294
|
19 Jun 2017, 10:17 |
Monica Aresté | General | Information | Status and plans after SASE1 Readiness Meeting | XTDs:
- There are no major issues, commissioning works smoothly this weekend.
FXE:
- Radiation safety measures done last Wednesday.
- Tests with CRL are on going but there are some problems with motors since are moving only in one direction. CAS is working on that issue.
- Loop1 need an update, support from AE necessary.
- Interlock conditions meeting to be held today, to carry out the test end this week.
SPB:
- Test with loop2 continue.
- Cables for Loop3 will be repaired today and tomorrow. Firmware already available.
- Export for loop 7 is done, AE is working to generate the firmware. EET has two persons working in the exports for loops 4 and 12.
- Interlock conditions already defined by SPB sometime ago.
Diagnostics:
- External trigger for Basler cameras still not always working, CAS keep working on that.
Electronics:
- Today and tomorrow working for the AGIPD, required an additional interlock part for the Vacuum.
- First priority is is to have the Vacuum system for FXE and SPB operational at the end of June. Next two weeks AE will be mainly focus in the loops that are still missing (SPB 4, 5, 7,12) or still not running (SPB 2, 3)
Software:
- Karabo version installed in a different domain, CAS is still testing ths version to ensure a smooth transition from one version to other.
|
352
|
02 Aug 2017, 10:17 |
Monica Aresté | General | Information | Status after 9:30 dispatch Meeting | General
-
This Thursday the radiation test in D.05 (FXE) will be performed (from approximately 0900 to 1500), access to all areas adjacent to the hutch is only allowed by those that are assisting with the measurements.
-
Meeting on Friday is cancelled. We will meet again on Monday 7-08-2017.
FXE
- Gotthard detectors to be tested in Karabo. On going.
- Finished commissioning of OGT2_CRL and OGT1_ATT. The laser to be used in September installed and connected to electronics.
SPB
-
Problem with Smaract motors has been identified. Loop 12 updated, full test still on going.
-
Cameras trigger for the sample environment is now working. Software issues, CAS is addressing that.
-
Vacuum interlock for Loop 5 (AGIPD) is being implemented. Interlock definitions for AGIPD under discussion with AE to continue work on this loop.
-
Working in the commissioning of Loop13.
Tunnels
-
In case of fake triggering of the fast valves, there is now a procedure to open them again remotely. Please check the related entry posted by M. Dommach.
-
Two issues with photonic cameras already solved by CAS.
-
Images are displayed later, this issue will be discussed off-line with CAS.
AE
-
FXE Interlock definitions have been changed and this reflects in the update of loop 1 and 2. Done.
-
Working on Alio Stages integration for Mono in the tunnel. Developing.
-
SPB Loop 12 – Smaract motors and ELMO controllers implementation done.
-
SPB Loop 5 thre are some issues with Julabo Chiller, AE contacted the manufacturer for information.
-
SPB Loop 13 - Phase 2 cables for some modules are at different positions compared to eplans. Change request submitted to swap module postions.
-
Cables for interface to Person Interlock laid. Connections to the MPS system to be done this week.
-
Loop 8 should be the next, EET to clarify if the export is done and provide to AE.
DET
-
LPD – Synchronization is still showing problems, this is delaying the tests.
-
AGIPD – Detector being tested in Hera south. KWrona started the tests of DAQ, some minor issues arised but in general it works.
CAS
-
2.1.13 Karabo version update is being agreed with the interested parties. Implementation will be next Tuesday 8.08.2017 in the afernoon. It takes approx. 3 hrs.
-
CAS will send around a list with the tasks foreseen to be solved during the next weeks.
|
356
|
07 Aug 2017, 12:45 |
Monica Aresté | General | Information | Status after 9:30 disptach meeting | General
SPB
-
Problem with Smaract motors has been identified. Loop 12 updated and working fine.
-
SPB working to focus the CRL, it works but beam is not stable.
