Message ID: 500     Entry time: 20 Mar 2024, 10:12
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 20.03.2024 
General Announcement:
-	 

CTRL:
- Nothing to report.

DA:
- All fine at DA.

EEE:
- PLC team received SCS calls regarding interlocks; under investigation.

VAC:
- Last weeks a shutdown on seven ion pumps happened on Friday but was restarted remotely.

XPD:
- All running good from XPD.

DET:
- AGIPD follow-up: nothing obvious was found, but module started working again after quadrant was moved; it may relate to vacuum issues and results from operation or electrical connection.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- Nothing to report.

UNSYS:
- Everything is fine;
- On Monday successful operation from BKR operators regarding Apple-X. 
A. Galler clarifies the Apple-X is not yet available for instruments and coordination with Unsys, machine and photon RCs are still needed.

SPB:
- Nothing to report.

FXE:
- Taking the beam and everything is fine so far.

MID:
- Nothing to report.

HED:
- Not present.

SCS:
- Since yesterday, Tuesday, an issue with a O2 sensor happens but TS and TN were informed.
- Interlock issues that EEE is also informed.

SQS:
- Not present.

SXP:
- Not present.