Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 2 of 30  Not logged in ELOG logo
ID Date Authordown Location Severity Subject
  34   02 Feb 2017, 17:46 Tobias HaasGeneralInformationStatus of component list as of 17:45
Attachment 1: Componets-XTD2-9.xlsx
  39   09 Feb 2017, 13:57 Tobias HaasGeneralInformationUpdate of installation list for tomorrow's S1R Meeting

 Please check if correct. I mark all newly done things in yellow!

Attachment 1: Componets-XTD2-9.xlsx
  40   09 Feb 2017, 17:16 Tobias HaasGeneralInformationStatus of Differential Pumping

Post on behalf of R. Villanueva

please find attached the updated status of the Differential Pumping
Modules in SASE 1. Just a few comments.

1. As you can imagine, no progress after KW4 in XTD2: system is ready to
deploy Karabo.
2. In XTD9, we have been pushing forward to finish the local test with AE.
Right now, everything has passed the local test except 3 vacuum gauges
that will be rechecked after the meeting. The main reasons for the little
progress (84%----->87%) are:

  a) more problems than expected with the cabling.
  b) a faulty Beckhoff Terminal.
  c) prioritization of  manpower (AE and VG) in other devices in the
tunnel.
  d)....the usual "sigmoidal" behavior of this kind of process.... ;)

3. In any case we aim to leave the system ready tomorrow so next week the
interlock code can be deployed safely.


Have a nice evening,

R.

  41   10 Feb 2017, 08:31 Tobias HaasGeneralInformationProgress Beam Transport

Post on behalf of Harald Sinn

Fortschritte, die ich letzte Woche beobachten konnte, sind: 

1.) Die Spiegelkammern wurden weiter lokal getestet. Benoit hat gestern abend den 
letzten Encoder am XTD9 vercrimmt. Wahrscheinlich muss der dann noch mal getestet werden, 
aber dann sollte das abgeschlossen sein. 
2.) Gestern haben wir zusammen mit Jan Tolkiehn den SRA und Filterkammer getetstet. 
SRA ist OK (incl. der Encoder), die Filterkammer auch, aber Wolfgang meinte, er müsste die 
LImit.switches noch mal etwas nachstellen (dafür sollte dann aber Karabo funktionieren, s.u.)
3.) Die PBLMs in XTD2 und die letzten beiden in XTD9 sich verkabelt und könnten von uns aus lokal 
getestet werden. Jan meinte allerdings, dass an den Elmo/technosoft (PBLM hat Elmo) Treibern noch etwas Arbeit
nötig ist, um zuverlässig Tests zu machen (MCI Library)
4.) Andreas Block hat mit Maik Neumann ausgemacht, dass sie sich Montag treffen und alle fehlenden Wasserverbindungen in 
SASE1 durchgehen und am besten sofort machen,. 
5.) Makus Schlösser hat bestätigt, dass nächste Woche (wohl leider nur) ein Team für uns arbeiten kann. 
Das wird zunächst aber in SASE3 hinten anfangen, weil wir da schnon einen Arbeitsstau in der Vakuumgruppe 
aufgebaut haben. Die relativ wenigen Komponenten in SASE1 werden natürlich auch fertig, aber Markus meinte, er würde vorhar 
lieber noch einige Daten konsolidieren. 
 
Zum lokalen testen: Das ist schon sehr wichtig, allerdings sollte es noch nicht mit dem technical commissioing 
verwechselt werden. Beim lokalen Testen wird nur festgestellt, ob sich der Motor in die richtige Richtung dreht 
und ob am Terminal die richtige LED leuchtet, wenn man den entsprechenden Endschalter drückt 
(Jan weiss dann, welche LED leuchten muss). Man sollte aber z.B. nicht auf den Endschalter fahren, weil in diesem 
Modus kein automatischer Stopp stattfindet, sondern man muss manuell eine Stopp Taste drücken. 
Auch werden nicht Motorgeschwindigkeit etc. optimiert oder gespeichert. 
Deswegen ist es wichtig, dass wir möglichst schnell Beckhoff+Karabo zum Laufen bringen, weil diese Tests 
essentiell sind und von den Komponentenverantwortlichen gemacht werden müssen. 
Falls die MCI Library tatsächlich ein Problem darstellt, was etwas dauert, würde ich vorschagen, die 
Beckhoff Motion Loop jetzt schon in Betrieb zu nehmen, mit den Motoren, die wir getestet haben. 
 