-
Vacuum interlock for Loop 5 (AGIPD) is being implemented. Interlock definitions for AGIPD under discussion with AE, this is still on going.
-
Export for Loop13 updated due to a reorganizattion of the modules into the rack. Firmware will follow.
-
Export for Loop 8 still missing.
Tunnels
-
Images are displayed later, this issue was discussed off-line with CAS. This issue has been fixed for one camera and it works, now will be deployed for the rest. Will be necessary 15min. of downtime to deploy, CAS to coordinate with Control room.
AE
-
SPB Loop 5 thre are some issues with Julabo Chiller, AE contacted the manufacturer for information, still working on this.
-
SPB Loop 13 - Phase 2 cables for some modules are at different positions compared to eplans. Change request submitted to swap module positions.
-
Loop 8 should be the next, EET to clarify if the export is done and provide to AE.
-
AE ask to define priorities for next week since they will have to work in SASE3 tunnels but threre are still many issues form SASE1 on going (Firmware, AGIPD..).
CAS
|
372
|
30 Aug 2017, 09:53 |
Monica Aresté | General | Information | Status and plans after SASE1/3 Readiness Meeting | Electronics
- Currently work continues on the SPB SmarACT stages, this issue progress slowly since right now it is not possible to reproduce the error.
- SPB loops 1/2/3/4/12 already updated, they will continue with the update of loops 5/7/13 today.
- Update on FXE loops will be the next.
- It is suggested to update also the loops in XTD9.
- AE report a request from J. Grunert to work in the HYREX. So far first priority is to work in the Experiments, this issue will be on hold.
CAS
- CAS has been working in the last days to solve the problems with the DAQ integration. Main showstopper now is the update of the Beckhoff loops.
- Still working to fix some minor issues for SPB.
Tunnels
- There is a problem in the HYREX photonic camera, CAS has been investigating but is not a KARABO issue.
|
390
|
25 Sep 2017, 12:58 |
Monica Aresté | General | Information | Status and plans after SASE1/SASE3 Readiness meeting | General
- Beam was lost due to incident with electron beam hitting & damaging components downstream of the northern dump.
- Goal is to stablish proper conditions for the beam again, last week seemed much better. On Wednesday this week it is expected to have stable beam conditions and sufficient pulse energy for next experiments.
SASE1 Instruments
- SPB :
- Several persistant problems with Karabo that affect DAQ and Detector. Detector failed on Saturday triggered by the Karabo issues, it took long to recover since a complete power cycle of the Detector was required (30 minutes).
- CAS is working to fix the problems.
Tunnels
- SASE1:
- Beam shutter closed during FXE shift, the reasons are not clear. M. Dommach and L. Samoylova to investigate to solve this issue.
Electronics
- MPS Interlock for SPB tested but not switched on. Agreed to switch on this Tuesday.
ITDM
- ITDM report that FXE experienced some problems with the DAQ but they did not inform ITDM . The Experiment team decided to continue and try to figure out by themselves. ITDM and FXE to discuss how to improve the communication for next time.
- Next experiments require Gotthard & LPD in parallel operation ==> to merge Gotthard & LPD to same run control ITDM needs some time to test. Agreed to carry out the tests Tuesday and Wednesday this week, also fine for SPB.
|
391
|
27 Sep 2017, 10:11 |
Monica Aresté | General | Information | Status and plans after SASE1/SASE3 Readiness meeting | General
- T. Tschentscher inform about Management Board priorities for the October shut down:
- Management Board Priority 1 after the Oct shutdown will be the characterization for SASE1 performance. Any still necessary development for this (MCP, HIrex operation; two-way functional DOOCS-Karabo interface and data exchange; etc.) should get highest priority during the shutdown period. It would be good to achieve substantial progress with the DOOCS-Karabo interface before the MAC meeting to avoid general bashing of our controls. The instruments will provide a detailed list to permit support groups (ITDM, CAS, AE) to plan resources.
