SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 501
Entry time: 25 Mar 2024, 10:24
|
Author: |
Frederik Wolff-Fabris |
Location: |
General |
Severity: |
Information |
Subject: |
Notes XO Integration Meeting 25.03.2024 |
|
|
General Announcement:
- A power glitch happened last night around 02:50AM.
CTRL:
- Nothing to report.
- DAQ update: MID had operation during the weekend and seems to run fine; one issue after several hours needed a recycling but further investigation is ongoing to provide a fix in the coming days.
DA:
- Nothing to report.
EEE:
- Nothing to report.
VAC:
- Nothing to report.
XPD:
- Nothing to report.
DET:
- Nothing major to be report.
- AGIPD in SPB/SFX is running with 16modules; issue with connection caused one module to do not work (due to positions). There is a golden position and for next quadrant move has to be observed.
For a fix one needs a heavy intervention (disassemble half the detector - for the big shutdown).
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Not present.
UNSYS:
- Everything is fine.
SPB:
- Nothing to report.
FXE:
- Not present.
MID:
- All fine at MID.
HED:
- Nothing to report.
SCS:
- Experiment goes well so far.
- Hall crew will support SCS this week.
SQS:
- Nothing to report.
SXP:
- Not present. |