Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 571     Entry time: 04 Dec 2024, 09:41
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 04.12.2024 
General Announcement:
- A. Galler informs X-rays for cw49 are currently been tuned today due to the issues with the cryo plant last week. Schedule for delivering the beam to instruments is to start by 15:00 today.

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- Everything is fine; switch to 17keV XGM went fine.
- As PRC, J. Gruenert has nothing to report.

DET:
- Nothing to report.
- Burned power plugs on LPD: no updates, however all modules are working.

ITDM: 
- Not present.

XRO:
- Nothing to report.

LAS:
- All quiet with Lasers.

UNSYS:
- Everything fine apart of the PS in cell20/SA3 (to be fixed in the WMP).

SPB:
- Nothing to report.

FXE:
- Regarding the LPD: cable was by-passed.

MID:
- All fine at MID.
- On Monday 09.12 there will be a switch in beam delivery to HED.

HED:
- Not present.

SCS:
- Nothing to report.

SQS:
- Nothing to report.

SXP:
- Preparing for beamtime this week.