Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 19 of 30  Not logged in ELOG logo
ID Date Author Location Severitydown Subject Text Attachments
  375   04 Sep 2017, 10:39 Tobias HaasGeneralInformationStatus after 0930 meetingSPB


Demo experiment done last
week
Flat fields taken with AGIPD
  
  376   04 Sep 2017, 12:03 Tobias HaasGeneralInformationStatus after 0930 meetingJust to clarify:


Tunnel and SPB are in different
Karabo Topics. It should not be a problem
  
  377   04 Sep 2017, 17:33 Gerd WellenreutherGeneralInformationTunnel access schedule updatedDear all,

I have updated the TAS with the
most recent information about Tuesday and
  
  378   06 Sep 2017, 11:04 Tobias HaasGeneralInformationStatus after 0930 meetingFXE


Still working on getting
the laser on the sample
Commissioning
  
  379   08 Sep 2017, 11:55 Gerd WellenreutherGeneralInformationTunnel access schedule updatedDear all,

I updated the TAS to incorporate
the newest dates for the October shutdown
  
  380   08 Sep 2017, 13:47 Tobias HaasGeneralInformationStatus and plans after SASE1/3 Readiness MeetingGeneral


User operation starts on
Thursday 14 September 08:00 in FXE
Instruments
  
  381   11 Sep 2017, 10:32 Tobias HaasGeneralInformationStatus and plans after 09:30 meetingGeneral


​More or less continuous
beam delivery over the weekend
Beam
  
  382   11 Sep 2017, 14:03 Gerd WellenreutherGeneralInformationTAS updatedDear all,

I updated the tunnel access schedule
to reflect the access to the XTDs tomorrow.
  
  383   11 Sep 2017, 14:04 Gerd WellenreutherGeneralInformationTAS updatedDear all,

I updated the tunnel access schedule
to reflect the access to the XTDs tomorrow.
  
  384   15 Sep 2017, 10:12 Tobias HaasGeneralInformationStatus and plans after SASE1 Status/SASE3 Readiness MeetingGeneral


User run is currently going
well. Thanks to everybody!
Preparations
  
  385   15 Sep 2017, 11:58 Tobias HaasGeneralInformationStatus and plans after SASE1 Status/SASE3 Readiness MeetingGeneral


User run is currently going
well. Thanks to everybody!
Preparations
  
  386   18 Sep 2017, 17:39 Gerd WellenreutherGeneralInformationTunnel access schedule updatedDear all,

XTD9 will be accessible tomorrow
until the afternoon, but access should be
  
  387   20 Sep 2017, 11:15 Tobias HaasGeneralInformationStatus and plans after 09:30 meetingGeneral


First user experiments
ended on Monday evening/Tuesday morning
They
  
  388   22 Sep 2017, 16:06 Gerd WellenreutherGeneralInformationStatus and plans after SASE1 Status/SASE3 Readiness MeetingGeneral


First users have done experiments
- despite the current problems it appears
  
  Draft   25 Sep 2017, 10:25 Monica ArestéGeneralInformationStatus and plans after SASE1/SASE3 Readiness MeetingGeneral

To stablish proper conditions for
the beam as it was before. On Wednesday to
  
  390   25 Sep 2017, 12:58 Monica ArestéGeneralInformationStatus and plans after SASE1/SASE3 Readiness meetingGeneral


Beam was lost due to incident
with electron beam hitting & damaging
  
  391   27 Sep 2017, 10:11 Monica ArestéGeneralInformationStatus and plans after SASE1/SASE3 Readiness meetingGeneral


T. Tschentscher inform
about Management Board priorities for the
  
  392   29 Sep 2017, 10:43 Gerd WellenreutherGeneralInformationStatus and plans after Readiness MeetingSPB (A. Mancuso): 

 

​Users
are in good shape
Beam operation
  
  393   29 Sep 2017, 11:03 Monica ArestéGeneralInformationSASE1/SASE3 Readiness meeting on Monday cancelled The SASE1/SASE3 Readiness meeting next
Monday is cancelled we will meet again on
Wednesday the 3rd of October.
  
  394   29 Sep 2017, 11:09 Monica ArestéGeneralInformationSASE1/SASE3 Readiness meeting on Monday cancelled Correction: We will meet again on Wednesday
the 4th of October.

  