Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther, Page 20 of 29  Not logged in ELOG logo
New entries since:Thu Jan 1 01:00:00 1970
ID Date Author Location Severity Subject
  194   27 Jan 2021, 09:08 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 27.01.2021

General Announcement:

- FFP2-Masks needs to be used in the experiment control hutches from now on regardless the number of people working in this areas. Regulations concerning the maximum number of staff in this areas remain the same.

- SASE1 Laser interlock upgrade originally scheduled for this week was postponed to next week. As soon as we receive the information on the new date, this will be communicated.

CTRL:

-   Intervention for the new scenes for the size of the labels was originally scheduled for yesterday. This was postponed as additional tests will be conducted in CTRL lab. A new date will be announced. 

- Panel topics: some old types doocs undulator devices were replaced for a single device. CTRL would like to remove the old ones in 2-3 weeks and kindly ask groups to inform if they are still in use. CTRL will send an e-mail on this subject.

DA:

- Nothing special to report.

EEE:

- Nothing special to report.

VAC:

- Still working in XTD10 and XTD6.

XPD:

- Tunnel works ongoing in XTD6 and XTD9, e.g. Shimadzu cameras / Imagers.

- EEE will need to have access at the end of the Imager intervention of XTD6.

DET:

- SPB Agipd: issues with new data acquisition system. It has been under work.

- This week DET plans to test the new Control fix medium gain to be used in user experiments.

ITDM:

- Nothing special to report.

XRO:

- Not present.

LAS:

- After SASE2 AMPHOS update: there are issues with the interlock

UNSYS:

- Unfortunately neither Desy or EuXFEL could grant access to the external company for the XTD4 tunnel cleaning. UNSYS is trying to organize themselves. PKG shall not be switched on before the clean is done.

SPB:

- Tests with DAQ of the AGIPD: new version has issues with data assignment of aggregated version. Currently AGIPD is back in the old version.

- Work of EEE with some crates of rack room.

FXE:

- Nothing special to report.

MID:

- all fine

HED:

- Nothing special to report.

SCS:

- Nothing special to report.

SQS:

- nothing to say

  193   25 Jan 2021, 09:28 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 25.01.2021

General Announcement:

- Test of automatic switch of power bridge is shifted to Feb.2: this affects all devices connected to orange or green power sockets (no power for few seconds/minute). General e-mail will be sent. Instruments will need to care for equipment which is connected to these sockets. This also affects the E0 level as well as office space in XHQ. Pease plug devices out or re-plug in other sockets.

  • The Covid-19 regulations continue valid. Only critical work in the XHEXP1 or tunnel activities shall take place.

- Work on the Soft Mono in XTD10 (SA3) takes place this week. XRO and ME asks everybody to do not move any motors in this device during the whole week.

CTRL:

- New Script to fix label issues in Karabo is ready and will be run today. An e-mail will be sent.

- ITDM and CTRL managed to get updated the “Read the docs”. It runs properly.

DA:

- Not present due to Satellite Workshop.

EEE:

- nothing to report

VAC:

- continuing with tunnel works

XPD:

- Ongoning with few tasks in the tunnel

DET:

- Not present

ITDM:

- nothing to report. Offline GPFS under work today: no Maxwell access during this time.

XRO:

- Not present. Please see general announcements on the Soft Mono.

LAS:

- Error with remote operation on mirrors for SA3/SQS PP-laser is found. A discussion after the meeting will take place between LAS and XO.

UNSYS:

- Nothing to report

SPB:

- Nothing to report

FXE:

- Nothing to add

MID:

- all fine

HED:

- Nothing to report

SCS:

- Nothing to report

SQS:

- Nothing to report

  192   20 Jan 2021, 10:32 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 20.01.2021
General Announcement:
- A. Galler encourages attendants to pose questions on the authorities decision of lockdown prolongation:  
Zunaira A. asks on travel restrictions between different cities: The commuting continues to be allowed, but not business travels; 
Adriano V. asks on business/meetings that were postponed (MID/AGIPD intervention) to February in order to plan work that will happen during the summer shutdown: Andreas 
G. says that if meeting can't be decided by Zoom, please send an e-mail to the task force with this enquire;
P. Gessler asks if EuXFEL considers to prepare documents (passport) again as in the first lockdown: A. Galler answers that this is in discussion but currently it will not 
to be implemented once no curfew is ongoing.

CTRL:
- Working with ITDM to get the Docs system running again.
- Working with EEE to have systems running by Friday.

DA:
- Nothing to report.

EEE:
- EEE reminds the update of SA1 motion loop (to allow work for Hirex) will take place today.

VAC:
- Not present.

XPD:
- Progressing with tunnel works, e.g. installation of viewports.
- A. Koch asks on the tunnel closure plans for XTD6 and XTD9. 
A. Galler says XTD9 will close around February 5th and for XTD6 one has to discuss with MXL-DESY on the possibility to keep it open for one week longer (until 12.02).

DET:
- Nothing to report on detector operation.

