SASE1 Status and SASE3 Readiness Technical integration and coordination
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 17 of 30  Not logged in ELOG logo
Entry   WP74 SASE1/3 readiness status and outlook, posted by Jan Grünert on 14 Jul 2017, 09:31 
Entry   TAS updated, posted by Gerd Wellenreuther on 14 Jul 2017, 10:50 
Entry   Status and plans after SASE1/3 Readiness Meeting, posted by Tobias Haas on 14 Jul 2017, 13:17 
Entry   Information AE OCD July 14--17 (till Monday 8:00), posted by Nicola Coppola on 14 Jul 2017, 18:46 
Entry   Tunnel access schedule updated, posted by Gerd Wellenreuther on 18 Jul 2017, 10:57 
Entry   Status and Schedule after 09:30 meeting, posted by Tobias Haas on 19 Jul 2017, 10:11 
Entry   Tunnel access schedule updated, posted by Gerd Wellenreuther on 20 Jul 2017, 15:19 
Entry   Tunnel access schedule updated, posted by Gerd Wellenreuther on 24 Jul 2017, 10:03 
Entry   Status and plans after SASE 1/3 Readiness Meeting, posted by Frederike Wittmaack on 24 Jul 2017, 10:07 
Entry   Status after 9.30 Meeting, posted by Adriano Violante on 24 Jul 2017, 10:38 
Entry   Tunnel access schedule updated, posted by Gerd Wellenreuther on 25 Jul 2017, 13:26 
Entry   Status after 9.30 Meeting, posted by Adriano Violante on 26 Jul 2017, 10:35 
Entry   SPB - Loop 5 is back online, posted by Bernard Baranasic on 26 Jul 2017, 14:10 
Entry   Fast valves in XTD9, posted by Martin Dommach on 26 Jul 2017, 18:04 
Entry   Restricted areas Durring Radiation Measurements of SASE 1, Friday 28.07, posted by Eric Boyd on 27 Jul 2017, 15:42 Restricted_areas_for_measurments.pptx
Entry   No Restricted Areas for Radiation Commissioning, posted by Eric Boyd on 28 Jul 2017, 11:10 
Entry   Status and plans after SASE 1/3 Readiness Meeting, posted by Frederike Wittmaack on 28 Jul 2017, 11:50 
Entry   Tunnel access schedule updated, posted by Gerd Wellenreuther on 30 Jul 2017, 23:04 
Entry   Status after 9.30 dispatch Meeting, posted by Adriano Violante on 31 Jul 2017, 11:58 
Entry   Status after 9:30 dispatch Meeting, posted by Monica Aresté on 02 Aug 2017, 10:17 