Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 515
Entry time: 22 May 2024, 09:53
|
Author: |
Frederik Wolff-Fabris |
Location: |
General |
Severity: |
Information |
Subject: |
Notes XO Integration Meeting 22.05.2024 |
|
|
General Announcement:
- Next Friday 24.05 is the deadline to submit maintenance task lists. Please contact XO in case you are not prepared to submit by the deadline.
CTRL:
- Nothing to report.
DA:
- Not present.
EEE:
- Issue with Hexapod in HED: under investigation by EEE and Bernard B. Not having the Hexapod will affect the experiment this week. A back plan exists but no guarantee it works if a fix can't be done.
VAC:
- Nothing to report.
XPD:
- Nothing to report.
DET:
- Julabo chiller at SPB/SFX does not maintain the low temperature - under work.
- Two weeks ago (user experiment) some AGIPD modules at SPB/SFX were exchanged and damage has been found at the new modules.
A report by SPB/SFX will be written for that it does not happen again as if damages are frequently happening one will run out of spare modules.
ITDM:
- Works started in the network at lab areas and are ongoing.
XRO:
- Nothing to report.
LAS:
- Flatness of SPB PP-laser under investigation;
- SA3 PP-laser stain issue did not go away: manufacture of front-end amplifier is contacted; further tests to be done today.
UNSYS:
- Not present.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- All fine at MID.
HED:
- Hexapod issue already mentioned.
SCS:
- Nothing to report.
SQS:
- Nothing to report.
SXP:
- Nothing to report. |