Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 14 of 30  Not logged in ELOG logo
New entries since:Thu Jan 1 01:00:00 1970
ID Date Authordown Location Severity Subject Text Attachments
  294   19 Jun 2017, 10:17 Monica ArestéGeneralInformationStatus and plans after SASE1 Readiness MeetingXTDs:


  
  352   02 Aug 2017, 10:17 Monica ArestéGeneralInformationStatus after 9:30 dispatch MeetingGeneral



This Thursday the
radiation test in D.05 (FXE) will be performed
  
  356   07 Aug 2017, 12:45 Monica ArestéGeneralInformationStatus after 9:30 disptach meetingGeneral



The Radiation measurement
test will be postponed until the beam reach
  
  372   30 Aug 2017, 09:53 Monica ArestéGeneralInformationStatus and plans after SASE1/3 Readiness Meeting
 

 
 

 
  Normal
  
  390   25 Sep 2017, 12:58 Monica ArestéGeneralInformationStatus and plans after SASE1/SASE3 Readiness meetingGeneral


Beam was lost due to incident
with electron beam hitting & damaging
  
  391   27 Sep 2017, 10:11 Monica ArestéGeneralInformationStatus and plans after SASE1/SASE3 Readiness meetingGeneral


T. Tschentscher inform
about Management Board priorities for the
  
  393   29 Sep 2017, 11:03 Monica ArestéGeneralInformationSASE1/SASE3 Readiness meeting on Monday cancelled The SASE1/SASE3 Readiness meeting next
Monday is cancelled we will meet again on
Wednesday the 3rd of October.
  
  394   29 Sep 2017, 11:09 Monica ArestéGeneralInformationSASE1/SASE3 Readiness meeting on Monday cancelled Correction: We will meet again on Wednesday
the 4th of October.

  
  397   04 Oct 2017, 12:10 Monica ArestéGeneralInformationStatus and plans after Readiness MeetingGeneral:

Reminder to all the groups to provide
the shutdown task list today afternoon to
 Shut_down_task_list.xlsx 
  437   08 Jan 2018, 09:50 Monica ArestéGeneralInformationReminder Readiness meeting today at 13:00Dear all,

This is a reminder to inform you
that Readiness meeting will resume today
  
  438   08 Jan 2018, 13:47 Monica ArestéGeneralInformationStatus and plans after Readiness MeetingPSPO: 

- G. Wellenreuther
inform that DESY is commissioning a new gun
  
  441   10 Jan 2018, 13:22 Monica ArestéGeneralInformationStatus and plans after Readiness meetingPSPO:

- G.Wellenreuther inform that MKK
is planning to test the Umschaltautomatik,
  
  480   26 Feb 2018, 12:09 Monica ArestéGeneralInformationStatus report after dispatch meeting 26.02SPB:


Ion pumps running in the
Mirror chamber.
Starting test
  
  Draft   25 Sep 2017, 10:25 Monica ArestéGeneralInformationStatus and plans after SASE1/SASE3 Readiness MeetingGeneral

To stablish proper conditions for
the beam as it was before. On Wednesday to
  
  51   24 Feb 2017, 15:14 Martin DommachXTD9Informationwork on FXE distribution mirror chamberDear all,
on Monday, 27th in the morning we
will start with preparation work for the
  
  52   24 Feb 2017, 15:15 Martin DommachXTD9Informationwork on FXE distribution mirror chamberDear all,
on Monday, 27th in the morning we
will start with preparation work for the
  
  334   14 Jul 2017, 12:44 Martin DommachXTD9ProblemFast Valves in XTD9Dear all,

the fast valves in XTD9 were causing
some trouble. From time to time they collect
  
  346   26 Jul 2017, 18:04 Martin DommachXTD9InformationFast valves in XTD9Dear all,

the problem with the fast valves
  
  440   09 Jan 2018, 10:32 Martin DommachGeneralProblemShutdown of compressed air distribution in XTDs todayDear all,

we got the information from MKK,
that they have to fix a leak in the main
  
  462   29 Jan 2018, 10:32 Martin DommachXTD10Informationclosing of XTD10 shifted to WednesdayDear all,

the closing of the XTD10 tunnel
is shifted to Wednesday (January 31st.) at
  
ELOG V3.1.4-7c3fd00