ITDM: 
- ITDM needs to finalize GPFS work which requires one day maintenance. The proposed date is next Monday 25.01. It means no access to data from Maxwell during the all day.
Instruments shall contact ITDM until tomorrow 21.01 in case of restrictions. 
- Tickets on e-mail lists (e.g. not authorized sending e-mails to some lists): ITDM is investigating.

XRO:
- XTD6 will have photon beam for recommissioning during the third week of February.

LAS:
- LAS asks instruments on their plans for when to use lasers (mid-February?). HED and MID confirm plans to have it by middle February. SQS, FXE and SCS will consult 
internally and let LAS known.

UNSYS:
- Two quad movers in SA2 are working again.
- Afterburner (winter shutdown tasks): Fire extinguishing system to be build; Cleaning the tunnel has to be made prior switching on the PKG.

SPB:
- Nothing to report.

FXE:
- Upgrade of Jungfrau and related work is postponed to Friday.

MID:
- All fine at MID.

HED:
- Nothing to report.

SCS:
- Nothing to report.

SQS:
- Nothing to report.
  191   18 Jan 2021, 09:44 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 18.01.2021
General Announcement:
- Clarification on the definition of a critical work will be made this afternoon during a discussion with group leaders and will be communicated to the staff. 
It includes also tasks carried out by two different groups.
- On Thursday there is going to be a switch of MPS components in the balcony room. 
This affects the timing signal distributed to XFEL, e.g. Lasers will not be able to follow timing. 
- Test of automatic switch of power bridge is shifted to Feb.2: this affects all devices connected to orange or green power sockets (no power for few seconds/minute).
General e-mail will be sent. Instruments will need to care for equipment which is connected to these sockets. 
This also affects the E0 level as well as office space in XHQ. Pease plug devices out or re-plug in other sockets.

CTRL:
- CTRL enquires ITDM on the issue with DOC (disk space full error). ITDM will take a look into it. 

DA:
- Getting prepared for involvements such as the data operation center.

EEE:
- Update of SA1 loop motion to take place by Wednesday. Affected staff is already informed.
- Firma Wille work on cabling is ongoing.

VAC:
- Continuing with works in the tunnels.

XPD:
- Tunnels works in XTD6 and XTD9 are ongoing. No incidents to report.

DET:
- Working on data analysis calibrations and installing the DOC.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- Regarding the Timing signal interruption mentioned in general announcements: it is not a problem as usually LAS keep the laser systems in the local timing during 
shutdown periods.
- Upgrading hardware that should be updated accordingly to the plans for the shutdown.

UNSYS:
- Works in tunnel are proceeding.
- Issues with SA2 cell 26 and cell27 were found and experts are going to the tunnel to solve it.

SPB:
- Working on making experimental plans for the Covid-19 beamtime.

FXE:
- Detectors: software upgrade taking place from today.

MID:
- All fine.

HED:
- Nothing to report.

SCS:
- Nothing to report.

SQS:
- Nothing to report.
  190   13 Jan 2021, 10:04 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 13.01.2021
General Announcement:
- Test of power grid switching affecting green and orange power sockets: this was planned for tomorrow 14.01 but it is not shifted to 02.02. 
For a second or so it may trigger power OFF in equipment. Groups have to identify devices that are connected to these sockets, for example at the instrument hutches. 
Devices shall be made safe. On the instruments rack room, equipment have two power supplies and therefore they shall be transparent to this intervention. 

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- Today EEE connects the new PLC for the AIBS project in SASE1 balcony room. One needs to restart momentarily EPS, SPB and FXE loops in SASE1 Tunnel after lunch. 
An e-mail was sent yesterday and clarified with instruments.

VAC:
- Tunnels are closed today for the interlock tests. XO thanks HED and FXE for making their hutches available.

XPD:
- Tomorrow XPD restarts with tunnel works, e.g., alignment of PES/XTD10 together with MEA.

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- Not present.

LAS:
- Proceeding with small steps but lasers are OFF.
- LAS waits for feedback from SRP and MB on the safety issue. Thomas Tschentscher will bring the safety issue to be discussed offline with MB, LAS and SRP.  
Zunaira A. questions if there were problems to re-start the Seeder Lock-in. Tomasz Z. says it is currently locked but after much additional work (no guarantee it can be 
locked again if Seeder is once more OFF). 

UNSYS:
- Working in the completion of SA3 undulator system.

SPB:
- Drilling ongoing: please keep in mind access to hutch may be affected.

FXE:
- Nothing to add.

MID:
- Wille Firma is working on cabling installation from today afternoon.

HED:
- Expecting Wille will be working from today but shall not interfere with Interlock tests. Zunaira A. says that interlock activities take around 20 minutes during this 
afternoon.

SCS:
- An external company is currently working onsite.

SQS:
- Nothing to report.
  189   11 Jan 2021, 10:54 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 11.01.2021
General Announcement:
- The Interlock test light in the hutches take place on January 13th. From tomorrow is starts in the tunnels. 
We understand no support from instruments are needed and we thank HED and FXE for making their hutches available for these tests.
- A Functional interlock test was planned for the end of January. This will be shifted to later point in time.
- XO states that planned maintenance tasks that are critical for operation can of course be performed onsite at the XFEL campus. 