Grüße 
 
Harald 
 
 
  42   10 Feb 2017, 15:07 Tobias HaasGeneralInformationUpdated Components List

 Added Diagnostic Screen for SPB and changed PRIO for DPS - XGM - DPS in XTD9 to high as discussed during the S1R meeting

Attachment 1: Componets-XTD2-9-new.xlsx
  44   10 Feb 2017, 16:34 Tobias HaasGeneralInformationUpdated Components List
Attachment 1: Components-XTD2-9.xlsx
  54   24 Feb 2017, 16:33 Tobias HaasGeneralInformationUpdate of component list after weekly meeting
Attachment 1: 240217_Components-XTD2-9.xlsx
  55   28 Feb 2017, 11:38 Tobias HaasGeneralInformationReminder: Stable operation and development periods

One word of clarification:

The discussion last Friday left some people uncertain over how to define stable operation and development periods. Hence I had a discussion with Nerea and Alessandro and agreed on the following:

PLC development: Tuesday - Thursday

Stable operation with Karabo: Friday - Monday

Handover period is Thursday afternoon between AE and CAS 

 

  58   03 Mar 2017, 16:40 Tobias HaasGeneralInformationUpdate of Component Priority list after weekly meeting
Attachment 1: 170303_Components-Priority-list.xlsx
  59   03 Mar 2017, 16:46 Tobias HaasGeneralInformationMinutes of weekly SASE1 Readiness Meeting

 Here is the link to the minutes Minutes

  67   10 Mar 2017, 11:15 Tobias HaasGeneralInformationUpdate of Tunnel Component Priority List after SASE1 Readiness Meeting
Attachment 1: Components-Priority-list.xlsx
  68   10 Mar 2017, 11:18 Tobias HaasXHEXPInformationInstrument Component Priority List update after SASE1 Readiness Meeting
Attachment 1: 170310_Instrument_Components-Priority-list.xlsx
  70   10 Mar 2017, 12:53 Tobias HaasGeneralInformationUpdate of Tunnel Component Priority List after SASE1 Readiness Meeting

Note that due to a bug in the elog the name appeared wrongly in my previous message. In general: Avoid underscores in the file names! 

Attachment 1: 170310-Tunnel-Components-Priority-list.xlsx
  72   10 Mar 2017, 16:56 Tobias HaasGeneralInformationTunnel Commissioning Schedule for Week 11
Day Motion Vacuum EPS Other 
Monday Loop is up. AE continues tests on MC2 lib Loop up. AE investigates problem with ion pump controller Loop inactive  
Tuesday Loop is up. AE continues tests on MC2 lib Loop down. AE implements fix for ion pump controller Loop inactive  
Wednesday Loop down. AE adds ELMO and TECHNOSOFT Loop up for testing AE brings up loop  
Thursday Loop down. AE adds ELMO and TECHNOSOFT Loop up for testing AE brings up loop  
Friday Loop up for testing Loop up for testing Loop up for testing  

 

In addition it should be tried to have a so called "Happy Hour" every day from 0800 - 1000. During this time loops should be up if possible. Meaning that in the evening before leaving, developers bring loops back up.

