there is missmatch of hardware and documentation (investigation is ongoin)),

- pumps: PUMP_TURBO4, PUMP_TURBO5, PUMP_TURBO8, PUMP_ROOT_1, PUMP_ROOT_2 ,PUMP_ROOT_3 and IRU_VAC/PUMP_ROOT_1  are without serial connection

Interlock is inlcuded and ready for testing.

 

Best Regards,

Bernard

  276   03 Jun 2017, 22:39 Alessandro SilenziGeneralProblemSOLVED BROKER Problem

A pile up in the BrokerQueue was detected by CAS monitoring system and

a response action from the On-Call personnel was triggered.

Regrettably, the following device servers have been shutdown and will be re-instantiated.

- Dataloggers
- alarm server
- camera servers
- Motion Loop and Vacuum Loop beckhoff servers

Sorry for the inconvenience

  554   28 Aug 2018, 11:19 Alessandro SilenziXTD10InformationSASE3 loops will restarted at 11:30

This announcement is to notify you that the intervention planned to configure the interlocks as read-only will be carried out at 11:30.

A following message will notify of the end of the intervention

Alessandro

  516   25 Apr 2018, 11:42 Marijan StuparXTD10InformationSASE3 MOV1 loop update

I will update the SASE3 MOV1 loop in 30 minutes. Please let me know if you would like me to postpone the update.

Best regards,

Marijan

  506   13 Apr 2018, 09:05 Torsten SchoenXHEXPInformationSASE3 E.21 and E.22 electrical power distribution

changes according to the racklist on the electrical power distribution cabinets for rackrooms E.21 and E.22 are done. Power supply should be stable now. Please note that there will be emergency power off tests prior to the final acceptance test of SASE3 electrical installations around mid of May. You will be notified about the exact time and date.

  393   29 Sep 2017, 11:03 Monica ArestéGeneralInformationSASE1/SASE3 Readiness meeting on Monday cancelled

The SASE1/SASE3 Readiness meeting next Monday is cancelled we will meet again on Wednesday the 3rd of October.

  394   29 Sep 2017, 11:09 Monica ArestéGeneralInformationSASE1/SASE3 Readiness meeting on Monday cancelled

Correction: We will meet again on Wednesday the 4th of October.

Monica Aresté wrote:

The SASE1/SASE3 Readiness meeting next Monday is cancelled we will meet again on Wednesday the 3rd of October.

 

  459   24 Jan 2018, 16:15 Bruno FernandesGeneralInformationSASE1 Timing System Update

Dear all,

the update to the SASE1 Timing system has been perform with no problems. The Timing board is now running firmware 1.24.0 and the doocs server was updated to version 7.8. I also updated the MCH firmware to version 2.19
 

  430   06 Dec 2017, 17:17 NEREA JARDONGeneralInformationSASE1 MOV

The Motion loop in SASE1 is totally operated again.

  258   21 May 2017, 17:10 Dennis GoeriesXTD2ProblemSASE1 Imager FR

Dear all,

we are experiencing constantly crashes with the photonic science camera in the SA1 imager FR. We found now out

- If the pixel format is set to Mono16 the camera will most likely crash, go in error.

- Before instantiation the camera may show Mono16. During connection Karabo but gets a fresh update and the field in the scene switches to Mono8.

 

Please don't apply Mono16 again.

Best wishes, Dennis