CTRL:
- Updated the microTCA crates was done.
- CTRL is testing many other systems.

DA:
- Nothing general to report.

EEE:
- Critical task to do related to the AIBS CPU: one power bridge is missing. EEE has to check and may need to switch one PLC off to replace the power bridge.

VAC:
- Continuing with tunnel installation works: urgent tasks.

XPD:
- No incidents to report. Tunnel works are ongoing together with VAC.
- Jan G. informed that not all channels are working in fast-ADC devices. XPD has informed CTRL and Steffen H. says that CTRL and EEE will take a look together.

DET:
- LPD calibration pipeline work is ongoing.

ITDM: 
- Nothing to report.

XRO:
- Ion pumps in SA1/3 photon beam transport are running. Pressure is in the order of 10^-8mbar.
- SA3 mc2 library update: continuing with checks some small items will need to be commissioned with beam.

LAS:
- Nothing to report.

UNSYS:
- Finishing small tasks at SA3 tunnel.

SPB:
- Start planning the revised schedule.
- XO informs that the emergency power OFF test takes place today in SA1 instruments. 

FXE:
- Nothing to add.
- XO informs that the emergency power OFF test takes place today in SA1 instruments.

MID:
- All fine at MID.

HED:
- Nothing to report.

SCS:
- Not present.

SQS:
- Nothing to report.
  188   06 Jan 2021, 09:05 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 06.01.2021

General Announcement:

  • Due to work restrictions, some of shutdown activities will not end as planned in time. This leads to a prolongation of the start-up phase starting next week. It means re-start of Accelerator and South branch will be delayed by 2-4 days while the North branch by about 1 week.
  • The first 2 weeks of X-Ray delivery (2.2-15.2) will most likely be affected and photon delivery cannot be guaranteed into all beam-lines at all days. Some flexibility in planning for the commissioning tasks is expected. A detailed schedule for an upcoming week will be available on the week before, latest on Friday.
  • Sara C. asks if tunnel access is allowed during this week. F. Wolff-Fabris understands tunnels still can be accessed this week apart of Covid regulations (in the context of tunnel maintenance tasks that have to be performed while tunnels are open). T. Tschentscher says the understanding is from Robert F. guidelines e-mail are still valid for this week and really important tasks may be conducted – an e-mail to Robert and Nicole pointing the task with the need of access could be sent. Steve A. reported from today’s Covid taskforce meeting that the regulations of last corona email are still valid - if there are any question send an email to health@xfel.eu.

CTRL:

- Due to incompatibility discovered after last update on Dec. 23rd, CTRL would like to update files on all microTCAs before user operation (Karabo devices) mostly likely next Friday.

- A network maintenance was performed by Desy. Please inform CTRL if issues are encountered.

DA:

- nothing to report

EEE:

- Preparing to finish the cabling in HED and MID.

- Nothing to report from PLC side.

VAC:

- nothing to report - tunnel update tomorrow

XPD:

- XPD OCD put in place during Christmas break had no emergencies calls.

- XPD expect earliest work to take place on next week.

DET:

- nothing to report

ITDM:

- Desy network team would like to do a update of the control network routers tomorrow at 1300 -> email comes to readiness

XRO:

- Proceeding with activities from last days of last year.

- No major updates. Testing the SA3 MC2 library update.

LAS:

- Lasers are down.

- SA2 seeder that took longer than expected time to be back in December after the OFF request by LSO. Probably on next OFF mode LAS has to exchange it.

UNSYS:

- Minimum gaps for SASE3 Undulator system is 10mm. Other SASEs shall be defined after the middle plan scans.

- Apple-X major work from Unsys is done.  

- Quad movers are working remotely.

- Remaining task: connecting fire extinguisher system in one rack.

SPB:

- nothing to report

FXE:

- nothing to add

MID:

- nothing to report

HED:

- nothing to report

SCS:

- not present

SQS:

- A High voltage power supply with double-polarity was installed. It is the first time this is installed at SQS.

  187   16 Dec 2020, 09:11 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 16.12.2020

General Announcement:

- Today is the last xo-integration meeting for this year. Xo wants to thank everyone for the participating in this meeting series while sharing information and giving updates.

- The next XO Int. Meeting will happen on 04 January.

CTRL:

- Beckhoff MC2 motor upgrades at SA3 is ongoing.

DA:

- no updates

EEE:

- all SA2 fast ADC tasks have been concluded.

- Cabling in HED is ongoing; On MID will happen next year.

- AIBS control at SA1 balcony room installation starts today.

- Testing Mc2 motor configurations in tunnel devices.

VAC:

- Trying to finish main shutdown tasks: GATT, new mirror chamber in SA3/SXP, SA2 M3 mirror chamber.

- M3 chamber InGa is clean and ready to be pumped down.

- XGM/SA1: broken gate will be replaced this week or next.

- Some members of VAC group are working on site next week.

XPD:

- XGM SA2/XTD6 was moved 4mm and is still in alignment (no damage found) -> Jan G and Harald S. will have a look today onsite. M. Dommach says the differential pump could not move that far away due to bellows. 