- Priority 2: SASE3 completion. It is expected that the machine will anyway be able to reach lasing at SASE3, but this has lower priority at present.
SASE1 Instruments
- SPB :
- No major issues to report
- FXE:
- In the next days FXE will work in the commissioning of Gothard & LPD in parallel operation to be ready to test with beam on Saturday.
Electronics
- MPS Interlock for SPB already switched on.
- No further issues to report.
ITDM
- Users have no access to on-line DAQ. They can use off-line cluster, the transfer is 5 min. after the end of the run.
- Out of the shift scientist should work with off-line cluster.
Safety
- There is a new procedure for tunnel access. Accelerator areas will have to be measured by Safety group before tunnel access release.
|
393
|
29 Sep 2017, 11:03 |
Monica Aresté | General | Information | SASE1/SASE3 Readiness meeting on Monday cancelled | The SASE1/SASE3 Readiness meeting next Monday is cancelled we will meet again on Wednesday the 3rd of October. |
394
|
29 Sep 2017, 11:09 |
Monica Aresté | General | Information | SASE1/SASE3 Readiness meeting on Monday cancelled | Correction: We will meet again on Wednesday the 4th of October.
Monica Aresté wrote: |
The SASE1/SASE3 Readiness meeting next Monday is cancelled we will meet again on Wednesday the 3rd of October.
|
|
397
|
04 Oct 2017, 12:10 |
Monica Aresté | General | Information | Status and plans after Readiness Meeting | General:
Reminder to all the groups to provide the shutdown task list today afternoon to PSPO. Find template attached.
SPB:
- In general was a succesful weekend. On Sunday there were some problems with control and DAQ already reported to CAS.
- To check if there were additional problems on Monday and report to CAS if necessary.
- To provide the shutdown task list to PSPO.
FXE :
- Was not present, so nothing was reported.
Tunnels:
- Nothing particular.
- List with the shutdown tasks to be provided to PSPO.
Laser:
- Motors were not working, this issue was partially solved in a couple of motors. Detected that the problem was a configuration issue in the PLC. WP-78 will test the solution in other motors of the same kind.
- Laser was running during thre weekend, data will be reviewed today to analyse laser behaviour.
Detectors:
- To investigate a problem with AGIPD, this will require the support from CAS.
Electronics
- Preparing for Oct. shutdown.
ITDM
- DAQ problems on Monday and Tuesday due to detector configuration, still working to find out the causes of the problem.
Software
- Working in the problems reported during the weekend.
|
Attachment 1: Shut_down_task_list.xlsx
|
437
|
08 Jan 2018, 09:50 |
Monica Aresté | General | Information | Reminder Readiness meeting today at 13:00 | Dear all,
This is a reminder to inform you that Readiness meeting will resume today at 13:00.
Best regards and Happy New Year !!
|
438
|
08 Jan 2018, 13:47 |
Monica Aresté | General | Information | Status and plans after Readiness Meeting | PSPO:
- G. Wellenreuther inform that DESY is commissioning a new gun in the injector that could take longer than expected. Harald Sinn is in a meeting today to disccuss this issue, any change in the scheduled will be reported.
SPB:
- Lost motor positions in the tunnel, CRL in defined state. Good state in general no major problems expected.
- Detector was clabled again.
- Loop updates still pending, SPB request to have loops ready during this week.
FXE: No one attended
Vacuum:
- SASE1:
- Some works in CRL for XTD1.
- Working in FXE grating chamber, necessary to update Vacuum loop.
- SASE3:
- M1 and M2 mirrors were installed before X-mas. Mirrors installation in K-mono to be finished next week.
- Created new loop this affects Vacuum loop, update necessary.
- XGM loop need to be updated.
- Motion loop 1 is working, some works in MCP motors on going.
Diagnostics:
- Technical commissioning of MCP on going together with the Russian collegues.
- MCP SASE2 will be transported to XTD6 on Wednesday afternoon.
