Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther, Page 27 of 29  Not logged in ELOG logo
New entries since:Thu Jan 1 01:00:00 1970
ID Date Authordown Location Severity Subject Text Attachments
  36   26 Apr 2019, 12:28 Adriano ViolanteGeneralInformationReport after dispatch meeting 09.00SPB/SFX


IRD commissioning ongoing.
CRL
motors being tested. --> Mechanical issue
  
  37   29 Apr 2019, 10:04 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30SPB/SFX


IRDa commissioning
ongoing. Focus (<5um) in the second interaction
  
  38   03 May 2019, 14:07 Adriano ViolanteGeneralInformationReport after dispatch meeting 9:00SPB/SFX


IRDa commissioning
ongoing. First images have been taken with
  
  39   06 May 2019, 10:20 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30SPB/SFX


IRDa commissioning
ongoing. 
For this week AGIPD
  
  40   08 May 2019, 10:10 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 08.05.19 SPB/SFX


IRDa commissioning
ongoing. 
CSS. Limit switches
 Technical_Integration_Meeting_07.05.2019_-_Copy.pptx 
  41   10 May 2019, 10:52 Adriano ViolanteGeneralInformationReport after dispatch meeting 09.00SPB/SFX


IRDa commissioning
successful. A. Mancuso thanked all the people
  
  42   13 May 2019, 11:24 Adriano ViolanteGeneralInformationReport after dispatch meeting 09.30SPB/SFX


The gear ratio of the CSS
is unclear but this was already known and
  
  43   15 May 2019, 12:53 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 15.05.19 SPB/SFX


Nano KB mirrors and CSS
controls are OK
Digitizers have
  
  44   17 May 2019, 10:47 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.00SPB/SFX


ADC have been requested.
HW should be already installed (SPB to check).
  
  50   03 Jun 2019, 12:57 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30SPB/SFX


No major issues.


FXE


Tool to save motor positions
  
  52   07 Jun 2019, 11:53 Adriano ViolanteGeneralInformationReport after dispatch meeting 09.00FXE

SPB/SFX


few days of beamtime remaining,
  
  53   12 Jun 2019, 12:40 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 12.06.19 FXE

SPB/SFX

SCS
  
  54   14 Jun 2019, 10:47 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.00FXE

SPB/SFX


Getting ready for the shutdown.
  
  55   17 Jun 2019, 10:43 Adriano ViolanteGeneralInformationReport after dispatch meeting 09.30FXE


Floor is being re-worked.
Experiment hutch is not accessible until
  
  56   19 Jun 2019, 10:55 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 19.06.19 FXE

SPB/SFX


No major issues
Starting
  
  58   21 Jun 2019, 10:13 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.00FXE

​SPB/SFX


An AC device in the control
  
  59   24 Jun 2019, 09:53 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30FXE


CRLs mainteinance has been
completed.


​SPB/SFX
  
  60   26 Jun 2019, 10:22 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 26.06.19 XO

From now on A. Galler will join
the technical integration meeting. Therefore
  
  61   28 Jun 2019, 11:25 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.00XO

FXE

SPB/SFX
  
  62   01 Jul 2019, 10:07 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 09.30XO

FXE

SPB/SFX
  
ELOG V3.1.4-7c3fd00