Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther, Page 19 of 29  Not logged in ELOG logo
New entries since:Thu Jan 1 01:00:00 1970
ID Date Author Location Severity Subject Text Attachments
  214   12 Apr 2021, 14:40 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 12.04.2021General Announcement:
-  
  
  213   07 Apr 2021, 08:52 Andreas GallerGeneralInformationNotes XO Integration Meeting 07.04.2021

General Announcement:


.


CTRL:
  
  212   31 Mar 2021, 11:01 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 31.03.2021General Announcement:
- There is no UOM on next Friday April 02.
- The next XO Int. Meeting takes place on
  
  211   29 Mar 2021, 10:45 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 29.03.2021General Announcement:
- The UOM does not take place on next Friday
02.April.
  
  210   24 Mar 2021, 10:06 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 24.03.2021General Announcement:
-  
  
  209   22 Mar 2021, 10:14 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 22.03.2021General Announcement:
- The Covid-19 health task force is looking
into testing schemes to be employed on-site.
  
  208   17 Mar 2021, 09:15 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 17.03.2021General Announcement:

- nothing.

CTRL:
  
  207   15 Mar 2021, 11:26 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 15.03.2021General Announcement:
- Following Desy e-mail to all EUXFEL staff,
the emergency call system of the elevators
  
  206   10 Mar 2021, 09:20 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 10.03.2021General Announcement:

- nothing for now

CTRL:
  
  205   08 Mar 2021, 10:49 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 08.03.2021General Announcement:
- SPB/SFX will continue receiving beam this
week for commissioning.
  
  204   03 Mar 2021, 09:23 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 03.03.2021General Announcement:

- Hick-ups in the beam operation
are happening since last night. There is
  
  203   01 Mar 2021, 10:49 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 01.03.2021General Announcement:
- An e-mail from Steve Aplin informs on how
to contact the DATA operation center during
  
  202   24 Feb 2021, 09:03 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 24.02.2021General Announcement:

- Due to a failure alarm in the
smoke extraction system in XTD6+8+9, Desy
  
  201   22 Feb 2021, 10:14 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 22.02.2021General Announcement:
- In case someone has any remaining question
on the use of masks in the hutches please
  
  200   17 Feb 2021, 09:27 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 17.02.2021General Announcement:



CTRL:
  
  199   17 Feb 2021, 08:52 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 15.02.2021General Announcement:
- It had been a cooling water issue with
SA1 and SA3 PPLs on Saturday. Other groups
  
  198   10 Feb 2021, 09:20 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 10.02.2021General Announcement:

- Tunnel closure: it has been
decided both XTD6 and XTD9 will be searched
  
  197   08 Feb 2021, 08:30 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 08.02.2021General Announcement:

- XTD10 tunnel was closed
last Friday; XTD9 to be closed by end of
  
  196   03 Feb 2021, 09:26 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 03.02.2021General Announcement:

- Automatic Power Switch Testing
was done yesterday. The switches are working
  
  195   01 Feb 2021, 09:06 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 01.02.2021General Announcement:

- The test of the emergency automatic
switch of power bridge is scheduled for Tuesday, 2nd
  