Entry   Status and plans after SASE1 Status/SASE3 Readiness Meeting, posted by Tobias Haas on 01 Dec 2017, 11:42 
General:


User Operation ongoing until Tuesday 5 Dec 8 AM
CAS shall present a release plan for KARABO 2.2 next week
Dispatch
meetings shall move to a Mo/Wed 13:00 schedule starting next Wedneday 6 Dec


Instruments
Entry   Status after 9.30 dispatch meeting, posted by Adriano Violante on 29 Nov 2017, 09:56 
General


Preparation for the user's run starting tomorrow (until 7:00 Tuesday morning)


 

Instruments
Entry   Status and plans after SASE1 Status/SASE3 Readiness Meeting, posted by Tobias Haas on 24 Nov 2017, 13:15 
General


User operation ongoing in SPB/SFX and FXE


 

Instruments
Entry   Status and Plans after 0930 meeting, posted by Tobias Haas on 22 Nov 2017, 10:57 
General


User experiments resume tomorrow morning
Beam should be coming back late this morning or early this afternoon
After
the Operation Coordinaton Meeting H. Sinn, L. Samoylova and the instruments will align the mirrors
Beam to the instruments should be available
Entry   Status after 0930 meeting, posted by Tobias Haas on 20 Nov 2017, 10:21 
General


Intensity and availability of beam was good over the weekend
Large drifts and jitter were observed that are significantly
higher than previously
Beam has two horizontal lobes as if it is too large for the mirrors


Instruments
Entry   Status and plans after SASE1 Status/SASE3 Readiness Meeting, posted by Tobias Haas on 17 Nov 2017, 17:14 
General


Beam is back with good intensity (up to 1 mJ) 
Next user period starts on  23 Nov
Time between now and
then should be used to optimize FEL, beam lines and Instruments


Instruments
Entry   Status after 0930 meeting, posted by Tobias Haas on 15 Nov 2017, 11:51 
Instruments


SPB:

Waiting for beam to come in a usable condition (500 uJ and pointing within aperture of optical elements)


FXE

Similar




AE


There was an interrupt of the vacuum loop in XTD2 due to a faulty pump controller. This was fixed by ZZ
Rotational SmarACT
Entry   Tunnel access schedule updated, posted by Gerd Wellenreuther on 14 Nov 2017, 11:05 
Dear all,

I received updates from DESY (M. Hüning) about how the access to the southern tunnels is being restricted in the next months, due to interlock
tests etc., and included it in the TAS. Please check, if you have work to be done in these tunnels:
Entry   Status after 9.30 dispatch meeting, posted by Adriano Violante on 13 Nov 2017, 09:45 
General


No user operation.
During the week end the accelerator was not able to deliver reliable and stable beam for the user
operation.
The M2 mirror bender stopped working on Saturday morning and had to be replaced. The mirror and blender were replaced as a whole
Entry   Status and plans after SASE1 Status/SASE3 Readiness Meeting, posted by Tobias Haas on 10 Nov 2017, 11:46 
General


User operation is delayed by 48h due to rocky startup of FEL.
FEL still has not reached acceptable levels of stability and
power


Instruments
Entry   Status after 0930 meeting, posted by Tobias Haas on 09 Nov 2017, 13:21 
General


There is currently no beam less than 24h before user operation is supposed to start in SPB
The affects everybody (Instruments,
Detector, Laser 
Entry   Status after 0930 meeting, posted by Tobias Haas on 06 Nov 2017, 14:13 
General


Recomissioning of the FEL has been bumpy and up to this point only very weak lasing could be achieved. 
So far SPB had
only little beam and FXE had no beam at all. Both instruments state that the commissioning time for the up coming user run is insufficient


Instruments
Entry   Tunnel access schedule updated, posted by Gerd Wellenreuther on 06 Nov 2017, 13:58 
Dear all,

I updated the TAS to include the upcoming user runs up to and including the winter shutdown. As you can see, there will only be access to the
XTDs in cases of urgency. In these cases, please contact Martin Dommach, Harald Sinn or Thomas Tschentscher.
Entry   WP74 OCD plan until next shutdown, posted by Jan Grünert on 04 Nov 2017, 03:28 WP74_OCD_Plan.xlsx
 
Entry   WP74 OCD contacts for this weekend, posted by Jan Grünert on 04 Nov 2017, 03:26 
4.11. from 08:00 until 5.11. 08:00 - Jan Gruenert by email (work mobile defect)

5.11. from 08:00 until 6.11. 08:00 - Naresh Kujala 9-6840 
Entry   Status and plans after SASE1 Status/SASE3 Readiness Meeting, posted by Tobias Haas on 03 Nov 2017, 15:06 
General


The rack layouts and rack placement were finalized during the PRR in August. The result is the basis of the network planning. The
network is currently being installed and will most likely be finished by the end of the year. Changes to the layout that affect the network planning are
Entry   Automatic logbooks for beamtimes, posted by Janusz Szuba on 02 Nov 2017, 10:09 
Hi

Logbooks for the first two upcoming proposals in FXE and SPB instruments have been set up and all missing users in the past 6 proposal have been
corrected. From now on, user registration is disabled, logbooks for next proposal will be set up automatically once the proposal info is migrated from
Entry   Status after 9.30 dispatch meeting, posted by Adriano Violante on 01 Nov 2017, 11:24 
Instruments


SPB:

When PLC loops are restarted, still many device parameters are not properly recovered. This generates a lot of work
for the team. Recently an entire day was lost.

The procedure now foresees a notice to the relevant group before each loop update. In particular,
Entry   Status and plans after SASE1 Status/SASE3 Readiness Meeting, posted by Tobias Haas on 27 Oct 2017, 11:38 
Instruments


SPB:

When PLC loops are restarted, still many device parameters are not properly recovered. This generates a lot of work
for the team. Recently an entire day was lost.

Answer from AE: The parameters are extracted by CAS using KARABO. It is possible that not
Entry   XTD10 closed and interlocked, posted by Tobias Haas on 26 Oct 2017, 17:34 
The SASE3 tunnel XTD10 was searched by Janni and her team and interlocked about one hour ago.

It is now almost ready for first lasing in SASE3:


The vacuum is completely connected and closed from V0 all the way to the end
All valves, pumps and gauges are included in