ID |
Date |
Author |
Location |
Severity |
Subject |
574
|
16 Dec 2024, 09:44 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 16.12.2024 |
General Announcement:
- Next Wednesday it is the last XO Integration Meeting.
CTRL:
- Proceeding with Karabo update accordingly to the schedule.
DA:
- Nothing to report.
EEE:
- Issue with PLCs: on Friday the SA3 GATT Loop had issue; not fixed until now and loop will be brought back as soon as possible. Working is ongoing.
VAC:
- Nothing to report.
XPD:
- Proceeding with:
PES repair (today afternoon goes back to tunnel);
SA1 XFELO photon diode and grating was installed (electronics ADC card in the uTCA crate was not found in the crate and EEE was contacted – P. Gessler says a normal card will be installed in the coming
days).
DET:
- Nothing to report; tests to be performed after Karabo updates.
ITDM:
- SA1 control network switches updates were done (two switches not yet operational but Desy experts are working on it).
XRO:
- Progressing well with maintenance activities.
- Note to CTRL: today Karabo update in SA1, tomorrow in SA2 and Wednesday in SA3; Also EEE makes an update today in SA3.
LAS:
- Not present.
UNSYS:
- Nothing to report.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
- LPD burned cable and plugs: new connectors were ordered and will be replaced.
MID:
- All fine.
HED:
- Nothing to report.
SCS:
- Nothing to report.
SQS:
- Not present.
SXP:
- Not present. |
575
|
18 Dec 2024, 09:55 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 18.12.2024 |
General Announcement:
- This is the last XO Integration meeting this year.
- Wajid E. reminds attendance to write a ticket to CTRL when needed
CTRL:
- Done with SA1 and SA2 Karabo update; today proceeds the SA3 update, to be done by mid-late afternoon.
DA:
- Nothing to report.
EEE:
- uTCA updates have been performed in all SASEs; All system up and running.
- One small CPU needs manual intervention in tunnel.
- GATT loop update is up and running now.
- Wolfgang F. says the XFELO crate in SA1 has a crate not working; EEE is looking into it and CTRL is working on the new device. A ticket is created.
VAC:
- Ending most of tunnel activities (XTD2, XTD6 and XTD10) which progressed well. Seems to be all done by end of this week.
XPD:
- PES has been put back in tunnel: was connected and pumped; looks all fine so far and can be brought in operation.
- XFELO worked were done, just missing the ADC (see EEE report);
- Imagers work were done with good progress.
DET:
- Systems are put in Christmas break.
- Tests after Karabo and uTCA updates looked good.
ITDM:
- E-mail to xo-info was sent about office switches.
- Friday afternoon the XFEL gateway will be updated.
XRO:
- Finishing the last activities.
- Cameras in SA2 had problems (not know if hardware or software issues). In January new tests will be done. Maybe access could be required to check or fix at later
date.
LAS:
- Not present.
UNSYS:
- Nothing to report.
SPB:
- Nothing to report.
FXE:
- Not present.
MID:
- Nothing to report.
HED:
- Not present.
SCS:
- Nothing to report.
SQS:
- Not present.
SXP:
- Not present. |
576
|
06 Jan 2025, 09:42 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 06.01.2025 |
General Announcement:
- Interlock tests shall start tomorrow 07.01. In case of questions please do not hesitate in contacting XO.
- Eric Boyd says on Wednesday 10AM two hutches shall be interlocked for the tests (FXE exp. Hutch and MID optical hutch) for ~15 minutes. It shall work for both instruments.
- A. Silenzi reminds that a tentative schedule for the bring-up days was sent to the instruments and a feedback is expected to be returned by the end of today.
CTRL:
- Present but with technical difficulties; it shall be all fine for CTRL.
DA:
- Nothing to report.
EEE:
- Nothing to report.
VAC:
- Nothing to report.
XPD:
- No incoming calls last weeks for the XPD OCD.
DET:
- Nothing to report.
ITDM:
- Reminder that tomorrow Desy computer center will perform central maintenance; it shall not affect XFEL.
XRO:
- Nothing to report.
LAS:
- Not present.
UNSYS:
- Nothing to be reported.
SPB:
- All quiet.
FXE:
- Nothing to report.
MID:
- All fine at MID.
HED:
- All fine at HED.
