SASE1 Status and SASE3 Readiness Technical integration and coordination
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 511     Entry time: 06 May 2024, 09:21
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 06.05.2024 
General Announcement:
- Summer maintenance task list was sent to the groups. Please contact XO in case of questions or if your group did not receive the list.

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- Discussion ongoing for the summer maintenance tasks.

VAC:
- No OCD calls for VAC and systems seemed to be not affected by this morning's power glitch at 05:47AM.

XPD:
- Everything fine with diagnostics.

DET:
- Nothing major to be reported.
- 500k AGIPD over the weekend was helped by DOC and DATA OCDs solved.

ITDM: 
- Nothing to report.

XRO:
- Event of misalignment of M6 on Friday for SA3/SXP under investigation. It will be discussed with SXP.

LAS:
- Not present.

UNSYS:
- All fine with undulators.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- Nothing to be reported.

HED:
- Running and thanks to DOC and OCDs for AGIPD help.

SCS:
- Not present.

SQS:
- Nothing to report.

SXP:
- Not present.