Entry   Motion loop, posted by NEREA JARDON on 12 May 2017, 09:23 
Dear all,
Due to local test needed in Rack 1.18 for the Motion loop, the loop will be interrupted only in Rack 1.18 XTD9 from now till the people in the
Tunnel finish the tests. It will not affect any other part of the Motion loop.
Entry   Motion loop, posted by NEREA JARDON on 16 May 2017, 13:50 
Dear all,
Due to local test needed in Rack 1.18 for the Motion loop, it  will be interrupted only in Rack 1.18 XTD9 from now till tests finish. It will not
affect any other part of the  Motion loop.
Entry   Access to tunnels updated, posted by Gerd Wellenreuther on 15 Jun 2017, 12:18 
XTD9 will be open until Friday this week 13:30. Check https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules
Entry   Access to tunnels updated, posted by Gerd Wellenreuther on 19 Jun 2017, 16:55 
Tunnel access schedule has been updated, access for XTD9 on Wednesday from 7-14:00 is now for granted.

https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules
Entry   Motion loop, posted by NEREA JARDON on 04 Jul 2017, 09:41 
Dear all,

Today we are planning to integrate part of Hirex motors into the Motion loop of SASE1. Therefore, the loop will be break, so you will loose communication
with whole XTD9 Motion part. I will back again to you when we are done,
Entry   Tunnel access schedule updated, posted by Gerd Wellenreuther on 06 Jul 2017, 08:51 
Dear all,

access to XTD9 has been extended until the Friday the 14.7. 14:00. Tunnel access schedule has been updated:

TAS
Entry   Vacuum Loop in XTD9, posted by NEREA JARDON on 13 Jul 2017, 10:27 
Dear all,

One power supply needs to be changed in SASE1 XTD9 rack 1.12 tomorrow and it's related to the Vacuum loop. Denis Finze will do this change
tomorrow morning, but we have to make sure before that we have all the equipments after this rack 1.12 in safe state (most concerning part, XGM in XTD9).
Entry   Fast Valves in XTD9, posted by Martin Dommach on 14 Jul 2017, 12:44 
Dear all,

the fast valves in XTD9 were causing some trouble. From time to time they collect some electrical noise what triggers the valve. The pressure
reading on the valve controller then shows oscillations of up to 10^-5 mbar, while the pressure around the fast valve gauges in the beamline is in the
Entry   Fast valves in XTD9, posted by Martin Dommach on 26 Jul 2017, 18:04 
Dear all,

the problem with the fast valves XTD9 tripping randomly is still not fully understood but we exchanged the controllers for both valves and they
now seem to be stable. The valves are set back to active mode again with 1*10^-6 mbar trigger level while vacuum pressure at the sensors is around 1*10^-8
Entry   Current PLC-Karabo Conflict, posted by Alessandro Silenzi on 03 Nov 2016, 12:58 
Tobias Freyermuth and me worked on the system and as of 
Entry   overview of required racks, posted by Sabine Cunis on 03 Nov 2016, 17:00 VCCT_Rack_1p06_b.jpgVCCT_Rack_1p07_b.jpg
just for reference ... here are pictures and schematics of the racks which are involved in the current commissioning.
Entry   Karabo Installation back to normal, posted by Alessandro Silenzi on 07 Nov 2016, 19:15 OK.pnginterlocked.pngbackToNormal.pngafteron.png
 Karabo to PLC communication has been tested successfully in the SA1 Vacuum installation.
in attachment:
OK.png -> Initial Status, all OK
Entry   new components list , posted by Sabine Cunis on 02 Dec 2016, 11:43 
please find the new (extended) components list under the old link given in the minutes  http://tinyurl.com/zn7otsa
,
and check whether all components are included and charakterized by the correct data.
Entry   VCTF-list updated, posted by Sabine Cunis on 09 Jan 2017, 10:47 
The VCTF-components-list 
has been updated. Labels on components, as far as visible, are in accordance with names in list.
... please, check for consistency, when naming and labeling XGM components!
Entry   STATUS UPDATE: XTD2 Differential Pumping Modules running under interlock control, posted by Tobias Haas on 24 Jan 2017, 08:17 
 Post on behalf of Raul Villanueva:
As we just finished the exhaustive testing and final adjustments of local
Entry   Modification of the vacuum PLC loop, posted by Tobias Freyermuth on 26 Jan 2017, 13:10 







Normal
0




false
false
false
Entry   XGM at XTD2 / issue with in-vacuum-resistor, posted by Tobias Haas on 26 Jan 2017, 17:02 
Post on behalf of Jan Grünert:

 
Entry   Component table update, posted by Thomas Tschentscher on 27 Jan 2017, 10:22 Components-XTD2-9.xlsx
 
Entry   Status of several XTD2 wiring tasks - on behalf of Bernard Baranasic, posted by Jan Grünert on 01 Feb 2017, 17:26 
Dear all,
 
today
I connected XGM Gas Supply to Beckhoff terminals in WP73 Vacuum crate in Rack 1.3.
Entry   WP74 components in XTD2 - electrical connections, posted by Bernard Baranasic on 02 Feb 2017, 18:29 
Status
of WP74 components testing and wiring this week:
 
On Monday we tested SR Imager and
K-Mono:
- issue with motor connect pinouts was discovered and I wanted to correct pinout today, but K-Mono and SR imager