Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 30 of 30  Not logged in ELOG logo
ID Date Author Location Severitydown Subject
  47   15 Feb 2017, 20:10 Alessandro SilenziGeneralFeedbackCurrent Vacuum Status

The PLC is still not completely error free.

It is considerably better performing than the last days:

the current average pressure as measured by the Ion Pumps is 4.21e-09 mBar

there are Currently 96 ion pumps in the Tunnels as seen by the PLC:

3 cannot properly communicate with the PLC

SA1_XTD9_VAC/IPUMP/P10510I

SA1_XTD9_VAC/IPUMP/P11130I

SA1_XTD9_VAC/IPUMP/P12120I

3 have an ambiguous control name:

SA1_XTD2_VAC
SA1_XTD9_VAC2
SA1_XTD9_VAC0
 

And 4 have no channel assigned in the Karabo inteface (CAS to solve this)

SA1_XTD2_VAC/IPUMP/P10340I
SA1_XTD2_VAC/IPUMP/P10350I
SA1_XTD9_VAC/IPUMP/P10370I
SA1_XTD2_VAC/IPUMP/P10360I

The remaining 86 replied and:

Average pressure is  4.210e-09 mBar

Maximum pressure is  2.60-08 mBar

Minimum pressure is  8.90e-10 mBar

  48   15 Feb 2017, 20:20 Alessandro SilenziGeneralFeedbackMotion loop status

The motion loop is as of 18:40 online.

the current status of the devices as seen by the Karabo is shown in the attachment:

In summary 63 devices (29 Motors):

18 in error

- 14 in error 0x8004 (Terminal unavailable)

- 4 in error 0x8003 (Terminal unavailable)

This is the list of motor that are behaving according to karabo

SA1_XTD2_MIRR-2/MOTOR/HMRZ Success State.OFF
SA1_XTD2_PSLIT/MOTOR/BLADE_RIGHT Success State.OFF
SA1_XTD2_IMGFEL/MOTOR/SCREEN Success State.OFF
SA1_XTD2_FLT/MOTOR/TARGET Success State.OFF
SA1_XTD2_MIRR-1/MOTOR/HMRZ Success State.OFF
SA1_XTD2_PSLIT/MOTOR/BLADE_LEFT Success State.OFF
SA1_XTD2_MIRR-1/MOTOR/HMTX Success State.OFF
SA1_XTD2_IMGSR/MOTOR/TARGET_X Success State.OFF
SA1_XTD2_MIRR-2/MOTOR/HMRX Success State.OFF
SA1_XTD2_IMGSR/MOTOR/IRIS Success State.OFF
SA1_XTD2_MIRR-1/MOTOR/HMRY Success State.OFF
SA1_XTD2_PSLIT/MOTOR/BLADE_BOTTOM Success State.OFF
SA1_XTD2_MIRR-2/MOTOR/HMRY Success State.OFF
SA1_XTD2_IMGSR/MOTOR/FOCUS Success State.OFF
SA1_XTD2_MIRR-2/MOTOR/HMTX Success State.OFF
SA1_XTD2_MIRR-1/MOTOR/HMTY Success State.OFF
SA1_XTD9_IMGPII45/MOTOR/SCREEN Success State.OFF
SA1_XTD2_MIRR-1/MOTOR/HMRX Success State.OFF
SA1_XTD2_PSLIT/MOTOR/BLADE_TOP Success State.OFF
SA1_XTD2_IMGPII45/MOTOR/SCREEN Success State.OFF
SA1_XTD2_IMGFEL/MOTOR/FILTER Success State.OFF
SA1_XTD2_MIRR-2/MOTOR/HMTY Success State.OFF
 

  49   17 Feb 2017, 09:56 Alessandro SilenziGeneralFeedbackMotion loop feedback

Quick feedback during the meeting:

- 63 Devices

- 29 Motors

Errors only in 

- SPB_XTD9_IMGPI

- FXE_XTD9_IMGPI

  78   16 Mar 2017, 13:34 Torben FalkGeneralFeedbackWiring status

Wiring status SASE 1:

Wiring progress:

  • Internal wiring of the XGM in XTD 9 is done.
  • Vacuum part wiring of the XGM in XTD 9 is done (ready for local Beckhoff test).
  • Gas Panel wiring of the XGM in XTD 9 is done.
  • Crate wiring (ADAM & Femto crate) of the XGM in XTD 9 is done.

Upcoming work XTD 2:

  • Serial connection from Beckhoff to TCP 350.
  • Change cold plug cables into halogenfree cables.

Upcoming work XTD 9:

  • INHIBIT connection Iseg HV crate.
  • Serial connection from MTCA to RVC 300.

Upcoming work XTD 10:

  • Vacuum part wiring of XGM.
  • Gas Panel wiring of XGM.
  • Internal wiring of XGM.
  • Installing ADAM & Femto crate.
  • Measure cable lengths for Imager and prepare cables.
  104   05 Apr 2017, 14:14 Andreas KochXTD9FeedbackPlease inform on rack status 1.18

The rack 1.18 in XTD9 is not operational at the moment because Nicola is working on it. Nerea, Tobias or others let me know when it is fully operational again. This avoids checking it in the tunnel. Alternatively, let me know if I can check remotely.

  118   07 Apr 2017, 17:43 Tobias FreyermuthGeneralFeedbackHotfix for all loops (VAC, MOV, EPS) deployed

Dear collogues,

 

all loops are up and running after deploying the hotfix.