SCS:
- Nothing to report.
SQS:
- Not present.
SXP:
- Not present. |
577
|
08 Jan 2025, 08:36 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 08.01.2025 |
General Announcement:
- Interlock tests are ongoing in tunnels and good progress has been made.
- Planning for the LIMP-2025: it has been worked on; currently there is not a detailed plan available as discussion for tasks is ongoing.
In case of questions or recommendations please do not hesitate in contacting XO. As soon as a timetable is available, it will be shared with everyone.
CTRL:
- Reminder that this week the camera acquisition system will be deployed to switch OFF them on Tuesdays 12:00, accordingly to the shared info in the e-mail.
Please contact CTRL for details, questions and suggestions.
DA:
- Al fine; nothing to report.
EEE:
- Situation in XTD2 rack 1.0: fast ADC does not work properly. To be followed up after the meeting.
VAC:
- Not present.
XPD:
- Nothing to report.
DET:
- Nothing to report. Restarting things prior bring-up dates.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Not present.
UNSYS:
- Everything is fine.
SPB:
- Not present.
FXE:
- Nothing to report.
MID:
- All fine at MID.
HED:
- All fine.
SCS:
- Nothing to report.
SQS:
- Not present.
SXP:
- Not present. |
579
|
15 Jan 2025, 09:40 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 15.01.2025 |
General Announcement:
- A. Galler announces that yesterday the cooling water of 20C was leaking. The reason is still to be found, as per e-mail from TS sent to the xo-info.
CTRL:
- Proceeding with updates and nothing to report.
DA:
- Ready for bring-up days.
EEE:
- Nothing to report.
VAC:
- Nothing to report.
XPD:
- Information: in XTD6 the PLC loop was repaired.
- XGMs are started (upstream ones).
- As PRC, J. Gruenert says a ZZ is ongoing in XTD10.
DET:
- Nothing to report; prepared for bring-up days.
ITDM:
- Nothing to report.
XRO:
- The XTD10 H-slit access is finished and cable connection is fixed;
- M. Vannoni sent the draft for the ramp-up plan during next week to the instruments.
LAS:
- Continuing with maintenance tasks.
UNSYS:
- Trying to understand why alignment quadrupoles were inserted in cell#24.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- Nothing to report.
HED:
- Not present.
SCS:
- Not present due to interlock tests.
SQS:
- Not present.
SXP:
- Not present. |
580
|
20 Jan 2025, 09:50 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 20.01.2025 |
General Announcement:
- E. Boyd reminds on the return of the beam shutter keys: actual plan is to return keys no later than Friday. The SA3 hutches are to be closed on the weekend.
- The User & Operation meeting will start from next week, Friday 31.01.
CTRL:
- Proceeding with bring up days.
DA:
- Busy with bring up days.
EEE:
- OCD was called due to rack 1.1 (SRA motors in SA1). ZZ was done yesterday and today another access at 10:00 to replace fuses.
VAC:
- Everything fine.
XPD:
- For XPD all is fine;
- As PRC Jan Gruenert reports on Friday problems with SRA slits in SA1 with motors in error and could not move. At some point it was moved but with wrong calibration;
On Sunday a fire alarm in rack 1.1 and extinguisher bottle was empty. No fire was found; Similar issue happened in November but this time the terminals seem to be OK - it seems to be only the fuse.
The gas bottle has to be exchanged and an access request is placed.
DET:
- Nothing to report; involved in bring-up days.
ITDM:
- An e-mail will be sent to announce on Thursday this week an upgrade to the Zulip backend of myLog to be done.
XRO:
- SA1 accident with SRA rack; nothing else to report.
LAS:
- Nothing to report.
UNSYS:
- Nothing to report.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- Busy at their satellite meeting.
HED:
- Busy with bring-up days;
- Power went down on Wednesday due to emergency OFF triggered by D3. XO is following up: no task that would trigger it was planned; mitigations will be done for the future.
SCS:
- Planned emergency OFF was successful and thanks to everyone who helped.
SQS:
- Not present.
SXP:
- Nothing to report. |
581
|
22 Jan 2025, 09:47 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 22.01.2025 |
General Announcement:
- Please call DOC number and get in touch with DRC is one needs to save data for any activity or face issues with CTRL and DAQ.
- User and Operation Meeting will start only next week 31.01.