- Installing of switches for HRIX will be most likely finished this month and some maybe in January.

DET:

- nothing to report.

ITDM:

- nothing today.

XRO:

- Not present.

LAS:

- Laser Hutches are locked (no access allowed) by Safety and LAS members can not continue the work in laser rooms. LAS maintenance tasks can not be finished and may be delayed over the end of shutdown.

- Emission of SASE2 Seeder laser was put in OFF yesterday due to inspection by SLSO. This means laser was OFF and there is no guarantee the PP-laser will be available in February, as they will not start mode-locking again after an Emission OFF. 

- Typically the Seeder lifetime is 3-4 years. Each time it is switched OFF it shortens the lifetime by half. If Seeder is included in the Interlock system, and taking into account the interlock trips 1 time per week or month (case of SASE3), the availability of PP-lasers is in risk and consequently the whole operation for instruments.

- Alignment lasers will be no longer provided. This also relates to the safety decision - such lasers are not allowed to be operated.

UNSYS:

- not present.

SPB:

- nothing to report: quiet days.

FXE:

- Craning activities over the hutches due to SXP construction still ongoing: not always a notice from construction workers.

MID:

- all fine.

HED:

- nothing to report.

SCS:

- not present.

SQS:

- nothing to report

  186   14 Dec 2020, 09:00 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 14.12.2020

General Announcement:

- Please write to xo.planning, if something comes up with intteruption of the maintenance due to new COVID-19 regulations.

CTRL:

- Migration of Beckhoff MC2 motors at SA3.

- Checking operation (e.g. soft mono at SA3).

- Final checks together with EEE.

DA:

- nothing to report

EEE:

- Migration at SA3 MC2 PLC´s.

- Fast ADC: SA2 maintenance starts.

- Cabling to be done in SQS today and tomorrow at HED.

- Crate was sent to Poland and shall arrive this week.

VAC:

- not present.

XPD:

- problem / alarm XGM at SASE1 / XTD2  - Needs to re-cable and install new gauges; requires VAC group.

- PES was re-installed in XTD10 and has been pumped down.

- DAQ test on friday - things are fine.

- XTD6 XGM alignment starts today - used to be confirmed with VAC.

DET:

- AGIPD intervention: need some internal coordination also with DASY groups - it will let XO know, if support needed

ITDM:

- XFEL gateway next Monday

- pre-anouncement: 90% of maxwell cluster update to be done on January 4/5. Communication to be send to Readiness mailing list.

XRO:

- Testing Controls in tunnel devices - needs to fix SA3 expected bugs.

- XTD10 close the vaccuum for M6 mirror chamber this week.

- XTD6 some problems with M3 mirror: to be pumped down this week and checked start of January.

LAS:

- Small delay on works at SA3, but no risk for users.

- Question from LAS: is the SA1 laser interlock update takes place?

- SA2 AMPHOS: external company is coming today

UNSYS:

- not present

SPB:

- nothing to report

FXE:

- nothing to report

MID:

- all fine

HED:

- don´t have anything

SCS:

- nothing to report

SQS:

- nothing to report

  185   09 Dec 2020, 10:24 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 09.12.2020
General Announcement:
- Regarding the e-mail related to the general radiation training and procedure to deliver a signed certificate, one can also send it by conventional post to Zunaira A.

CTRL:
- BKR machines has been updated to the new Karabo release.
- The Notification service update will follow form today.
- CTRL reminds on getting configuration from the timing feature on the GUI: right click on the device and then "get configuration". 
An e-mail with detailed instructions will be sent today.

DA:
- Nothing to report.

EEE:
- Fast electronics: SASE3 maintenance is finished; SA2 will follow.
- PLC side: SQS has some loops running but not all of them due to the cooling issue. SCS will get their loops soon running.
- Cabling works at FXE is completed; at HED is ongoing.

VAC:
- Not present due to tunnel activities.

XPD:
- XPD has completed PES beamtime at Petra. Would like to thank ITDM for the smooth work. XPD has collected data for over 300 runs.
- Today XPD brings back other PES to SA3 tunnel. There is an appointment with MEA and the plan is to connect to the beamline tomorrow together with VAC.
- A. Koch asks EEE at CTRL if DAQ tests on XPD tunnel devices can happen on Friday. 
Nerea J. points SA3 is not yet commissioned (has to check motors) but SA1 and SA2 can be done on Friday as it has only pending vacuum update. 
Steffen H. says that cameras can be tested in all 3 SASEs; connections shall be fine; requests a list of all cameras. 
Jan G. adds the idea is to verify the components can be operated and acquire data, following a test with XPD/ITDM. 
Steffen H. reminds that for testing the digitizers one has to re-start (faster ADC) the device server. 

DET:
- Not present.

ITDM: 
- Nothing to report.

XRO:
- Nothing present.

LAS:
- Lasers are on good track.
- Interlock tests: there was miscommunication. The SA2 AMPHOS is disassembled for maintenance and therefore the PP-laser test in SA2 is postponed to next week. 

UNSYS:
- Not present.

