314
|
04 Jul 2017, 11:47 |
NEREA JARDON | XTD2 | Information | Motion loop | It will be replaced today around 1pm.Therefore Motion loop will be broken from this rack position.
NEREA JARDON wrote: |
We are finished. One encoder terminal has failed and needs replacing: rack 1.5 EC14
NEREA JARDON wrote: |
Dear all,
I have received a request from Konstantin Sukharnikov to break the Motion loop in XTD2 from Rack 1.5 in order to do checks in the CRLs. So you will loose communication with almost the whole Motion loop in SASE1. I will let you know when they are finished.
Thank you,
|
|
|
315
|
04 Jul 2017, 14:07 |
NEREA JARDON | XTD2 | Information | Motion loop | The encoder terminal in rack 1.5 has been replaced.
NEREA JARDON wrote: |
It will be replaced today around 1pm.Therefore Motion loop will be broken from this rack position.
NEREA JARDON wrote: |
We are finished. One encoder terminal has failed and needs replacing: rack 1.5 EC14
NEREA JARDON wrote: |
Dear all,
I have received a request from Konstantin Sukharnikov to break the Motion loop in XTD2 from Rack 1.5 in order to do checks in the CRLs. So you will loose communication with almost the whole Motion loop in SASE1. I will let you know when they are finished.
Thank you,
|
|
|
|
316
|
05 Jul 2017, 17:48 |
NEREA JARDON | General | Information | Motion loop update | Dear all,
In order to finish the configuration of part of Hirex devices, we need to make an update of the Motion loop tomorrow morning at 10am. Please drive your devices to safe position before this hour.
Thank you |
318
|
06 Jul 2017, 12:49 |
NEREA JARDON | General | Information | Vacuum Loop | Dear all,
Sorry for the short notice, but we have to do an update of the Vacuum loop in order to get the neecssary interlock for the experiments done. I will contact know WP74 and Vacuum group so they can be awared about their equipments.
Thank you, |
319
|
06 Jul 2017, 15:03 |
NEREA JARDON | General | Information | Vacuum Loop | Vacuum Loop is running again.
Thank you!
NEREA JARDON wrote: |
Dear all,
Sorry for the short notice, but we have to do an update of the Vacuum loop in order to get the neecssary interlock for the experiments done. I will contact know WP74 and Vacuum group so they can be awared about their equipments.
Thank you,
|
|
321
|
07 Jul 2017, 13:24 |
NEREA JARDON | General | Information | EPS loop | Dear all,
We need to update EPS SASE1 loop in order to finish the interlock communication for the experiments. I will do the update around 14h.
Thank you! |
325
|
10 Jul 2017, 15:23 |
NEREA JARDON | General | Information | Motion loop update | Dear all,
We will do an update of the Motion Loop in the next 15minutes in order to fix one analog signal related to the KMONO.
Thank you |
327
|
12 Jul 2017, 15:15 |
NEREA JARDON | General | Information | Motion loop update | Dear all,
Tomorrow morning we will do an update in the Motion loop due to some hardware changes requested in Rack number 1.18. You might will not have communication with this rack during whole day, because they will be doing local test after changing the hardware..
Thank you and bests, |
328
|
13 Jul 2017, 07:46 |
NEREA JARDON | General | Information | Motion loop update | Motion loop is up and running again, as I have said, you will not have communicatin with equipments of Racks 1.18 till Denis finishes with hardware changes.
Thank you,
NEREA JARDON wrote: |
Dear all,
Tomorrow morning we will do an update in the Motion loop due to some hardware changes requested in Rack number 1.18. You might will not have communication with this rack during whole day, because they will be doing local test after changing the hardware..
Thank you and bests,
|
|
329
|
13 Jul 2017, 10:27 |
NEREA JARDON | XTD9 | Information | Vacuum Loop in XTD9 | Dear all,
One power supply needs to be changed in SASE1 XTD9 rack 1.12 tomorrow and it's related to the Vacuum loop. Denis Finze will do this change tomorrow morning, but we have to make sure before that we have all the equipments after this rack 1.12 in safe state (most concerning part, XGM in XTD9). Please, could you make sure that everything it's ok tomorrow at 10am? However I will send an email now to the involved people.
