Group Selection Page HELP Controls Group ITDM Vacuum WP78 SPB SQS XO ToBeMigrated2XWiki ToBeMigrated2GitlabPages ToBeMigratedByGroup Migrated2Zulip Archived2PDF not2MigrateOrArchive
SCS SXP Migrated2Zulip Photon Commissioning Team XRO DOC HED Migrated2Zulip WP74 MID PSPO_XO XO_Operation SQS Migrated2Zulip FXE Migrated2Zulip DET Sample Environment SPB Migrated2Zulip
SASE1 Status and SASE3 Readiness Technical integration and coordination
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 17 of 30  Not logged in ELOG logo
Entry   Status and plans after SASE1 Readiness Meeting, posted by Tobias Haas on 07 Jun 2017, 11:43 
 General

    Technicians from Actemium/JOWO arrived and
found that a lot more connectors than originally estimated need to be replaced
    Tests are finished in SPB Optics (40 connectors to be replaced)
Entry   Motion loop update, posted by NEREA JARDON on 07 Jun 2017, 12:00 
Dear all,
Due to some hardware changes needed in Motion loop, we will last a little bit more in the Motion update. You will loose communication but I will
come back when it is running again.
Entry   Motion loop update, posted by NEREA JARDON on 07 Jun 2017, 14:19 
Dear all,
Motion loop is up and running again, now with all the PBLMs configured.
Thank you,
Entry   XTD10 open , posted by Tobias Haas on 08 Jun 2017, 08:24 
 Author: limberg, tischhauser
due to the cryogenic failure we will open XTD10 from 9am for working.
at XTL and XTD2/4 ZZ is
possible for repairs/work.
Entry   XTD10 and XTD9 tunnel opening and closings, posted by Harald Sinn on 08 Jun 2017, 08:24 
Dear all, 
according to the DESY logbook XTD10 will be opened today again: See DESY logbook entry:
'due to the cryogenic failure we will open XTD10 from 9am for working.
Entry   Status and plans after SASE1 Readiness Meeting, posted by Monica Aresté on 09 Jun 2017, 12:41 







Normal
0


21


false
false
false
Entry   Information AE OCD June 9 -- 12, posted by Nicola Coppola on 09 Jun 2017, 19:09 
 AE/PLC on call service:
     Contact Person:
              Nicola Coppolla
Entry   Status and plans after SASE1 Readiness Meeting, posted by Monica Aresté on 12 Jun 2017, 10:55 
Tunnel's schedule:


    Monday 12th June:  XTD10 closed, XTD9 open
Entry   Tunnel's schedule, posted by Monica Aresté on 12 Jun 2017, 11:17 







Normal
0


21


false
false
false
Entry   Tunnel's schedule updated, posted by Monica Aresté on 12 Jun 2017, 13:21 
Last information is that tomorrow Fire brigade will come to inspect the tunnels, therefore all tunnels will be open from 7:00 to 15:00.
H. Sinn inform that XTD9 will not be searched until Wednesday morning.
Tunnel's schedule:
Entry   Status and plans after SASE1 Readiness Meeting, posted by Monica Aresté on 14 Jun 2017, 10:57 




General:




Entry   Status and plans after SASE1 Readiness Meeting, posted by Monica Aresté on 16 Jun 2017, 10:18 Radiation_Measurments_for_Commissioning.pptx20170615-Components-Detectors.xlsx

 
  
 

 
  Normal
  0
  
  
  21

 
  
  false
  false
Entry   WP74 OCD plan update, posted by Jan Grünert on 16 Jun 2017, 18:12 WP74-OCD-plan-6-8-2017.xlsx
The WP74 OCD plan is also published in WP74-Alfresco and sent by email to HR/WoCo/STGL.

Please note that this plan could be subject to
changes depending on the needs of the involved colleagues (e.g. if they want to swap OCD assignments).

The actually performed OCD-times are
reported to HR at the start of each following month.

Entry   Status and plans after SASE1 Readiness Meeting, posted by Monica Aresté on 19 Jun 2017, 10:17 
XTDs:


There are no major issues, commissioning works smoothly
this weekend.


Entry   Status and Plans after 09:30 meeting, posted by Tobias Haas on 21 Jun 2017, 10:21 
XTDs:


DESY requests the KMONO to be commissioned since the K Values of the undulators appear not to be as accurately calibrated as originally
advertised. Management decided to put KMONO at the top of the priority list for this reason. W. Freund should work together with Mahadi and Nerea on getting
Entry   Tunnel access schedule updated, posted by Gerd Wellenreuther on 21 Jun 2017, 14:13 
Dear all,

I extended the tunnel access schedule up to the beginning of the shutdown (3.7.). As always, you can find it under https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules

Access request to Harald Sinn. Works during the shutdown have to be reported to Harald Sinn and Dirk Nölle for scheduling.
Entry   Status and plans after SASE1 Readiness Meeting, posted by Tobias Haas on 23 Jun 2017, 11:11 
General


A low intensity beam is being put into the SASE1 intrument hutches in this order: SPB Optics, FXE Instrument, SPB Instrument
No
special precautions outside the hutches are needed due to the low intensity. 
The work will most likely not finish today. If necessary
Entry   Status and Plans after 09:30 meeting, posted by Tobias Haas on 26 Jun 2017, 10:57 
General:


​Beam was brought to all SASE1 hutches on Friday. Beam was available to both instruments splitting it with M3 until Sunday morning.
Afterwards SASE tuning was done and the beam should be back in the hutches some time today. Beam operation will continue this week with very low intensity.
Entry   Tunnel access schedule updated, posted by Gerd Wellenreuther on 26 Jun 2017, 15:52 
Dear all,

I tried to update the TAS to include the times for each XTD during the shutdown-week at the beginning of July. It is currently not entirely clear
when XTD9 and XTD10 will be searched, and as always this is subject to change...
Entry   Tunnel access schedule updated, posted by Gerd Wellenreuther on 27 Jun 2017, 10:26 


Dear all,

according to Dirk Nölle access to XTD4 during the shutdown will be extended until Thursday.
ELOG V3.1.4-7c3fd00