CTRL:
- Nothing to report.
DA:
- Nothing to report.
EEE:
- Following up the issue with SRA in SA1: issues with temperature in motors (not sure if terminals or motor itself) still happening.
Another ZZ is being organized together with PRC for tomorrow for further investigation. Temperatures seem to be beyond 60C while in other tunnels is around 30C.
VAC:
- Everything fine for VAC.
- Will support with the SRA ZZ in tunnel tomorrow.
XPD:
- All fine for XPD.
- W. Freund adds to the SRA that it was moved yesterday to open for K-mono tests but it did not close again.
DET:
- Nothing to report; bring-up days ongoing - so far so good.
ITDM:
- Tomorrow Update on Zulip accordingly to the shared e-mail.
XRO:
- Not present.
LAS:
- Nothing to report.
UNSYS:
- Hardware: no problems;
- Small issues with software that are under investigation.
- K-mono measurements were not finished because of the issues with the SRA. Wolfgang F. adds the data was not saved; it is liked because bring-up days happens only today and no ticket for saving data was
submitted.
SPB:
- Monday the bring-up days happened with EEE and went quite well; On Friday bring-up days with DET and DA.
FXE:
- Nothing to report.
MID:
- Nothing to report.
HED:
- Not present as busy with Workshop.
SCS:
- Not present.
SQS:
- Not present.
SXP:
- Not present. |
582
|
27 Jan 2025, 09:59 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 27.01.2025 |
General Announcement:
- Maurizio Vannoni reports on behalf of XRO on the ramp-up activities over the weekend:
SA1 - positions of mirrors were found (post in Zulip) No major problems were found; Attenuators look fine;
SA2 - positions of mirrors were found and placed at commissioning logbook; one Attenuator had a problem and feedback from instruments will be asked;
Piezo in M1 was misbehaving and is repaired, but still to be set by XRO;
SA3 - positions were found and almost the same as before maintenance, small differences are set and shall be used as a guide when beam is taken;
A limit switch in M5 need a ZZ to be moved by 1mm; Horizontal SCS slit has relative encoders and work with 1um in accuracy. Soft-mono auto collimator is also commissioned (XRO can help if needed).
CTRL:
- Proceeding with bring-up days. All fine so far.
DA:
- Bring-up days: 5 out 7 days went well so far.
EEE:
- Nothing to report.
VAC:
- Nothing to report.
XPD:
- Taking beam this morning in SA3 for MCP detector.
- Last days: Spectrometers in SA1 and SA2 are up and running also calibrated with Mono; HXRSS setup was also commissioning (all motors working); All good from spectrometers (HIREX and PES).
- All fine for Imagers.
DET:
- Nothing to report.
ITDM:
- Reminder for update/service on Dcache tomorrow.
XRO:
- Couple of things that need access in XTD10 (stuck motor and a switch). Probably to be done on Tuesday morning.
- Motor/temperature issues with SRA SA1: Terminals were replaced and everything is fine.
LAS:
- Nothing to report.
UNSYS:
- Everything is fine;
- On Friday afternoon measurements with K-mono in SA1 and SA3 were done; analysis is ongoing.
SPB:
- Bring up days went fine.
FXE:
- Nothing to report.
MID:
- Nothing to report.
HED:
- Concluded bring up days. Thanks for the support.
SCS:
- Bring up day today; changed day plan due to a change with Gotthard-II that has to be fixed.
SQS:
- Nothing to report.
SXP:
- Bring up days: all good. |
583
|
29 Jan 2025, 09:50 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 29.01.2025 |
General Announcement:
- Steffen Hauf comments that DOC is active from today and also requests SXP and SCS to get in touch with DRC on needed nodes.
- UOM will restart next Friday at 9AM.
CTRL:
- Successful bring-up days were concluded.
DA:
- One last bring-up day to be done today.
EEE:
- Successful bring-up days.
VAC:
- All fine with VAC.
XPD:
- Concluded last action of XPD preparations. Small issues were addressed.
- ZZ in XTD6 yesterday: Shimadzu camera ZZ everything is fine by restarting PC.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- ZZ in XTD10: stuck pre-mirror in soft-mono due to Elmo controller; physical activity brought back.
- 1mm of limit switch of M5 SA3 is also corrected.