 

Have a nice weekend,

    Tobias

  119   07 Apr 2017, 17:54 Tobias FreyermuthGeneralFeedbackHotfix for all loops (VAC, MOV, EPS) deployed

Tobias Freyermuth wrote:

Dear collogues,

 

all loops are up and running after deploying the hotfix.

 

Have a nice weekend,

    Tobias

 

 Confirmed from Karabo side.

  135   11 Apr 2017, 17:44 Raśl Villanueva-GuerreroXTD2FeedbackXTD2 Complete Gas Section (DPS-XGM-DPS) Isolation Interlock tested - SUCCESSFUL

 The interlock definition for complete isolation of the whole section based on high pressure signal has been successfully tested. 

DPS (Upstream and Downstream) are now fully "controlled" by Karabo.

XGM has been reported by J. Grünert that it will be re-integrated during the evening.

 

Still some problems to call the remote operation of the turbopumps from Karabo, but it doesn´t compromise any of the interlock definitions (only is troublesome if the one needs to work with the pump, for instance after the interlock has been triggered).

  136   11 Apr 2017, 18:29 Raśl Villanueva-GuerreroXTD2FeedbackFast Valve Test - SUCCESFUL

 The Fast Valve test has been positively tested. 

It has been consider that the signal on the EPS to open again, should be also available in the vacuum loop. Still this need to be further discussed.

 

 

  137   11 Apr 2017, 18:38 Raśl Villanueva-GuerreroXTD2FeedbackBeam Stopper and V0 valve test - SUCCESSFUL

 The Interlock conditions for these two components has been positively tested but not exhaustively done:

The triggering of both via the actuation on the Fast Valve----------------->DONE and OK

Their triggering via HV down of each of the 6 ion pumps------------------>Partially DONE and OK: Partially means that only one of the pumps randomly chosen has been deactivated. The agreement is that the other remaining 5 can be done later, also from the office since the correspondence between the devices and the physical components has been confirmed. 

Also, the individual actuation of both, Beam Stopper and V0 valve has been proof showing a consistent behaviour regarding the interlock definition.

Finally the XFEL Vacuum OK signal is available but AE is currently improving it. By the moment is not automatically sent to DESY, but instead it needs to be activated manually. According to AE feedback this should be corrected in the following days.

 

  145   13 Apr 2017, 16:21 Tobias FreyermuthGeneralFeedbackVAC loop up and running agian

The first EtherCAT coupler in 1.7 VAC was broken and is replaced now. The loop is up and running again.

Cheers,

    Tobias

  163   21 Apr 2017, 15:30 Tobias FreyermuthXTD9FeedbackSASE EPS RACK 1.14 connected

The EPS-loop is now complete again.

The interface from EPS to MPS is working now. One broken wire in the cable between EPS and MPS was found. We are using now other pairs for the signals "SA1_SYS_EPS2MPS/DCTRL/MODE1", "SA1_SYS_EPS2MPS/DCTRL/MODES" and "SA1_SYS_EPS2MPS/DCTRL/MODEM".

Cheers,

    Tobias

  179   26 Apr 2017, 19:21 Raśl Villanueva-GuerreroXTD9FeedbackXTD9 Complete Gas Section (DPS-XGM-DPS) Isolation Interlock tested - SUCCESFUL

 Dear all,

Finally the tests were run with the expected results: Pressure thresholds for the 3 involved gauges were forced on the system and the interlock on the two gate valves that limit the whole gas section were automatically closed in every case. Also the release switch was tested and the valves were able to be normally operated again.

However the interlock definition also involves the closing of the so-called "shut-off" valve in the gas injection line at the XGM. Unfortunately its behaviour couldn´t be completely observed since the Karabo device is not fully implemented. On the other hand, J. Grünert reported that after the interlock was triggered the valve was shown as also "interlocked" (despite the actual status, open or closed was not clear). This situation may require a second test, combined for instance with the gas injection test to be run by WP74 in the upcoming date). 

In any case the final results were rather positive. (despite there still some permanent uncertainty about devices being reachable or not through Karabo, as it has been previously reported).

 

Thanks to everyone involved.

 

Raúl Villanueva on behalf of B. Rio, N. Jardon and V. Bondar.

 

 

  204   03 May 2017, 14:38 Raśl Villanueva-GuerreroXTD9FeedbackGas Section Interlock on XTD9 - Shut off valve also operative

 Dear all,

during the test run today by our colleagues of WP74, the interlock condition inside the XGM module was met (small volume pressure burst up to 10-2 mbar range). Now we can see also the expected cut-off event of the gas injection (see attached pictured). It seems that the reason why there was any feedback from the respective shut-off valve was the solenoid actuator on the respective shut-off valve was set in manual mode.

This means that XTD9 Interlock for the whole gas section has been up and running as expected the whole time.

Best Regards.

  238   16 May 2017, 15:59 Andreas KochXTD2FeedbackRequest for imager checks

Since tomorrow there is no beam I want to use the time for some checks of the imagers in XTD2. Please, let the motion loop up if possible until 10 am, otherwise let me know.

  249   18 May 2017, 16:32 Andreas KochXTD2FeedbackImager status

After the update of the PLC firmware, the imagers are in following status:

SR: auto gain off seems to work, correct image, screens are out. Beamview just crashed, I asked Alessandro and Dennis to have a look.

Pop-In: Everything fine.

FEL: strange image. We had this before, no idea what the reason is. I will keep trying.

Another update of the motion loop is planned later. Contact Nerea for details.

  Draft   14 Sep 2018, 13:38 Adriano ViolanteXHEXP  