Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 498     Entry time: 13 Mar 2024, 11:30
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 13.03.2024 
General Announcement:
-	 

CTRL:
- Nothing to report.

DA:
- Not present.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- Nothing to report.

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- Nothing to report.

UNSYS:
- Everything is fine. ZZ on Monday was successful.

SPB:
- Nothing to report;
- Problem with AGIPD chiller: seems solved for the moment - see how it goes next days.

FXE:
- Nothing to report.

MID:
- All fine at MID.

HED:
- Starting with the beam.

- SCS:
- Prepared equipment; maybe electronics will be contacted later.

SQS:
- All good.

SXP:
- All not present.