Thank you and best regards, |
430
|
06 Dec 2017, 17:17 |
NEREA JARDON | General | Information | SASE1 MOV | The Motion loop in SASE1 is totally operated again. |
509
|
13 Apr 2018, 13:50 |
NEREA JARDON | General | Information | Shutdown MicroTCA4 SPB and FXE | This entry is on behalve of Frank Babies, if you have any doubt about it, contact him:
On 16.Apr.2018 09:45am till Noon I have to shutdown the MicroTCA4 Crates Rackroom from FXE
"fxe-rr-sys-utc-1"
"fxe-rr-sys-utc-2"
because of the Power Down issue on Monday.
On 17.Apr.2018 09:45am till Noon I have to shutdown the MicroTCA4 Crates Rackroom from SPB
"spb-rr-sys-utc-1"
"spb-rr-sys-utc-2"
because of the Power Down issue on Tuesday.
This will affect timing system and MPS communication.
|
227
|
12 May 2017, 12:26 |
Monica Aresté | General | Information | Update of Instrument component priority list | Find attached the Instrument Component priority list discussed this morning.
Regards,
Monica |
Attachment 1: 170512_Instrument_Components-Priority-list.xlsx
|
252
|
19 May 2017, 12:46 |
Monica Aresté | General | Information | Update of Instrument component priority list |
Find attached the Instrument Component priority list discussed this morning.
Regards,
Monica
|
Attachment 1: 170519_Instrument_Components-Priority-list.xlsx
|
284
|
09 Jun 2017, 12:41 |
Monica Aresté | General | Information | Status and plans after SASE1 Readiness Meeting |
General
- E. Boyd presents a summary of the next tasks for the radiation measurements for hutch commissioning. There are some dates (13th and 20th June) that safety needs exclusively access to the hutches. Safety will be in close contact with Instruments to agree the dates.
- Tests are finished in SPB Optics (40 connectors to be replaced) and continue now in FXE.
- There is an interference of connector replacement and tests of the interlock. If Instruments grant exclusively access for the Interlock works, this has to communicate to PSPO to inform company JOWO that is working in the cable reparations.
- Starting this week, new messages in the elog appear not to be sent to all registered user. The system unsuscribed automatically from one elog when you suscribe to a new one. IT has already fixed this problem.
- WLAN access at the end of XTD9 is not very good and not sufficient for testing cameras, e. g. in PBLMs
XTDs
- Motion loop updated twice during this week, but there is still an issue with Elmo limits. AE will first test a solution and decide if a new update is necessary.
- PBLM tests with Mahadi and Natalia shall start after motion loop update.
- There has been a modification of the interlock conditions by RAUL for the gas section. This needs to be carefully checked.
- There is a request to improve the information when the tunnels are open/close, now it takes too much time to find the information in the elog. Suggested to have a unique place with the information up-to-date.
FXE
- There is a mistake in the channel assignment of the Ion pump controllers, modules BKF00074 and BKF00096 will be modified today. Moreover firmware for loops 1 and 2 have to be updated.
- JJ XRay is here this week, acceptance test for CRL is done. Work will continue with von Hamos Spectrometer
- The LPD 2-tile system brought into the hutch to test the controls.
- Loop 8 already deployed.
- Interlock defintion for FXE is done.
SPB
- Currently there is no working version of Karabo for SPB (Fixes were implemented that broke base functionality)
- EET is working to generate the exports for loops 7 and 12.
- There are still some mismatches in the connectors of 11 cables, A. Legrand working with Actemium to fix the problems.
- In loop2 one module is being reworked by AE.
- SPB is also affected by the problem with the Ion pumps, AE to figure out which modules have to be reworked.
Laser
- The humidity in the hutch is down to 50%, but still oscillates
- AE is fixing connectors with water problems
- After PLC cycling the Beckhoff terminals loose the proper parameter set. AE working on that issue but need soe additional information.