- ZZ in SA2: piezo cables of M1 was swapped and working back.
- Bring up days went fine yesterday.
LAS:
- Nothing to report.
UNSYS:
- Nothing to report.
SPB/SFX:
- PBLM was found in front of the beam; took a time to realize that, fixed by now.
FXE:
- Nothing to report.
MID:
- Issues with power slits at tunnel; but fix ongoing; not a show stopper.
SCS:
- Nothing to report.
SQS:
- Not present.
SXP:
- Getting beam today. |
584
|
03 Feb 2025, 09:39 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 03.02.2025 |
General Announcement:
- Experiment tuning week is ongoing; Two downtimes happened over the weekend due to 1. an electronic component part of quench circuit of a cold magnet in A20 (11hs) and 2. interlock issues at the injector
laser (3hs).
CTRL:
- Nothing to report.
DA:
- Nothing to report.
EEE:
- Nothing major to report.
VAC:
- Nothing to report.
XPD:
- Nothing to report;
- Naresh K. work went fine on Saturday (wavefront sensor at HED); program was cut because of short time due to downtime.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- No major problems; hiccups were investigated and there is nothing preventing operation.
LAS:
- Not present.
UNSYS:
- Nothing to report.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- Nothing to report.
HED:
- Not present.
SCS:
- Nothing to report.
SQS:
- Not present.
SXP:
- Not present. |
585
|
05 Feb 2025, 09:44 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 05.02.2025 |
General Announcement:
-
CTRL:
- Nothing to report.
DA:
- All quiet, good.
EEE:
- Nothing to report.
VAC:
- Nothing to report.
XPD:
- Nothing to report.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- Not present.
LAS:
- Report from SCS with double pulses coming from the laser: still in further investigation (may not be related to LAS, but with experimental setup).
UNSYS:
- Optimization of Circular polarization yesterday: went fine accordingly to expectations; after switching air coils all was in symmetric way; contrast is fine.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- All fine.
HED:
- Not present.
SCS:
- BKR was surprised that SCS gets beam.
- Problem with magnet chiller; internal valve can not be controlled and needs to be sent to the company for repair.
If another groups has a similar chiller to help SCS, please get in touch with Jan Torben.
SQS:
- Not present.
SXP:
- Not present. |
586
|
10 Feb 2025, 09:45 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 10.02.2025 |
General Announcement:
-
CTRL:
- Nothing to report.
DA:
- Nothing to report.
EEE:
- Anything to be report.
VAC:
- Nothing to report.
XPD:
- No issues.
DET:
- No major issues;
- Small ones to follow up: Jungfrau at MID (connection issues); SQS Gotthard 2 with weird data.
ITDM:
- Nothing to report.
XRO:
- Note to instruments: devices not used in operations are now locked. Please instruments contact XRO to unlock any instruments that may be needed.
LAS:
- Nothing to report.
UNSYS:
- Nothing to be reported.
SPB:
- Nothing to report.
FXE:
- Motor X3 of the XTD2 CRL went into the limit switch while moving in the wrong direction. CTRL will further investigate on Tuesday.
MID:
- Nothing to report.
HED:
- Nothing to report.
SCS:
- Nothing to report.
SQS:
- Not present.
SXP:
- Not present. |
587
|
12 Feb 2025, 09:53 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 12.02.2025 |
General Announcement:
- Delivery to instruments restarted this morning with good FEL performance (above the average). HXRSS in SA2 to be done during the day.
- As PRC, Maurizio Vannoni has nothing to report. So far so good.
CTRL:
- Instrument Control Integration team has a retreat today and tomorrow. So far only a "nothing to report" arrived to XO.
DA:
- Nothing to report.
EEE:
- Nothing to report.
VAC:
- Nothing to report; all fine.
XPD:
- Nothing to report.
DET:
- Nothing major;
- Jungfrau MID issue: looks to be permanently solved; further analysis on the reason behind is being done.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- It had to replace a uTCA in SA3 which was causing timing drifts; after replacement the restarted is ongoing and EEE helps. Hope to have delivery today by lunch time.
UNSYS:
- Nothing to report.
SPB:
- Nothing to report.
FXE:
- XTD2 CRL motion issue is solved: Nerea J. informs Leandro Z. did tests with SPB and motor is behaving properly.
