| 194 | 27 Jan 2021, 09:08 | Arvid Gebhardt | General | Information | Notes XO Integration Meeting 27.01.2021 | General Announcement: 
 - FFP2-Masks needs to be used in
 the experiment control hutches from now on
 |  | 
| 193 | 25 Jan 2021, 09:28 | Arvid Gebhardt | General | Information | Notes XO Integration Meeting 25.01.2021 | General Announcement: 
 - Test of automatic switch
 of power bridge is shifted to Feb.2: this
 |  | 
| 192 | 20 Jan 2021, 10:32 | Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 20.01.2021 | General Announcement: - A. Galler encourages attendants to pose
 questions on the authorities decision of
 |  | 
| 191 | 18 Jan 2021, 09:44 | Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 18.01.2021 | General Announcement: - Clarification on the definition of a critical
 work will be made this afternoon during a
 |  | 
| 190 | 13 Jan 2021, 10:04 | Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 13.01.2021 | General Announcement: - Test of power grid switching affecting
 green and orange power sockets: this was
 |  | 
| 189 | 11 Jan 2021, 10:54 | Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 11.01.2021 | General Announcement: - The Interlock test light in the hutches
 take place on January 13th. From tomorrow
 |  | 
| 188 | 06 Jan 2021, 09:05 | Arvid Gebhardt | General | Information | Notes XO Integration Meeting 06.01.2021 | General Announcement: 
 
 Due to work restrictions,
 some of shutdown activities will not end
 |  | 
| 187 | 16 Dec 2020, 09:11 | Arvid Gebhardt | General | Information | Notes XO Integration Meeting 16.12.2020 | General Announcement: 
 - Today is the last
 xo-integration meeting for this year. Xo
 |  | 
| 186 | 14 Dec 2020, 09:00 | Arvid Gebhardt | General | Information | Notes XO Integration Meeting 14.12.2020 | General Announcement: 
 - Please write to xo.planning,
 if something comes up with intteruption of
 |  | 
| 185 | 09 Dec 2020, 10:24 | Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 09.12.2020 | General Announcement: - Regarding the e-mail related to the general
 radiation training and procedure to deliver
 |  | 
| 184 | 07 Dec 2020, 11:08 | Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 07.12.2020 | General Announcement: -
 
 |  | 
| 183 | 02 Dec 2020, 10:21 | Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 02.12.2020 | General Announcement: - Laser interlocks activities in SA2 are
 delayed by two days. Therefore, activity
 |  | 
| 182 | 30 Nov 2020, 09:15 | Arvid Gebhardt | General | Information | Notes XO Integration Meeting 30.11.2020 | General Announcement: 
 - /
 
 CTRL:
 |  | 
| 181 | 25 Nov 2020, 10:14 | Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 25.11.2020 | General Announcement: - There is no UOM or XO Int. Meeting next
 Friday 27.11. We will continue with XO Int.
 |  | 
| 180 | 23 Nov 2020, 11:33 | Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 23.11.2020 | General Announcement: - An e-mail to the readiness and stgl mailing
 lists was sent regarding the calendar share
 |  | 
| 179 | 18 Nov 2020, 11:23 | Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 18.11.2020 | General Announcement: - Updates on the maintenance schedule will
 be made available in Alfresco. Guidelines
 |  | 
| 178 | 16 Nov 2020, 13:14 | Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 16.11.2020 | General Announcement: -
 
 |  | 
| 177 | 11 Nov 2020, 10:49 | Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 11.11.2020 | General Announcement: - XO is in contact with some groups regarding
 the winter shutdown, in order to get additional
 |  | 
| 176 | 10 Nov 2020, 10:53 | Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 09.11.2020 | General Announcement: - Maintenance summary task list has been
 made available at the S:\ folder as well
 |  | 
| 175 | 04 Nov 2020, 10:55 | Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 04.11.2020 | General Announcement: - XO reminds on the 4.5MHz operation: MXL
 tested a 12hs switching mode and this will
 |  |