  87   24 Mar 2017, 13:21 Tobias HaasGeneralInformationSchedule for PLC and Karabo Week 13

 

Day Motion Loop Vacuum Loop EPS Loop SPB Tunnel Loop Karabo
Monday Loop up.  Loop up.  Loop up  Loop inactive Version update by CAS 12:00 - 18:00
Tuesday Loop up.  Loop up.  Loop up  Loop inactive Running and no change
Wednesday Loop up.  Loop up  Loop up  AE brings up loop Running and no change
Thursday Loop up Loop up  Loop up  AE brings up loop Running and no change
Friday Loop up  Loop up  Loop up  Loop up Running and no change

 

 
  88   24 Mar 2017, 15:24 Tobias HaasGeneralInformationUpdate of component priority list after weekly meeting
Attachment 1: 170324-Tunnel-Components-Priority-list.xlsx
  90   31 Mar 2017, 15:00 Tobias HaasGeneralInformationUpdate of component list after weekly meeting
Attachment 1: 170331-Tunnel-Components-Priority-list.xlsx
  93   03 Apr 2017, 10:03 Tobias HaasGeneralInformationSchedule for PLC and Karabo 3 April after 09:30 Meeting

Tunnels closed today and tomorrow

- AE updates Vacuum and motion loop in the morning

- V. Bondar, J. Eidam and H. Sinn test vacuum in the afternoon (emphasis on understanding interlock conditions)

- A. Koch tests XTD2 imagers in the afternoon

See also  https://in.xfel.eu/redmine/projects/sase1/agile_board

 

Problems solved on Friday last week:

- Arms 2 & 4 of SRA are now moving. Apparently spindles had mechanical resistance that resulted in error condition. After moving a few times, this appears to be gone

- One of the problematic ion pumps had the serial line disabled. However, other lines 

 

 

 

  94   04 Apr 2017, 11:21 Tobias HaasGeneralInformationSchedule after 09:30 Meeting

 Tunnel closed today. Might re-open around 14:00

Note that that we re-convene briefly at 17:00 today in MCR (Mock-up Control Room)

Vacuum Loop:

Status:

  • Large number of ion pumps not responding properly (2 in XTD2, 63 in XTD9). There is the suspicion that the parameters on some ion pump controllers might be set incorrectly, such as baud rate or the bus address. The generated error code indicates a bad address.
  • Test in the lab requires Ion pump controller and PCL. No setup currently readily available. Check in the tunnel required. Could take place between 1200 and 1300 in XTD2 with a ZZ. (Update: B. Racky thinks she will be done around 1400 and would prefer access after this time)
  • Preparations needed to include XGM 

EPS Loop:

Status:

  • Temperature sensors return null value. Suspected firmware bug has been fixed and EPS loop updated by TF
  • EPS to MPS interface requires testing. Should be done tomorrow

Motion Loop:

Status:

  • Fixes have been applied to the MC2 lib. Tested for TECHNOSOFT driver. Should now work also for PBLMs . Tests do be done starting Wednesday

Imagers

Status:

  • Camera driver for SR imager not working
  • Camera driver for FEL driver working for imager in XTD2 but not for XTD9

Tasks for today:

  • E. Eidam, V. Bondor, , J. Tolkiehn H. Sinn go through all ion pumps in the Silenzi list
  • E. Eidam, T. Freyermuth check pump controller settings in the tunnel
  • A. Koch and W. Ehsan work on Photonics Camera driver for FEL imager

 

Tasks for tomorrow:

  • M. Planas, T. Maltezopoulos, N. Jardon, J. Eidam test XGM vacuum integration in XTD2 (not XTD9)
  • N. Gerasimova, N. Gerasimova and 1 firmware expert test PBLMs in the tunnel
  • T. Freyermuth tests EPS -> MPS interface

 

Other topics

  • The two signals from MCP to EPS shall be called MCP-upstream and MCP-downstream

 

 

 

 

 

 

 

  97   04 Apr 2017, 15:11 Tobias HaasGeneralInformationAccess to XTD2

MPS informed me that they hit some problems and that they still need 30 mins to 1 h until we can go to XTD.  