ID |
Date |
Author |
Location |
Severity |
Subject |
Text |
|
497
|
04 Apr 2018, 13:43 |
Gerd Wellenreuther | General | Information | Status reports after dispatch meeting 13:00 4.4. | SPB/SFX:
Mirror installation next
week
FXE: |
|
496
|
29 Mar 2018, 09:48 |
Hugo Silva Santos | General | Information | Re: Status report after dispatch meeting 09.30 | Update regarding Digitizer:
----- Forwarded Message -----
From: "hamed sotoudi namin" |
|
495
|
28 Mar 2018, 15:22 |
Adriano Violante | General | Information | Status report after dispatch meeting 09.30 | SPB
Sample delivery installed.
Tonight will be commissioned. Experiment |
|
494
|
27 Mar 2018, 14:18 |
Jan Gruenert | General | Information | XTD1 open | Info from BKR: the southern tunnels
were opened, thus XTD1 can be accessed now. |
|
493
|
26 Mar 2018, 13:10 |
Adriano Violante | General | Information | Status report after dispatch meeting 09.30 | General
Due to the triggering of the emergency
power off in FXE caused by electrical works |
|
492
|
25 Mar 2018, 10:57 |
Gerd Wellenreuther | XHEXP | Problem | FXE emergency power-off has been triggered | Dear all,
apparently the Emergency Power-Off
at FXE was triggered at around 10:00 - 10:30 |
|
491
|
21 Mar 2018, 10:02 |
Adriano Violante | General | Information | Status report after dispatch meeting 09.30 | SPB
On monday there was an issue with
a detector related PLC due to misconnection |
|
490
|
19 Mar 2018, 10:24 |
Adriano Violante | General | Information | Status report after dispatch meeting 09.30 | No new issues to be discussed where reported
by any groups.
The status and issues reported |
|
489
|
19 Mar 2018, 08:42 |
Adriano Violante | General | Information | Status and plans after SASE1 Status/SASE3 Readiness Meeting 16.03.. | Photon Run Coordinator (H. Sinn):
1.) SASE1: User experiment SPB
could be finished sucussfully after several |
|
488
|
14 Mar 2018, 10:06 |
Adriano Violante | General | Information | Status report after dispatch meeting 09.30 | SPB (Weinhausen/Round/Mancuso):
Again on the fast valve was
triggering the MPS interlock system. For |
|
487
|
12 Mar 2018, 13:18 |
Adriano Violante | General | Information | Status report after dispatch meeting 09.30 | SPB (Weinhausen):
During the night there
was an interlock issue. The fast shutter |
|
486
|
12 Mar 2018, 08:18 |
Adriano Violante | General | Information | Status and plans after SASE1 Status/SASE3 Readiness Meeting 09.03 | Photon Run Coordinator (L. Samoylova):
Commissioning during |
|
485
|
07 Mar 2018, 11:14 |
Adriano Violante | General | Information | Status report after dispatch meeting 09.30 | SPB:
Monday morning Karabo failed.
It was not possible to operate anything. |
|
484
|
05 Mar 2018, 16:37 |
Adriano Violante | General | Information | Details on SPB issues reported in the dispatch meetings | Below some clarifications from R. Bean
on the issues reported in today's dispatch
meeting: |
|
483
|
05 Mar 2018, 11:07 |
Adriano Violante | XHEXP | Information | Status report after dispatch meeting 09.30 |
SPB
Last night the beam disappeared |
|
482
|
02 Mar 2018, 14:36 |
Adriano Violante | General | Information | Status and plans after SASE1 Status/SASE3 Readiness Meeting 02.03. | Photon
Run Coordinator (N. G. Kujala):
SASE1
|
|
481
|
28 Feb 2018, 10:55 |
Adriano Violante | General | Information | Status report after dispatch meeting 09.30 | SPB:
Ion pumps running in the
Mirror chamber. Vacuum level OK to run.
D.02 |
|
480
|
26 Feb 2018, 12:09 |
Monica Aresté | General | Information | Status report after dispatch meeting 26.02 | SPB:
Ion pumps running in the
Mirror chamber.
Starting test |
|
479
|
23 Feb 2018, 15:54 |
Gerd Wellenreuther | General | Information | Status and plans after Readiness Meeting 23.02. | Photon Run Coordinator (L. Samoylova):
SASE1 tuning is ongoing
(350 microJ)
SASE3 3000microJ
SASE1 |
|
478
|
21 Feb 2018, 13:49 |
Alessandro Silenzi | General | Information | Re: Status report after dispatch meeting 09.30 | Small correction:
The coordinated motion is the KB-mirror's,
not the Vacuum. |
|