SPB:
- Nearly done with putting together the AGIPD. The Final test for DQA begin next week.
- Problem with timing but currently it has been running on local mode.

FXE:
- Not present.

MID:
- All fine at MID.

HED:
- Nothing to report.

SCS:
- Not present.

SQS:
- Nothing to report.
- SQS has ongoing work on Beckhoff crates.
  184   07 Dec 2020, 11:08 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 07.12.2020
General Announcement:
-	 

CTRL:
- Deployment updates: control network topics are through - SPB to be done in January.
- BKR and notification service updates to be deployed tomorrow or Wednesday.

DA:
- Nothing to report.

EEE:
- Cabling: finishing FXE and starting HED in the course of this week.
- Fast ADC: uTCA in SCS will be restarted for updated. SCS will contact Bruno F.
- SCS racks: cooling water is disconnected. Thomas Baumann informs TS needs to order cooling water lines and only in January will be connected. 
It is suggested to run with open doors in the meantime; Nerea J. says if one needs 1-2 loops then this is fine; Thomas B., Ulf B. and Nerea J. will discuss the details. 

VAC:
- Nothing to report.

XPD:
- PES installation will happen next Wednesday/Thursday. J. Laksman will contact VAC.
- Alarms in various XGM seem last week were due to updates. It is not a real problem.

DET:
- Nothing to report.

ITDM: 
- Lennart B. coordinates with instruments.
- Due to tomorrow timing update, the upgrade of DAQ on tunnels devices to start on Friday. Others will be contacted individually.
- Jan G. asks on issues of recording DAQ of PES during Petra ongoing beamtime. K. Wrona says it would be better to be informed in advance on the beamtime. 
The issue happens due to overload with a buggy script. If this script is not running, then the issue should not repeat again. 
At Petra it is used a standard control network which is different from the one at EuXFEL.

XRO:
- Not present.

LAS:
- All lasers are in local timing mode.
- LAS requests Bruno F. to have a crate update today as they have ongoing work in SA3. Bruno F. says the updates are agreed to be done today.
- Laser interlock upgrades: there is no news or known progress.

UNSYS:
- Not present.

SPB:
- Detector intervention ongoing and nearly finished. Test with DAQ and final test by end of this week. It is expected to be ready for Monday.

FXE:
- Elektro Wille firma working in the hutch.

MID:
- All fine at MID.

HED:
- Nothing to report.

SCS:
- Water leak last week was the only major event.

SQS:
- Nothing to add.
  183   02 Dec 2020, 10:21 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 02.12.2020
General Announcement:
- Laser interlocks activities in SA2 are delayed by two days. Therefore, activity in SA1 will start later.
- Gerd W. reports the cooling water in SA3 was refilled; air conditionings are running and maintenance on them are ongoing; 
next week temperature and humidity stability in other SASEs will be working; water leakage in SCS (yesterday) has been taken care by TS (crates are not damaged).

CTRL:
- Currently working in SASE2 deployment. SASE1 deployment happened yesterday and went relatively smooth. 
- Fast ADC cards in lasers stop working. CTRL will need to look with EEE.

DA:
- Works on updates are progressing/done.

EEE:
- MicroTCA SA1 update is done. Next week continues with SASE3 update.
- Cabling installation ongoing in FXE. It will be followed by SQS, SCS and MID.
- SA2 and SA1 motion loops updates to be done this week.
- Fast ADC issue with Lasers: Bruno F. says the installed update is the last version and Karabo has also to be updated to its last version also. CTRL and EEE will discuss 
together.

VAC:
- Maintenance activities are going as expected, some tasks are ahead of schedule.

XPD:
- SA3 PES is in the lab and being replaced parts. Plan is to test it today. XPD will discuss with VAC to install back this week or next week.
- XPD received a beamtime shift in PetraIII for the PES. This influences XPD schedule as many people are involved. Beamtime starts this Friday until next Wednesday.
- DAQ tests on Tuesday morning are scheduled. XPD will talk to ITDM to postpone to after the mentioned beamtime shift. 

DET:
- Nothing major to report. AGIPD Intervention: so far, so good.

ITDM: 
- Updates ongoing.

XRO:
- Not present.

LAS:
- ADC cards problems are communicated to CTRL. 
- Observed issues with trigger delay signal and it points to issues with recent update. Currently the lasers use local timing. CTRL will investigate if this can be the 
cause.

UNSYS:
- Not present.

SPB:
- Doing OK with AGIPD intervention: expected to be ready with final tests at start of the next week.

FXE:
- Cabling installation ongoing; Today there is the crane activity for SXP.

MID:
- All fine at MID.

HED:
- Everything is fine.

SCS:
- Not present.

SQS:
- Nothing to report.
  182   30 Nov 2020, 09:15 Arvid GebhardtGeneralInformationNotes XO Integration Meeting 30.11.2020

General Announcement:

- /

CTRL:

- Karabo 2.10 FXE was sucessful.

- go on with SPB and go on with other instruments. On Thurthday 3rd all SASE3 topics.

- Connenting Gui clients, if gateway there is no need to write a tiket this week. If local installation, please make an update.