- Issue with LPD appeared this morning (no further info on the issue details) but experts are contacted.
MID:
- Nothing to report.
HED:
- Nothing to report.
SCS:
- Thanks for EEE for recent help.
- Lasermet work is done accordingly to LAS.
SQS:
- Not present.
SXP:
- Nothing to report. |
588
|
17 Feb 2025, 09:39 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 17.02.2025 |
General Announcement:
-
CTRL:
- Small report: last week issue with bunch pattern configuration (Karabo reporting error). Seems to be obsolete properties removed from DOOCS were still in Karabo.
Valerii B. is working with DOOCS people and will be ready next days. Device is operational.
DA:
- Couple of calls involving setting data analysis tools.
EEE:
- Nothing to report.
VAC:
- Nothing to report.
XPD:
- All fine with XPD.
DET:
- From DOC: hiccups from one module at LPD. Right now all of them are working. Confirmed by FXE.
ITDM:
- Info today Maxwell servers will be reconfigured. It shall not disturb anyone.
XRO:
- Nothing to report, also from PRC side (Maurizio V.).
LAS:
- Issues with timing card update was solved by EEE.
UNSYS:
- Received 19 OCD calls due to stuck Apple-X undulators during SA3 scans. To understand software bug, one needs time to work with them.
SPB:
- Nothing to report.
FXE:
- Issues with LPD.
- Stuck motor that was not able to be reset (user motor 19). DOC is informed.
MID:
- All fine at MID.
HED:
- Not present.
SCS:
- Nothing to report.
SQS:
- Nothing to report.
SXP:
- Not present. |
592
|
03 Mar 2025, 09:48 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 03.03.2025 |
General Announcement:
- For next Friday 07.03 UOM a jitter report from instruments is expected together with presentations from groups using beam during this FD week.
CTRL:
- Nothing to report.
DA:
- Not present.
EEE:
- Nothing to report.
VAC:
- Issue with vacuum at HED Mono on Sunday morning 06:40AM: spike on vacuum happened (needs investigation with HED and EEE to further understand it). Recovered half way by HED colleagues.
Please do not hesitate in calling VAC-OCD in such situations. The V0 closed and was masked at MPS - now it is back unmasked (Desy-MXL will investigate).
XPD:
- Nothing to report.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Not present.
UNSYS:
- Nothing to be reported.
SPB:
- Energy drop on Saturday 02:20AM (bunches not lasing) was seen (fixed); vacuum spike in the chamber being investigated by SPB/SFX.
FXE:
- Nothing to report.
MID:
- Nothing to report.
HED:
- Apart of the VAC, all fine.
SCS:
- Discussion with BKR will be done.
SQS:
- Nothing to report.
SXP:
- Nothing to report. |
593
|
05 Mar 2025, 09:40 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 05.03.2025 |
General Announcement:
- On the LIMP-2025 (accordingly to an e-mail sent by M. Doering on 24.02): reminder that groups are requested to give a feedback on the task list for the LIMP until tomorrow, 06.March.
- Next Friday UOM will have presentations from selected FD activities and jitter reports from instruments.
CTRL:
- Nothing to report.
DA:
- Nothing to report.
EEE:
- Nothing to report.
VAC:
- Nothing to report.
XPD:
- Everything fine; busy being involved with FDs.
DET:
- Working on SPB replacing module for AGIPD; also busy with installation of AGIPD400K.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Not present.
UNSYS:
- Nothing to report.
SPB:
- Nothing apart of AGIPD intervention.
FXE:
- Nothing to report.
MID:
- Motor position issues while doing FD yesterday but experts are contacted.
HED:
- Nothing to report.
SCS:
- Jan Torben informs they are busy with installation; nothing to report.
SQS:
- Not present.
SXP:
- Not present. |
594
|
10 Mar 2025, 09:53 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 10.03.2025 |
General Announcement:
- From the DRC side, there is nothing particular to report.
- From the PRC side, nothing apart of what was reported below.
- XFELO studies: J. Gruenert says a successful time last week to bring all diagnostics in operation; for the first time full system was operational and detected; length of the cavity was measured;
it was a major step forward by having a signal that can be tuned or amplified.
CTRL:
- Nothing to report.
DA:
- Not present.
EEE:
- Nothing to report.