AE:
- Working to implement redundancy into FXE loops.
- To agree a date with FXE to work in the grating chamber at the end of XTD10.
- Motion loop for SASE1 will be interrupted this afternoon at 14:00 to add some terminals for mirror 2.
Software:
- Deployment of Karabo 2.2.0 will start this Wednesday in FXE.
- Next dates for Karabo deployment are: 15th January for the Tunnels, 22nd January for SPB.
TS:
- Torsten Schoen inform that it is necessary to carry out an 'Emergency off button' test during the Shutdown.
- SPB agreed to perfom the test the 22nd January in the morning.
- For FXE the proposal is to perfom the test the 17th January, to be confirmed with AE and FXE.
|
441
|
10 Jan 2018, 13:22 |
Monica Aresté | General | Information | Status and plans after Readiness meeting | PSPO:
- G.Wellenreuther inform that MKK is planning to test the Umschaltautomatik, this will affect XHE1, XHE3, XHPSC, XHEXP, XHVAC. Oleg Engelmann will send a mail with detailed information.
SPB:
- AGIPD is fully occupied again and restarted this morning as scheduled. Everything works well so far and it is expected to finish the test on time. Further test with new Microcontroller are scheduled for next week.
- Most of the loops that required modifications are updated or on going.
- Module BKF00128 will be modified this week, update of Loop 5 will folllow.
- Loop 12 is ready to be deployed, to confirm if modifications in the modules are finished and reorganization on rack UH2.12 is ready.
- It is necessary to correct an error in module BKF00220, AE will agree with SPB when this will be possible.
FXE:
- New Vacuum device in operation.
- Karabo 2.2.0 being deploy today for FXE.
AE:
- Replace one Micro-TC in SASE3, a cooling unit is failing and one module will be replaced by a new one today. This is providing timing for XGM and K-mono. AE will inform by the logbook before to start the replacement.
|
480
|
26 Feb 2018, 12:09 |
Monica Aresté | General | Information | Status report after dispatch meeting 26.02 | SPB:
- Ion pumps running in the Mirror chamber.
- Starting test with mirrors together with CAS this week.
- In general everything in good position to receive beam.
- Primary limits for coupled motion not included in E-plan, safety switches are implemented but SPB prefers to have the primary limits included. This will suppose a hardware modification.
AE:
- SASE3: train IDs in loop2 are working, the problem was fixed last Friday.
ITDM:
- Measurements for commissioning continues.
CAS:
- H.Santos inform that CAS has not resources to run tasks for SASE2, this might affect the date for first lasing in SASE2. Priorities are SASE1 operation and SASE3 commissioning.
- G. Wellenreuther will bring this topic to the PSO meeting.
FXE/VAC/Detector/XPD: nobody attended
|
Draft
|
25 Sep 2017, 10:25 |
Monica Aresté | General | Information | Status and plans after SASE1/SASE3 Readiness Meeting | General
To stablish proper conditions for the beam as it was before. On Wednesday to have the mirrors in the correct configuration and machine back to the old conditions at the end of the week.
SASE 1 Instruments
- ​SPB (M. Messerschmidts):
- Reported several persistant problems with Karabo that affectd the DAQ and Detector. On Saturday detector falled over and took long time to recover. CAS wokring to fix this issue.
- FXE:
Tunnels (M. Dommach):
- SASE1:
- Beam shutters closed during FXE shift. It is not clear the reasons why this happened, to investigate.
Electronics (P. Gessler)
- MPS Interlock tested but not swichted on. SPB agreed to switch on the MPS tomorrow.
ITDM (K. Wrona)
- FXE was runnig experiments with problems in DAQ, the experiment this was not reported to ITDM
- Next experiments require Gotthard & LPD in parallel operation ==> to merge Gotthard & LPD to same run control ITDM needs some time to test, agreed to perform these tests Tuesday and Wednesday this week.