- network upgrade takes place at SASE1 tomorrow. Karabo will be updated later.

DA:

- /

EEE:

- MircoTCA updates today and on going. Timing won´t be avaliable for short period.

VAC:

- /

XPD:

- /

DET:

- /

ITDM:

- Tomorrow network update SASE1, but there no Karbo update.

- at the beginning of January DESY-IT will do some work on data center / maxwell clust. interuptions are expected. Schedule is still be to expacted.

XRO:

- Not present.

LAS:

- Tests on the mircoTCA failt. More tests needs to be done.

- LAS request comunication from instruments go thru XO.

UNSYS:

- Not present.

SPB:

- Aigipd intervention is running well. To be tested by the end of this week.

FXE:

- cable installation on going.

MID:

- all fine

HED:

- /

SCS:

- Not present.

SQS:

- /

  181   25 Nov 2020, 10:14 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 25.11.2020
General Announcement:
- There is no UOM or XO Int. Meeting next Friday 27.11. We will continue with XO Int. Meeting next Monday 30.11.

CTRL:
- Karabo Deployment in FXE takes place today. Schedule for full Karabo deployment was sent to the Readiness mailing list.
- Two SA2/SA3 Beckhoff devices topics will be updated today (5-10 minutes downtime).

DA:
- No issues or announcement to report.

EEE:
- PLC side: tunnel updates to be started with CTRL.
- Change requests also to start today in a couple of instruments.

VAC:
- Not present.

XPD:
- PES/MEA: there are individual tasks ongoing.

DET:
- Nothing major to report. AGIPD intervention is goes faster than planned.

ITDM: 
- Offline storage update was done and is available since Tuesday.
- Online cluster update has started: SA1 already available since Tuesday. Today ITDM will finish SA2/SA3. Crosscheck and start DAQ will follow.

XRO:
- Not present.

LAS:
- Nothing special to report.

UNSYS:
- Not present.

SPB:
- AGIPD work is ongoing and fine.

FXE:
- Wille company is installing cables in the hutch.
- Issue with craning on SA3 / SXP activities above FXE area: FXE asks for coordination to avoid interrupting activities. 
Gerd W. says it shall not be a problem as crane will be used for few period. Martin K. will inform his phone number for arranging craning times.

MID:
- All fine at MID.

HED:
- All fine at HED.

SCS:
- Shutdown activities ongoing.
- Situation of JJ X-ray will be clarified by SCS staff. 

SQS:
- Nothing to report.
  180   23 Nov 2020, 11:33 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 23.11.2020
General Announcement:
- An e-mail to the readiness and stgl mailing lists was sent regarding the calendar share and updated task list. Please contact xo-planning@xfel.eu in case of any issue.
- Desy has made mandatory for the tunnel works the use a community mask all the time and a FFP2 mask if distance between two persons is less than 1.5m.

CTRL:
- CTRL sent requests to the DA colleagues. S. Hauf asks the colleagues to take a look and have a discussion afterwards. 
- Karabo deployment on FXE will take place on Wednesday. 
M. Turcato says one DET person must be back to work on that day to switch Detector off and on by again: Wed afternoon or Thursday morning it shall be OK.

DA:
- Nothing to report.

EEE:
- PLCs will start shutdown with planned activities on today and tomorrow in SA3 instruments.

VAC:
- Not present.

XPD:
- Plan for XGM/SCS is to keep it running (under vacuum). XPD reminds SCS people to keep XGM on vacuum. 

DET:
- AGIPD intervention: is progressing quite well and advancing. 
A. Violante says it is progressing faster than expected and many small issues were solved during the weekend; first quadrant was already re-mounted and tested. 
By the end of this week an update on time planning will be made. 

ITDM: 
- Today ITDM starts the update of offline storage system (unavailable all day).
- The update on the online cluster system will start today in SA1 and then SA2 and SA3. It will not be available until Wednesday.

XRO:
- Working on the winter shutdown.

LAS:
- Carrying on planned maintenance work.

UNSYS:
- Not present.

SPB:
- AGIPD intervention is going well and is under control.

FXE:
- Cabling works starting today in the hutch.
- A. Galler asks if calibration of LPD was done. D. Khakhulin mentions that the raw data was used and calibration constants were not used. 
M. Turcato says one has to discuss together with calibration team.

MID:
- All fine.

HED:
- Nothing to report.

SCS:
- Nothing to report.

SQS:
- Nothing to report.
  179   18 Nov 2020, 11:23 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 18.11.2020
General Announcement:
- Updates on the maintenance schedule will be made available in Alfresco. Guidelines in how to integrate calendars will be sent to readiness mailing list, for example.
- Please feel free to contact XO by to share any thoughts related to the Maintenance.

CTRL:
- Successful tests of HED pulser were done on Monday;
- CTRL is preparing Karabo 2.10 deployment: a schedule will be sent around per e-mail. FXE starts on 25/11. Remaining areas take place on Tue/Wed/Thu of week 49. 
SPB will be discussed later due to the AGIPD work.

