Group Selection Page
HELP
Controls Group
ITDM
Vacuum
WP78
FXE
SPB
HED
SQS
SXP
Sample Environment
PSPO
XO
TS
Migrated2Zulip
Archived2GitlabPages
Archived2PDF
MigratedByGroup
|
|
SCS
Photon Commissioning Team
XRO
DOC
WP74
MID
XO_mig
XO_Operation
SQS Migrated2Zulip
DET
|
|
Technical integration and coordination
|
| Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
 |
|
|
Message ID: 93
Entry time: 18 Dec 2019, 10:06
|
| Author: |
Adriano Violante |
| Location: |
General |
| Severity: |
Information |
| Subject: |
Report after tech. Int. meeting 09.30 |
|
|
MID:
- SDL tests ongoing. Important motors have been tested. Alignment of the mechanics with the alignment laser ongoing. Will be pumped over Christmas.
EEE:
- uTCA puppet migration: Instr. done. Tunnels and balconies probably will be updated at the beginning of next year.
- SASE2 EPS loop will be updated probably today.
- SPB/SFX is getting a new CPU.
- Migration to MC2 motors has been agreed with controls, XRO, XPD. in XTD 6 XPD the upgrade will be done in KW2. For the rest a plan has to be made.
ITDM
- Meeting this week ITDM/EEE/TS to discuss how to mitigate issues caused by accidents (e.g. cooling water interruption caused by power cut).
Controls:
- CY sent a mail several weeks ago to XO and the DH. The topic is emergency procedures during Christmas. No reply. CY announces that in the period 23.12-07.01 the Controls OCDs would not be available.
AoB
- No dispatch meeting on 06.01. Next meeting will be the Technical Integration one on 08.01.
|