VAC:
- Friday issue with ion pump controller in XTD1: exchanged by VAC OCD and EEE colleagues in a ZZ.
- Sunday worked in XTD6 on the PBLM - tunnel is open and will be closed after lunch.
- Work ongoing to check piezo at the monochromators.
- No news on the Mono vacuum issue last week at HED (reason).
XPD:
- Blue week studies were successful (e.g. XFELO diagnostics (adjusted grating by ZZ on Friday))
DET:
- No major issue to report.
- SPB pre-intervention with AGIPD took place last week: replaced module and tested - at the moment module is operational;
however, connection was lost and needs time to evaluate if it will work in stable conditions. Intervention in summer will be later decided.
ITDM:
- Nothing to report.
XRO:
- During tunnel activity on Sunday also a temperature sensor was exchanged at the PBLM.
LAS:
- Not present.
UNSYS:
- Undulators are all operational.
- Apple-X studies last week: very successful; it reached rotation of microbunching, beam separation and measured contrast (90);
it was found the orbit before SA3 was not optimal and explain why the expected contrast was not reached; due to ZZ could not use full beamtime allocation; needs further development to improve contrast.
SPB:
- Pulse arrival time tests were done; an issue needs to be corrected, in touch with experts.
FXE:
- Issue with vacuum interlock (3 ions pumps): was a PLC issue resolved by EEE.
MID:
- Nothing to report.
HED:
- Nothing to report.
SCS:
- Nothing to report.
SQS:
- Nothing to report.
SXP:
- Commissioning last week went well; GATT could not be set on Friday; R. Villanueva comments the interlock is expected to be set and is a feature to avoid sudden jumps in pressure.
After stopping and restarting injection, this releases the interlock. |
595
|
12 Mar 2025, 09:36 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 12.03.2025 |
General Announcement:
- A. Galler informs the beam delivery start is delayed currently up to 15:00 due to difficulties in setting up the machine after the FD week.
- Couple of meetings regarding the LIMP are scheduled; plans have been distributed and will be shared during the meetings.
Please attend the meetings and if you want an invitation, contact Martin Doering. Also a DATA meeting on LIMP is happening today and please contact Patrick G., Steffen H. or Martin Doering for invitation.
CTRL:
- Nothing to report.
DA:
- Not present.
EEE:
- Nothing to report.
VAC:
- Nothing to report.
XPD:
- Nothing to report; all fine.
DET:
- Nothing major to report.
ITDM:
- Nothing to report.
XRO:
- Not present.
LAS:
- Nothing to report.
UNSYS:
- Nothing to report; everything fine.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- Nothing to report.
HED:
- Nothing to report.
SCS:
- Preparing for next weeks.
SQS:
- Nothing to report.
SXP:
- Nothing to report. |
596
|
17 Mar 2025, 09:36 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 17.03.2025 |
General Announcement:
- As DRC, Jola S.-D. says it was a quiet weekend.
CTRL:
- Nothing to report.
DA:
- Not present.
EEE:
- Nothing to report.
VAC:
- Nothing to report.
XPD:
- Nothing to report.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- Not present.
LAS:
- Not present.
UNSYS:
- Nothing to report; all fine.
SPB:
- Nothing to report; all good downstairs.
FXE:
- Nothing to report.
MID:
- Nothing to report.
HED:
- All fine at HED;
- Question: possibility to use beam parasitically tomorrow? A. Galler says one can always open the shutter if stability or tuning is not required.
Please contact the PRC for details on status or help with communication with BKR.
SCS:
- Not present.
SQS:
- Nothing to report.
SXP:
- Preparing for this week's experiment. |
597
|
19 Mar 2025, 09:35 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 19.03.2025 |
General Announcement:
- As PRC, A. Galler informs delivery has started this week and everything runs accordingly to the plan so far.
CTRL:
- Nothing to report.
DA:
- Not present.
EEE:
- Nothing to report.
VAC:
- Nothing to report.
XPD:
- Nothing to report; XGMs settings at SA1 are fine.
DET:
- Nothing to report.
ITDM:
- Not present.
XRO:
- Not present.
LAS:
- Nothing to report.
UNSYS:
- Everything fine.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- All fine at MID.
HED:
- Not present.
SCS:
- Nothing to report.
SQS:
- Not present.
SXP:
- Not present. |