Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 583     Entry time: 29 Jan 2025, 09:50
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 29.01.2025 
General Announcement:
- Steffen Hauf comments that DOC is active from today and also requests SXP and SCS to get in touch with DRC on needed nodes.
- UOM will restart next Friday at 9AM.

CTRL:
- Successful bring-up days were concluded.

DA:
- One last bring-up day to be done today.

EEE:
- Successful bring-up days.

VAC:
- All fine with VAC.

XPD:
- Concluded last action of XPD preparations. Small issues were addressed.
- ZZ in XTD6 yesterday: Shimadzu camera ZZ everything is fine by restarting PC.

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- ZZ in XTD10: stuck pre-mirror in soft-mono due to Elmo controller; physical activity brought back.
- 1mm of limit switch of M5 SA3 is also corrected.
- ZZ in SA2: piezo cables of M1 was swapped and working back.
- Bring up days went fine yesterday.

LAS:
- Nothing to report.

UNSYS:
- Nothing to report.

SPB/SFX: 
- PBLM was found in front of the beam; took a time to realize that, fixed by now.

FXE: 
- Nothing to report.

MID: 
- Issues with power slits at tunnel; but fix ongoing; not a show stopper.

SCS: 
- Nothing to report.

SQS:
- Not present.

SXP:
- Getting beam today.