Software
- FXE:
- Still daily meetings, prepare LPD & Gotthard
- Working on GreatEyes, too
- SPB
- Configure slow-data cameras
- Laser project is running in CAS
- SASE3:
- C. Youngman is the CAS-responsible, should collect requirements to compile master equipment list for SASE3 ==> to be compared against MEL SASE1 to identify additional work required.
- SASE1:
- Loops & Karabo will be updated together.
|
51
|
24 Feb 2017, 15:14 |
Martin Dommach | XTD9 | Information | work on FXE distribution mirror chamber | Dear all,
on Monday, 27th in the morning we will start with preparation work for the mirror installation in XTD9.
The mirror chamber (VS10130) will be vented and opened. This will affect:
V10270G and V10280G: they will be closed and disconnected
P10410I and P10420I: C10902I will be switched to "local" mode and the HV of the pumps will be switched off.
The work will take at least until Friday, March 3rd.
|
52
|
24 Feb 2017, 15:15 |
Martin Dommach | XTD9 | Information | work on FXE distribution mirror chamber | Dear all,
on Monday, 27th in the morning we will start with preparation work for the mirror installation in XTD9.
The mirror chamber (VS10130) will be vented and opened. This will affect:
V10270G and V10280G: they will be closed and disconnected
P10410I and P10420I: C10902I will be switched to "local" mode and the HV of the pumps will be switched off.
The work will take at least until Friday, March 3rd.
|
334
|
14 Jul 2017, 12:44 |
Martin Dommach | XTD9 | Problem | Fast Valves in XTD9 | Dear all,
the fast valves in XTD9 were causing some trouble. From time to time they collect some electrical noise what triggers the valve. The pressure reading on the valve controller then shows oscillations of up to 10^-5 mbar, while the pressure around the fast valve gauges in the beamline is in the 10^-9 mbar range.
To operate the beamline in the meantime I have opened and disabled both fast valves.
This needs further investigation on the service day next wednesday.
Best regards,
Martin |
346
|
26 Jul 2017, 18:04 |
Martin Dommach | XTD9 | Information | Fast valves in XTD9 | Dear all,
the problem with the fast valves XTD9 tripping randomly is still not fully understood but we exchanged the controllers for both valves and they now seem to be stable. The valves are set back to active mode again with 1*10^-6 mbar trigger level while vacuum pressure at the sensors is around 1*10^-8 mbar.
In case one of the valves closes again in the next time you can do the following:
1. check the ion pump pressure in the beamline to make sure that it’s not a real event (they should be in 10^-8 mbar range or better)
2. If it’s not a real vacuum inrush you can open the valve by pressing “Open" button followed by the “Reset” button (SPB: Karabo scene SA1_XTD2_VAC/V11030F or for FXE: SA1_XTD2_VAC/V12030F )
3. Open the adjacent gate valves which were triggered by the vacuum interlock and continue with beam operation
4. Please inform the vacuum group (vacuum@xfel.eu)
If opening the valve again does not help because it trips to often, the fast valve can be disabled:
1. Open the valve by pressing “Open” button
2. When the valve is open again, switch off the high voltage of both sensors
3. Please inform the vacuum group (vacuum@xfel.eu)
Best regards,
Martin |
440
|
09 Jan 2018, 10:32 |
Martin Dommach | General | Problem | Shutdown of compressed air distribution in XTDs today | Dear all,
we got the information from MKK, that they have to fix a leak in the main compressed air line. Therefore they will close the valves to the tunnels for approximately one hour starting today at 1 p.m.
Please do not use the compresed air system in the tunnels during that time with air driven tools or air guns, as the volume of the distribution systems acts as a buffer.
Regards,
Martin
|
462
|
29 Jan 2018, 10:32 |
Martin Dommach | XTD10 | Information | closing of XTD10 shifted to Wednesday | Dear all,
the closing of the XTD10 tunnel is shifted to Wednesday (January 31st.) at 2 p.m.
Best regards,
Martin |
|