DA:
- DA has received two messages from CTRL related to Karabo and data analysis deployment: first about deployment and second about bridge.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- XPD is involved on MID tests this week;
- Shimadzu camera tests/development is cancelled due to AGIPD intervention at SPB.

DET:
- Nothing to report.

ITDM: 
- Planning for next week maintenance and working with AGIPD/SPB intervention.

XRO:
- Nothing to report.

LAS:
- Nothing to report.

UNSYS:
- A problem with SA2/cell37 coupler is found and will be fixed during shutdown.

SPB:
- Work on AGIPD is going OK. It has been found the expected minor issues. SPB expects AGIPD experts on site.

FXE:
- Nothing to report.

MID:
- Fast-ADC issue is under investigations together with EEE/Bruno F.

HED:
- Nothing to report.

SCS:
- Not present.

SQS:
- Nothing to report.
  178   16 Nov 2020, 13:14 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 16.11.2020
General Announcement:
-	 

CTRL:
- Further improvements on the SA3 vacuum loop will continue during the shutdown.

DA:
- No issues to report.

EEE:
- 1 OCD call from SCS call related to PLC: hardware issue.
- Fast electronics side: MID timing system problem is still present. Frequency that this issue happens is reduced.
- For the Winter maintenance, EEE will ship some crates to Poland. Due to Covid-19 situation, only crates with non-critical changes for next run will be sent. EEE is in 
closed contacts with instruments.

VAC:
- 1 OCD during the weekend was related to GATT and promptly solved.

XPD:
- Nothing to report.

DET:
- Last Friday problem with offline jobs was solved (it had to be followed by IT).
- SPB activity for AGIPD baseline intervention/correction to start today.

ITDM: 
- Maintenance on the offline storage will happen next Monday 23.11. An e-mail was sent this morning. The system will be OFF and all data will not be accessible that day.
- ITDM will also start the maintenance of online cluster on 23.11. They will not be available until the end of maintenance (about 3 days).

XRO:
- Nothing to report.

LAS:
- OCD calls from SCS: 1. observed crystal degradation in SCS side; 2. laser pattern server could not be changed (LAS forward the message to CTRL).
- All other PP-lasers are fine.

UNSYS:
- BKR tested air coils in the last SA2 undulators cells for performing work on Wednesday for photon beam alignment (there was a problem with Cell37/SA2 not responding).

SPB:
- Instrument and beam delivery were running successfully last week;
- This week SPB starts working with AGIPD: one aim to work as fast as possible to finish before Christmas break.

FXE:
- D3 is currently preparing the tests.

MID:
- Continues to use beam this week for detector tests. 

HED:
- Tested AGIPD during last weekend. Currently HED is changing setup to use High Intensity laser this week.

SCS:
- Not present.

SQS:
- Nothing to report.
  177   11 Nov 2020, 10:49 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 11.11.2020
General Announcement:
- XO is in contact with some groups regarding the winter shutdown, in order to get additional information or solve potential conflicts. 
If there are any question, please contact us in this meeting or via e-mail.
- Steffen adds on the idea of using FXE for initial deployment of updated Karabo version. It will take place after 23/Nov.
- Jan asks how XO needs to be informed for tasks that groups deal with each other. A. Galler says XPD is on the list for setting a date to discuss this. 
Groups are encouraged to communicate with other support groups beforehand.

CTRL:
- Misbehaving timing server at MID yesterday was initially solved by EEE. EEE replaced the hardware of the timing system itself but problem continued. 
System seems now to be healthy but from time to time there are small timing interruptions. Investigation is ongoing and will be discussed in the digitizer meeting of Data 
department.
- One CTRL ticket on Doocs device at SCS: it was a problem with custom installation. CTRL asks to be informed in case groups have custom installations. This may pose a 
risk when deploying new updates.

DA:
- AGIPD train-ID issue: a small workaround until shutdown is in place. One has to set the individual channel and seems to be now working. Next intervention to take place 
during Winter maintenance time.

EEE:
- Nothing else to report aside of the MID timing system.

VAC:
- Nothing to report.

XPD:
- SA3 XGM was switched to Ne as requested by instruments.

DET:
- Preparation for activities on AGIPD at SPB/SFX during the winter time is ongoing.

ITDM: 
- Pre-announcement: at the start of the maintenance, ITDM has activity on the computer cluster. A separate announcement will be sent.

XRO:
- Nothing to report.

LAS:
- Nothing to report.

UNSYS:
- Nothing to report.

SPB:
- No issues to report.
- Intervention date of AGIPD: SPB requires due to highest priority work that between 16/11-18/12 no interruptions of electrical power or the need of EQP may happen. 

FXE:
- Crosstalk SA1/SA3 was not seen yesterday as SQS used only 1 bunch.

MID:
- Nothing to add besides what CTRL and EEE have mentioned.

HED:
- Next week HED does not use X-ray beam: commissioning of the high power laser and test of pulse on demand are planned. A. Galler says it pulse on demand was fixed by 
CTRLs and can be used. 
- Question on use of ADCs: Bruno says some trains will not be recorder or be repeated. This may be related to the timing issue like in MID. 
But data can be acquired. It is under investigation accordingly to Bruno, with CTRL, DA, ITDM.