- There is a mismatch beween the motors and trthe control, AE will check if it a firmware or hardware problem.
Detector
- LPD test working succesfully, waiting when FXE hutch will be ready to move the LPD. Radiation protection has to be finished before to move the detector.
Software
- Deployment of KARABO version 2.1.12 will be deployed today to FXE. D. Goeries shows a presentation with a description of improvements in the new version.
|
287
|
12 Jun 2017, 10:55 |
Monica Aresté | General | Information | Status and plans after SASE1 Readiness Meeting | Tunnel's schedule:
- Monday 12th June: XTD10 closed, XTD9 open
- Tuesday 13th June: from 7:00 to 15:00 all open.
- There is a request to have a unique place with updated information when the tunnels are open/closed, PSPO is working to set a place in the intranet and will inform as soon as this will be agreed.
General
- Cable reparations on OPT hutch on going, FXE will follow.
- WLAN access at the end of XTD9 is not very good and not sufficient for testing cameras, e. g. in PBLMs. ITDM re-cabled some ports and provided office network port in rack 1.17 that could be used to commission the cameras. According to Liuba it worked well.
- From 08/06/2017 the ITDM group provides the OCD service. The general principle is that the 1st level support is provided by CAS group and in case they cannot solve the ITDM related issue they call us. The phone number for ITDM OCD is: 98070 or directly +49 175 9814494. There is a single number for 3 mobile phones so the number is valid independent on the person providing OCD.
XTDs
- Motion loop updated twice during last week, but there is still a feature to be fixed.
- There has been a modification of the interlock conditions by RAUL for the gas section. Already implemented and working.
FXE
- There is a mistake in the channel assignment of the Ion pump controllers, modules BKF00074 and BKF00096 modified. Bug with the ion pump controllers still not corrected, AE and CAS are working on that.
- Acceptance test for CRL is done, final parameters settled down, next step is to test CRL with PLC.
- Loop 8 already deployed but still not working. This loop is low priority.
- Radiation safety measurements are the first priority for this wwek in FXE.
SPB
- Currently there is no working version of Karabo for SPB (Fixes were implemented that broke base functionality)
- EET is working to generate the exports for loops 7 and 12. Export for loop 7 will take longer than expected acc. to last info from EET.
- All motors in loop 1 are working.
- In loop2 one module is being reworked by AE, still on going.
- Firmware for Loop 3 is available.
- SPB is also affected by the problem with the Ion pumps, modules BKF00056, 00057 affected. AE working to solve this issue.
Laser
- After PLC cycling the Beckhoff terminals loose the proper parameter set. AE working on that issue but need some additional information from Laser group.
- There is a mismatch beween the motors and the control, AE will check if it ia a firmware or hardware problem.
Software
- Deployment of KARABO version 2.1.12 was deployed to FXE on Friday. The new version is deployed but not activated since there are some issues to fix.
|
288
|
12 Jun 2017, 11:17 |
Monica Aresté | General | Information | Tunnel's schedule |
Tunnel's schedule clarification:
- Monday 12th June: XTD10 closed, XTD9 open
- Tuesday 13th June: from 7:00 to 15:00
all XTD9 and XTD10 open (all is incorrect, I mean XTD9 and XTD10).
Someone pointed out that XTD2 maintenance for tomorrow is cancelled and XTD2 wil be closed.
|
289
|
12 Jun 2017, 13:21 |
Monica Aresté | General | Information | Tunnel's schedule updated | Last information is that tomorrow Fire brigade will come to inspect the tunnels, therefore all tunnels will be open from 7:00 to 15:00.
H. Sinn inform that XTD9 will not be searched until Wednesday morning.
Tunnel's schedule:
- Monday 12th June: XTD10 closed, XTD9 open
- Tuesday 13th June: from 7:00 to 15:00 all open
|
290
|
14 Jun 2017, 10:57 |
Monica Aresté | General | Information | Status and plans after SASE1 Readiness Meeting | General:
- G. Wellenreuther has created a link to the first version of a central schedule of "our" tunnels: https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules
- Any changes of schedules should be put in there first, and THEN a short message can be sent using the e-log pinpointing people always to this page. Please check correctnesss, and feel free to provide Gerd with any feedback.
