ID Date Authordown Location Severity Subject Text Attachments
  98   04 Apr 2017, 16:29 Tobias HaasGeneralInformationAccess to XTD2 and XTD9 is now possible Interlocks in the northern fan are broken!    
  99   04 Apr 2017, 16:31 Tobias HaasGeneralInformationMeeting at 17:00 should take place at 17:45since tunnel access is now possible    
  100   04 Apr 2017, 18:16 Tobias HaasGeneralInformationProgress on Vacuum LoopJ. Eidam, V. Bondor, T. Freyermuth checked
Ion pump controller settings in XTD2 and
XTD9.
  
  103   05 Apr 2017, 10:15 Tobias HaasGeneralInformationSchedule after 0930 MeetingTunnel
Open.
  
  107   05 Apr 2017, 16:40 Tobias HaasGeneralInformationDESY wants to close XTD2 & XTD4 over the weekend...I expect that some of us may need the weekend
as a reserve (e. g. mirror installation).
So we should probably say no. Let's discuss
  
  109   06 Apr 2017, 11:27 Tobias HaasGeneralInformationStatus and Schedule after 09:30 meeting Tunnel
Open.
  
  123   10 Apr 2017, 10:47 Tobias HaasGeneralInformationSchedule after 09:30 MeetingTunnel
Open.
  
  129   11 Apr 2017, 12:51 Tobias HaasGeneralInformationStatus after 0930 meetingTunnel   
  140   12 Apr 2017, 12:52 Tobias HaasGeneralInformationStatus and plans after 09:30 meeting Tunnel
Closed.
  
  142   13 Apr 2017, 12:07 Tobias HaasGeneralInformationStatus and Plans after 09:30 meeting Tunnel
Closed until approx 1300, Open over the Easter
  
  143   13 Apr 2017, 13:19 Tobias HaasGeneralInformationStatus Interlock Tests TodayRadiation Interlock Tests are finished.
Tunnels XTD9 and XTD10 up to the fence at
the dump can be accessed right now. Magnet
  
  144   13 Apr 2017, 14:09 Tobias HaasGeneralInformationInterlock tests are finished in Northern FanAll northern tunnels XTD2/4/9/10 are fully
accessible again! 
  
  148   18 Apr 2017, 13:06 Tobias HaasGeneralInformationStatus and Plans after 09:30 meetingXTD   
  149   18 Apr 2017, 13:21 Tobias HaasGeneralInformationKW16 Accelerator Plans    
  152   19 Apr 2017, 11:49 Tobias HaasGeneralInformationStatus and Plans after 09:30 meetingTunnels
XTD2 and XTD4 are closed, XTD9/10 remain
  
  153   20 Apr 2017, 10:25 Tobias HaasGeneralInformationStatus and Plans after 09:30 meeting Tunnels
XTD2 and XTD4 are closed, XTD9/10 remain
  
  154   20 Apr 2017, 17:18 Tobias HaasGeneralInformationMaintenance/Access in KW17 In KW17 there will be NO maintenance
day on Tuesday (25.04.) 

 
  
  165   24 Apr 2017, 11:08 Tobias HaasGeneralInformationStatus and Plans after 09:30 meeting 
  
  176   26 Apr 2017, 17:48 Tobias HaasGeneralInformationAccess XTD2 tomorrowI added the requests that I was made aware
of to the list of access requests for tomorrow.
While the interlock in XTD2 will be broken
  
  183   27 Apr 2017, 15:11 Tobias HaasGeneralInformationStatus and Plans after 09:30 meeting XTDs
Info:
  