Notes XO Integration Meeting 19.02.2024, posted by Frederik Wolff-Fabris on 19 Feb 2024, 09:55
|
General Announcement:
- As PRC Maurizio V. mentions there is nothing particularly important to report.
|
Notes XO Integration Meeting 14.02.2024, posted by Frederik Wolff-Fabris on 14 Feb 2024, 12:21
|
General Announcement:
- As PRC, Maurizio Vannoni says so far everything is going well this week.
|
Notes XO Integration Meeting 12.02.2024, posted by Frederik Wolff-Fabris on 12 Feb 2024, 09:40
|
General Announcement:
- As PRC, Andreas G. informs the week went smooth so far.
|
Notes XO Integration Meeting 07.02.2024, posted by Frederik Wolff-Fabris on 07 Feb 2024, 10:29
|
General Announcement:
-
|
Notes XO Integration Meeting 05.02.2024, posted by Frederik Wolff-Fabris on 05 Feb 2024, 09:57
|
General Announcement:
-
|
Notes XO Integration Meeting 31.01.2024, posted by Frederik Wolff-Fabris on 31 Jan 2024, 09:57
|
General Announcement:
- Steffen Hauf informs on DAQ: the crashes on slow aggregators were reproduced in the lab. A work is being prepared to be tested at MID tomorrow or Friday.
|
Notes XO Integration Meeting 29.01.2024, posted by Frederik Wolff-Fabris on 29 Jan 2024, 09:57
|
General Announcement:
- Experiment tuning week starts on Wed 7AM until Tue 7AM next week. It is the first week with Tuesday as tuning day by machine.
|
Notes XO Integration Meeting 22.01.2024, posted by Frederik Wolff-Fabris on 22 Jan 2024, 09:47
|
General Announcement:
- Reminder that machine tuning day is on Tuesdays and Friday's User op meeting does not contain Coordinator reports this year which are to be done on Mondays
RC meeting.
|
Notes XO Integration Meeting 17.01.2024, posted by Frederik Wolff-Fabris on 17 Jan 2024, 09:44
|
General Announcement:
- Functional interlock tests at instruments are ongoing by D3 and SRP. Information was sent by e-mail.
- A. Galler reminds that from this year the machine maintenance and tuning day takes place on Tuesdays.
|
Notes XO Integration Meeting 15.01.2024, posted by Frederik Wolff-Fabris on 15 Jan 2024, 10:52
|
General Announcement:
- Interlock tests light: functional tests will happen this Wednesday starting at 09:00 at the instruments. Emergency OFF will not be pressed.
|
Notes XO Integration Meeting 10.01.2024, posted by Frederik Wolff-Fabris on 10 Jan 2024, 10:37
|
General Announcement:
- Interlock tests are finished and XTD6 and XTD9 will be closed again today during the day. They shall close on January 19th.
|
Notes XO Integration Meeting 08.01.2024, posted by Frederik Wolff-Fabris on 08 Jan 2024, 09:41
|
General Announcement:
-
|
Notes XO Integration Meeting 20.12.2023, posted by Frederik Wolff-Fabris on 20 Dec 2023, 09:43
|
General Announcement:
- This is the last XO Integration meeting for this year.
|
Notes XO Integration Meeting 18.12.2023, posted by Frederik Wolff-Fabris on 18 Dec 2023, 10:13
|
General Announcement:
-
|
Notes XO Integration Meeting 13.12.2023, posted by Frederik Wolff-Fabris on 13 Dec 2023, 10:04
|
General Announcement:
-
|
Notes XO Integration Meeting 11.12.2023, posted by Frederik Wolff-Fabris on 11 Dec 2023, 09:51
|
General Announcement:
-
|
Notes XO Integration Meeting 06.12.2023, posted by Frederik Wolff-Fabris on 06 Dec 2023, 09:49
|
General Announcement:
- Jan Gruenert announces a seminar done by UK guests from Daresbury on UK plans for FEL. The seminar happens on THU 13:30 at XHQ E2.042. Please contact
Jan G. for zoom link.
|
Notes XO Integration Meeting 04.12.2023, posted by Frederik Wolff-Fabris on 04 Dec 2023, 09:52
|
General Announcement:
-
|
Notes XO Integration Meeting 29.11.2023, posted by Frederik Wolff-Fabris on 29 Nov 2023, 09:43
|
General Announcement:
- Please remember and remind group members that the machine day is on Tuesdays and not Mondays anymore. Delivery will then start on Wednesday.
- Regarding the 2025 shutdown at the 2nd half of the year: XO is collecting initial tasks. Please groups are asked to provide a draft to XO of the planned |
Notes XO Integration Meeting 27.11.2023, posted by Frederik Wolff-Fabris on 27 Nov 2023, 09:39
|
General Announcement:
- User operation finished this morning 7AM for the year.
- Reminder that WMP starts on Thursday. Possible photon tunnels open on Wednesday but this still to be confirmed and e-mail will be sent.
|