SCS:
- Not present.

SQS:
- Nothing to report.
  176   10 Nov 2020, 10:53 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 09.11.2020
General Announcement:
- Maintenance summary task list has been made available at the S:\ folder as well as in the XO Alfresco page.

CTRL:
- On Thursday laser1 went down: error on deployment related to fix zero train ID.
- Lasers safety deployment is fixed.
- SA3 vac loop: progress was made and new version of Karabo needs re-start this morning.
- SA3 fixed MC2 motor issues. Coordinated with instruments to do tests today.

DA:
- 1 OCD was received and solved during the weekend.

EEE:
- Announces that on tomorrow's PBS there will be a EEE presentation on the Digitizer instruments.

VAC:
- Nothing to report.

XPD:
- No issues. The switch of XGM settings at different energies went well.

DET:
- Nothing to report.

ITDM: 
- Meeting with MID on train-ID is set. There is a mitigation error plan which will be implemented.

XRO:
- Nothing to report. Minor issues on CTRLs but are not stoppers.

LAS:
- PP-laser for SPB run was interrupted for 45 minutes.
- Issue with synchronization / motor becomes unstable, relating to motor slippage. Hardware will be replaced during the shutdown.

UNSYS:
- Nothing to report.

SPB:
- Finished user experiment: went OK but machine not very stable. Intensity and pointing very unstable. After beam losses timing came quite different. 
Data for pointing quantification to be analyzed.

FXE:
- Unstable beam the whole week. 
- Crosstalk between SA3 and SA1: sometimes BKR could fix/work on it, sometimes not. This happens when FXE runs at 150 bunches and SA3 varying 1-100. 
SA1 intensity goes down by factor 2.

MID:
- DET and ITDM contacted during the weekend.

HED:
- Not present.

SCS:
- Not present.

SQS:
- Crosstalk SA1/SA3: night shift crew said it is not a problem for next week if run without Interleaved.
  175   04 Nov 2020, 10:55 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 04.11.2020
General Announcement:
- XO reminds on the 4.5MHz operation: MXL tested a 12hs switching mode and this will be used along the week. 
The night shift operates at 4.5 MHz and day shift at 2.25MHz to avoid sending unnecessary bunches to the dumps.

CTRL:
- Issues with MC2 motors (bug in moving, mainly in SA3). CTRL has a fix but it is hard to find a proper time slot this week to apply it. The idea is to deploy next Monday 
only in SA3 first. 
If issues are found beforehand, please contact CTRL.
- SQS mentions a bug in the mirror observed yesterday which relates to the above described issue. SQS has to observe it to verify it moves all the way and then one can 
wait until Monday for the fix.

DA:
- Nothing to report.

EEE:
- Crate issue in SA2: it was not needed to exchange the crate. A reboot on Monday afternoon helped to bring system back. 
Crate works as normal. During winter shutdown EEE will replace crate and power modules.
- MID and LAS reported issues with train-ID / timing servers. Triggers have not been delivered in 10Hz. This is in discussion with DESY. 
One solution is an update of the DOOCS timing serves that do not show errors which does not interrupt timing servers. In MID this may be related to data recording. 
For the PP Laser further discuss with Desy colleagues will be made. This affects only MID because the use of old version of Doocs server. 
- MCP problems reported by XPD: mismatch on the firmware version and EEE plans to upgrade this week. 
- Preparation for the winter maintenance is ongoing and installations can start on 23/11.

VAC:
- VAC would like to thank EEE and CTRL for the SA3 loop vacuum fix.

XPD:
- XPD found another issue with MCP: wrong assigned triggers. A ticket will be created. 

DET:
- Update of MID AGIPD is still an issue but this is not critical at the moment.
- CTRL has accessed the LPD detector issue.

ITDM: 
- K. Wrona informs ITDM has the reservation of Maxwell for data analysis during next two weeks. 
The user groups have to be informed that one has to use Maxwell reservation to quick analyze data.

XRO:
- Nothing to report.

LAS:
- SA1 SPB PP-laser had to increase energy and is on work.
- SA2 PP-laser missing trigger from around 7PM yesterday. Laser went OFF due to this and luckily LAS was watching it and was able to switch ON quickly. LAS is in touch 
with EEE and Desy. 
A fallback solution could be to generate triggers by hardware but there is no progress from Desy side. LAS will prepare specifications for this module.

UNSYS:
- Small hiccup in one SA2 undulator that was remotely corrected.

SPB:
- Trying to align beam: SPB sees elliptical rings. Andreas G. suggests if this continues please communicate to the PRC.

FXE:
- No further information on issues with the LPD.

MID:
- Tomorrow it takes place the AGIPD train-ID meeting.

HED:
- Vacuum valves in differential pumping system were strangely closed on Friday 2AM. HED discovered this only yesterday. Pressure slowly went up. HED will further 
investigate.

SCS:
- Not present.

SQS:
- 4.5MHz operation had gun trips due to the overheating of the dump. 
F. Wolff-Fabris comments that was due to the radiation alarms on the dumps that removed beam permission by about one hour around 4AM.