35
|
24 Apr 2019, 10:05 |
Gerd Wellenreuther | General | Information | Minutes of the Technical integration meeting 24.04.19 | SPB/SFX
SPB/SFX is preparing for
the upcoming beamtime.
CRL motors |
|
46
|
22 May 2019, 09:58 |
Gerd Wellenreuther | General | Information | Minutes of the Technical integration meeting 22.05.19 | FXE
SPB/SFX
XTD2 attenuator |
|
81
|
21 Aug 2019, 11:15 |
Adriano Violante | General | Information | Minutes of the Technical integration meeting 21.08.19 | XO
A review of the procedures
in case of power failure is in progress. |
|
86
|
20 Nov 2019, 10:12 |
Adriano Violante | General | Information | Minutes of the Technical integration meeting 20.11.19 | FXE
Wille was asked by D3
to pull new cables for the Pandora in FXE |
|
22
|
20 Mar 2019, 14:07 |
Adriano Violante | General | Information | Minutes of the Technical integration meeting 20.03.19 | SPB/SFX
CRL implementation in the
hutch will happen in April. AE and EET involved. |
|
10
|
20 Feb 2019, 11:16 |
Adriano Violante | General | Information | Minutes of the Technical integration meeting 20.02.19 | SPB/SFX
CSS component commissioning.
Concept and implementation being finalized.==> |
|
56
|
19 Jun 2019, 10:55 |
Adriano Violante | General | Information | Minutes of the Technical integration meeting 19.06.19 | FXE
SPB/SFX
No major issues
Starting |
|
68
|
17 Jul 2019, 10:05 |
Adriano Violante | General | Information | Minutes of the Technical integration meeting 17.07.19 | XO
FXE
SPB/SFX |
|
34
|
17 Apr 2019, 11:34 |
Adriano Violante | General | Information | Minutes of the Technical integration meeting 17.04.19 | SPB/SFX
CRL motors being tested.
Today BB (AE) will check the status.
CSS |
|
43
|
15 May 2019, 12:53 |
Adriano Violante | General | Information | Minutes of the Technical integration meeting 15.05.19 | SPB/SFX
Nano KB mirrors and CSS
controls are OK
Digitizers have |
|
79
|
14 Aug 2019, 10:01 |
Gerd Wellenreuther | General | Information | Minutes of the Technical integration meeting 14.08.2019 | XO
On Monday at around 12:20
there was a power glitch at least in Hamburg, |
|
19
|
13 Mar 2019, 11:11 |
Adriano Violante | General | Information | Minutes of the Technical integration meeting 13.03.19 | SPB/SFX
CRL implementation in the
hutch will happen in April. AE and EET involved. |
|
7
|
13 Feb 2019, 10:59 |
Adriano Violante | General | Information | Minutes of the Technical integration meeting 13.02.19 | SPB/SFX
CSS component commissioning.
RBean is discussing with AE. Concept and |
|
53
|
12 Jun 2019, 12:40 |
Adriano Violante | General | Information | Minutes of the Technical integration meeting 12.06.19 | FXE
SPB/SFX
SCS |
|
66
|
10 Jul 2019, 16:16 |
Adriano Violante | General | Information | Minutes of the Technical integration meeting 10.07.19 | XO
In SASE3 the apertures
of the GATT have to be realigned. The upstream |
|
31
|
10 Apr 2019, 10:54 |
Adriano Violante | General | Information | Minutes of the Technical integration meeting 10.04.19 | SPB/SFX
CRL implementation in the
hutch. Tests can start today.
CSS |
|
40
|
08 May 2019, 10:10 |
Adriano Violante | General | Information | Minutes of the Technical integration meeting 08.05.19 | SPB/SFX
IRDa commissioning
ongoing.
CSS. Limit switches |
|
77
|
07 Aug 2019, 11:55 |
Adriano Violante | General | Information | Minutes of the Technical integration meeting 07.08.2019 | XO
The accelerator is now working
at 2.25 MHz. Kicker can be used. DET informs |
|
16
|
06 Mar 2019, 10:31 |
Adriano Violante | General | Information | Minutes of the Technical integration meeting 06.03.19 | SPB/SFX
CSS component commissioning.
Concept and implementation finalized. EPLAN |
|
4
|
06 Feb 2019, 11:13 |
Adriano Violante | General | Information | Minutes of the Technical integration meeting 06.02.19 | SPB/SFX
AGIPD commissioning and
tests. ==> intervention on the wings is |
|