Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 509     Entry time: 24 Apr 2024, 09:49
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 24.04.2024 
General Announcement:
-	 

CTRL:
- Broker incident on SA2 and LAS topics last Saturday: update to be done in a split mode; 
SA2 topic could not be done yesterday so is planned for Tuesday 30.04 morning and LAS topic to be done still this week as none uses PP-laser.

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- Everything fine;
- SA2 FEL IMG issue: linked mainly to a bridge connection to DOOCS (left over from broker issue on Saturday). Restart it only yesterday and not during the weekend. 

DET:
- Nothing major;
- Feedback from Jungfrau test at SPB last week: unfortunately, did not fully run as expected as user Bragg magnifier scene was optimized at 10keV and not 21keV. 
Nevertheless, data could be seen and it was useful to have beamtime.

ITDM: 
- On EXFEL Gateway: need to apply a fix and update security; an e-mail will be sent for scheduling on next Tuesday.

XRO:
- Not present.

LAS:
- Nothing to report.

UNSYS:
- Everything fine.

SPB:
- Nothing o report.

FXE:
- Problem with middle layer server reported to DOC this morning. It seems solved after server restarted.

MID:
- Nothing to report.

HED:
- Not present.

SCS:
- Nothing to report.

SQS:
- Nothing to report.

SXP:
- Issue with detector/data found last week and on the way to be fixed for next week. 
ELOG V3.1.4-7c3fd00