Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 19 of 30  Not logged in ELOG logo
New entries since:Thu Jan 1 01:00:00 1970
ID Date Author Location Severitydown Subject Text Attachments
  375   04 Sep 2017, 10:39 Tobias HaasGeneralInformationStatus after 0930 meetingSPB


Demo experiment done last
week
Flat fields taken with AGIPD
  
  376   04 Sep 2017, 12:03 Tobias HaasGeneralInformationStatus after 0930 meetingJust to clarify:


Tunnel and SPB are in different
Karabo Topics. It should not be a problem
  
  377   04 Sep 2017, 17:33 Gerd WellenreutherGeneralInformationTunnel access schedule updatedDear all,

I have updated the TAS with the
most recent information about Tuesday and
  
  378   06 Sep 2017, 11:04 Tobias HaasGeneralInformationStatus after 0930 meetingFXE


Still working on getting
the laser on the sample
Commissioning
  
  379   08 Sep 2017, 11:55 Gerd WellenreutherGeneralInformationTunnel access schedule updatedDear all,

I updated the TAS to incorporate
the newest dates for the October shutdown
  
  380   08 Sep 2017, 13:47 Tobias HaasGeneralInformationStatus and plans after SASE1/3 Readiness MeetingGeneral


User operation starts on
Thursday 14 September 08:00 in FXE
Instruments
  
  381   11 Sep 2017, 10:32 Tobias HaasGeneralInformationStatus and plans after 09:30 meetingGeneral


​More or less continuous
beam delivery over the weekend
Beam
  
  382   11 Sep 2017, 14:03 Gerd WellenreutherGeneralInformationTAS updatedDear all,

I updated the tunnel access schedule
to reflect the access to the XTDs tomorrow.
  
  383   11 Sep 2017, 14:04 Gerd WellenreutherGeneralInformationTAS updatedDear all,

I updated the tunnel access schedule
to reflect the access to the XTDs tomorrow.
  
  384   15 Sep 2017, 10:12 Tobias HaasGeneralInformationStatus and plans after SASE1 Status/SASE3 Readiness MeetingGeneral


User run is currently going
well. Thanks to everybody!
Preparations
  
  385   15 Sep 2017, 11:58 Tobias HaasGeneralInformationStatus and plans after SASE1 Status/SASE3 Readiness MeetingGeneral


User run is currently going
well. Thanks to everybody!
Preparations
  
  386   18 Sep 2017, 17:39 Gerd WellenreutherGeneralInformationTunnel access schedule updatedDear all,

XTD9 will be accessible tomorrow
until the afternoon, but access should be
  
  387   20 Sep 2017, 11:15 Tobias HaasGeneralInformationStatus and plans after 09:30 meetingGeneral


First user experiments
ended on Monday evening/Tuesday morning
They
  
  388   22 Sep 2017, 16:06 Gerd WellenreutherGeneralInformationStatus and plans after SASE1 Status/SASE3 Readiness MeetingGeneral


First users have done experiments
- despite the current problems it appears
  
  Draft   25 Sep 2017, 10:25 Monica ArestéGeneralInformationStatus and plans after SASE1/SASE3 Readiness MeetingGeneral

To stablish proper conditions for
the beam as it was before. On Wednesday to
  
  390   25 Sep 2017, 12:58 Monica ArestéGeneralInformationStatus and plans after SASE1/SASE3 Readiness meetingGeneral


Beam was lost due to incident
with electron beam hitting & damaging
  
  391   27 Sep 2017, 10:11 Monica ArestéGeneralInformationStatus and plans after SASE1/SASE3 Readiness meetingGeneral


T. Tschentscher inform
about Management Board priorities for the
  
  392   29 Sep 2017, 10:43 Gerd WellenreutherGeneralInformationStatus and plans after Readiness MeetingSPB (A. Mancuso): 

 

​Users
are in good shape
Beam operation
  
  393   29 Sep 2017, 11:03 Monica ArestéGeneralInformationSASE1/SASE3 Readiness meeting on Monday cancelled The SASE1/SASE3 Readiness meeting next
Monday is cancelled we will meet again on
Wednesday the 3rd of October.
  
  394   29 Sep 2017, 11:09 Monica ArestéGeneralInformationSASE1/SASE3 Readiness meeting on Monday cancelled Correction: We will meet again on Wednesday
the 4th of October.

  
ELOG V3.1.4-7c3fd00