  640   25 Aug 2025, 09:28 Andreas GallerGeneralInformationNotes XO Integration Meeting 25.08.2025General Announcement:


Martin Doering

XTD6
today maintenance of cooling water pumps
  
  641   27 Aug 2025, 09:30 Andreas GallerGeneralInformationNotes XO Integration Meeting 27.08.2025General Announcement:


Martin shows the preview
for cw36,  

Implementation
  
  1   30 Jan 2019, 11:26 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 30.01.19 SPB/SFX


Planned for the next 2
weeks

AGIPD commissioning and
  
  2   01 Feb 2019, 12:49 Adriano ViolanteGeneralInformationReport after dispatch meeting 09.00SPB/SFX


Open AGIPD wing. Next 3
days are needed for fixing purposes.


FXE
  
  3   04 Feb 2019, 10:17 Adriano ViolanteGeneralInformationReport after dispatch meeting 09.30SPB/SFX


Waiting for the loop 12
to be running to start the commissioning
  
  4   06 Feb 2019, 11:13 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 06.02.19 SPB/SFX


AGIPD commissioning and
tests. ==> intervention on the wings is
  
  5   08 Feb 2019, 10:42 Adriano ViolanteGeneralInformationReport after dispatch meeting 09.00SPB/SFX


IT cables in D.23 were
re-measured yesterday. Waiting for the measurements.
  
  6   11 Feb 2019, 09:59 Adriano ViolanteGeneralInformationMInutes of the dispatch meeting 09.30SPB/SFX


Beam is back on Wed. night.
IT
cables in D.23 were re-measured on friday.
  
  7   13 Feb 2019, 10:59 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 13.02.19 SPB/SFX


CSS component commissioning.
RBean is discussing with AE. Concept and
  
  8   15 Feb 2019, 12:14 Adriano ViolanteGeneralInformationReport after dispatch meeting 09.00SPB/SFX


SPB requires the new trigger
solution to be implemented for AGIPD. This
  
  9   18 Feb 2019, 10:09 Adriano ViolanteGeneralInformationMinutes of the dispatch meeting 09.30SPB/SFX


Data aggregators were often
crashing during the WE and needed to be re
  
  10   20 Feb 2019, 11:16 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 20.02.19 SPB/SFX


CSS component commissioning.
Concept and implementation being finalized.==>
  
  11   22 Feb 2019, 12:36 Adriano ViolanteGeneralInformationMInutes of the dispatch meeting 09.00SPB/SFX


Pulse picker commissiong
- Issues concerning motors position and triggers
  
  12   25 Feb 2019, 09:52 Adriano ViolanteGeneralInformationMinutes of the dispatch meeting 09.30SPB/SFX


Change to the triggers
for  cameras is being discussed/implemented
  
  13   27 Feb 2019, 11:27 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 27.02.19 SPB/SFX


CSS component commissioning.
Concept and implementation finalized. EPLAN
  
  14   01 Mar 2019, 14:18 Adriano ViolanteGeneralInformationReport after dispatch meeting 09.00SPB/SFX


Today Loop 8 could be ready
(AE)
Agipd - visualization of
  
  15   04 Mar 2019, 10:38 Adriano ViolanteGeneralInformationMinutes of the dispatch meeting 09.30SPB/SFX


Ongoing discussions with
the support groups to organize the shutdown
  
  16   06 Mar 2019, 10:31 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 06.03.19 SPB/SFX


CSS component commissioning.
Concept and implementation finalized. EPLAN
  
  17   08 Mar 2019, 13:01 Adriano ViolanteGeneralInformationMinutes of the dispatch meeting 09.00SPB/SFX


Only minor issues being
addressed with the support groups.


FXE
  
  18   11 Mar 2019, 11:58 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30SPB/SFX


Experiments were succesfull
Calibration
pipeline has issues - being fixed
Detailed
  