XTDs
- Minor problem with Ion pump controllers, AE working on it.
- Vacuum loop needs an update but it is not urgent.
FXE
- Ion pumps controller issue already fixed.
- Test of CRL with PLC is on going. There are some issues with encoders, could be a cable mismatch problem in PP, JJ to check. The cables for CRL have been already measured and are correct.
- Radiation safety measurements being doing today.
SPB
- EET is working to generate the exports for loops 7 and 12. Export for loop7 will be ready this week and EET will continue with loop 12.
- Tests with loop2 on going.
- Firmware for Loop 3 is available, but cables have to be repaired.
- Modules BKF00056, 00057 affected by Ion pumps issue already modified.To double check with N. Coppola if more modules are also affected by this problem.
- Cameras are not in Karabo, this is a requirement before cameras can be connected. A. Silenzi to work on that.
Laser
- After PLC cycling the Beckhoff terminals loose the proper parameter set. AE working on that issue but need some additional information from Laser group.
- There is a mismatch beween the motors and the control, AE will check if it ia a firmware or hardware problem.
Diagnostics
- External trigger not always working, CAS working to find the cause and provide a solution.
Software
- Karabo version installed in a different domain, this will permit to fix errors. When this version will be ready, CAS will need 2 hours of downtime to implement.
|
292
|
16 Jun 2017, 10:18 |
Monica Aresté | General | Information | Status and plans after SASE1 Readiness Meeting | General:
- E. Boyd update the status about the tasks for radiation measurements the 26th June. See presentation attached.
- J. Gruenert suggest to use similar interface as is being use for the machine and will send the link to G. Wellenreuther.
XTDs
- Images for Photo commissioning on the tunnel are stored by a temporary solution. J. Grunert request when the DAS routines will work, CAS will prepare a short presentation for the meeting next Friday to show the progress on that issue.
- This weekend is scheduled to commissioning with a WL of 1,5Å and 30 bunches into the dump for first time.
FXE
- Radiation safety measures done last Wednesday.
- Leaks in the Vacuum system already fixed.
- Cables for motors already repaired by JOWO this week. Reparations will continue next week after urgent cables for SPB are done.
- In general loops are working but there are still some minor issues, AE working in some loops updates.
- Meting on Monday between FXE and AE to define Interlock to deploy.
SPB
- Loop 1 is working, AE to fix some mismatchs in loops 2 and 3.
- Export for loop 7 is done, AE is working to generate the firmware. EET has two persons working in the exports for loops 4 and 12.
- Ion pump cables repaired and tests on going.
- All connector reparations in the OPT-hutch are done and the test of the motors are on going.
- JOWO will keep working in 20 urgent cables for SPB and then move back to FXE.
Detector
- AGIPD is fully powered, there are still some issues for the Intelock that needs AE support.
- More details see attached file provided by Detector Group.
Laser
- The humidity in the hutch still oscillates, this shoud be fixed urgently since it is preventing further commissioning.
- Image processor not working since each 2-3 hours stops, CAS to fix that issue.
- There are motors not working, CAS to investigate.
Electronics
- First priority is is to have the Vacuum system for FXE and SPB operational at the end of June. Next two weeks AE will be mainly focus in the loops that are still missing (SPB 4, 5, 7,12) or still not running (SPB 2, 3)
- Elmo controllers not integrated, AE will test a solution in SPB on next week. If it works will be deployed also for the tunnels but this is not first priority and will be done in July.
Software
- CAS is working to have a more robust system, S. Brockhauser point out that new request from instruments should we send to CAS to define priorities.
- To prepare a short presentation for next Friday about the issue of the tunnel DAS to store images (see point in XTDs)
|
Attachment 1: Radiation_Measurments_for_Commissioning.pptx
|
Attachment 2: 20170615-Components-Detectors.xlsx
|
|