Message ID: 545     Entry time: 04 Sep 2024, 09:40
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 04.09.2024 
General Announcement:
- Machine tuning last two days was hindered as a power supply for a camera in injector laser had to be exchanged. As consequence, the camera moved and had to be re-aligned costing time. 
So far, they manage to tune satisfactory and beam is delivered to instruments since 7AM.

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- Not present.

DET:
- Nothing new on the AGIPD issue.

ITDM: 
- Nothing to report.

XRO:
- No deterioration of M1/SA1 since weekend.

LAS:
- PP-L SA1 AMPHOS service finished and in delivery to instruments.

UNSYS:
- Issue of last Monday is fixed.

SPB:
- Aligned beam with FXE together; beam is found at SPB/SFX and FXE.

FXE:
- Nothing to report.

MID:
- All is fine.

HED:
- Setup of beamtime going smooth; HIREX setup ongoing; tuning for HXRSS from 11AM.

SCS:
- Mechanical problem: vacuum chamber had to be vented and is now pumping down.
- Other work in parallel with samples is progressing.

SQS:
- Nothing to report.

SXP:
- Not present.